Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 1]

Kerala High Court

Messrs Bhima Jewels vs The Chief Engineer on 8 September, 2009

Author: S.Siri Jagan

Bench: S.Siri Jagan

       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 37150 of 2001(V)



1. MESSRS BHIMA JEWELS
                      ...  Petitioner

                        Vs

1. THE CHIEF ENGINEER, TVM
                       ...       Respondent

                For Petitioner  :SRI.P.R.VENKETESH

                For Respondent  :SRI.P.SANTHALINGAM, SC, KSEB

The Hon'ble MR. Justice S.SIRI JAGAN

 Dated :08/09/2009

 O R D E R
                              S. Siri Jagan, J.
               =-=-=-=-=-=-=-=--=-=-=-=-=-=-=-=-=-=
                         O.P. No. 37150 of 2001
               =-=-=-=-=-=-=-=-=--=-=-=-=-=-=-=-=-=
                 Dated this, the 8th September, 2009.

                             J U D G M E N T

The petitioner is a commercial consumer of electricity from the Kerala State Electricity Board. On 27-11-2000, the Assistant Executive Engineer of the High Tension Meter Testing Unit inspected the electrical installation of the petitioner and found that the P.T Unit installed in the petitioner's premises was faulty. By Ext. P1, the petitioner was directed to replace the P.T. Unit with a new one. The petitioner replaced the same on 12-12-2000. Thereafter, the petitioner was served with Ext. P4 bill for arrears of electricity charges for the period from 2/1999 onwards. The petitioner filed an original petition against that demand, which was disposed of by Ext. P5 judgment permitting the petitioner to file an appeal. The petitioner's appeal was rejected by Ext. P7 order. The petitioner is challenging Exts.P4 and P7 in this original petition.

2. The contention of the petitioner is that without referring the dispute regarding fault in the meter to the Electrical Inspector as required under Section 26(6) of the Indian Electricity Act, the respondents cannot recover arrears of electricity charges from the petitioner. The petitioner contends that the meter was recording the correct consumption. It is further contended that even assuming that arrears can be recovered, that can only be for the period of six months prior to the date of detecting fault in the meter.

3. A statement has been filed on behalf of the respondents, in which they would take the contention that insofar as the petitioner never sought reference of the dispute regarding the meter to the Electrical Inspector and they acknowledged the fact that the meter is faulty by replacing the P.T Unit by themselves. Therefore, they cannot now contend that they are not liable to pay arrears of electricity charges for the period when on account of the fault in the O.P. No. 37150/2001 -: 2 :- P.T Unit, the meter was not recording the correct consumption of electricity. They would further contend that as is clear from the petitioner's pattern of consumption of electricity, it is abundantly clear that the reading drastically came down in February, 1999 and again drastically increased after the P.T Unit was re-commissioned on 9-1-2001. They have produced Ext. R1(a) statement regarding the consumption of electrical energy by the petitioner every month from March, 1998 onwards till December, 2001. The respondents would, therefore, contend that the petitioner is liable to pay the arrears of electricity charges.

4. I have considered the rival contentions in detail.

5. It is not as if the petitioner was not aware of the fact that according to the respondents the meter was faulty. In fact, when by Ext. P1 the petitioner was directed to change the P.T Unit on the ground that it is faulty, without any objection, the petitioner replaced the P.T Unit. If the petitioner had a contention that the P.T Unit was not faulty, the petitioner would certainly have disputed Ext. P1, instead of replacing the P.T Unit in accordance with the directions in Ext. P1. Therefore, the petitioner was aware of the fact that recording of electrical energy in the petitioner's premises was not correct. If the petitioner had any dispute regarding that fact, it was perfectly open to the petitioner to seek a reference of the matter to the Electrical Inspector under Section 26(6) of the Act before changing the P.T Unit. By changing the P.T Unit by themselves, the petitioner themselves made it impossible to get the matter referred to the Electrical Inspector. That being so, the petitioner cannot now contend that no arrears can be recovered from the petitioner without referring the matter to the Electrical Inspector.

6. The pattern of consumption of electrical energy by the O.P. No. 37150/2001 -: 3 :- petitioner is given in Ext. R1(a), which corresponds to the readings given by the petitioner in the original petition itself up to 13-12-2000. Ext. R1(a) reads thus:

----------------------------------------------------------------------------
             MONTH                             UNITS
                                            CONSUMED
----------------------------------------------------------------------------
             3/98                              14672

             4/98                              14796

             5/98                              15584

             6/98                              13607

             7/98                              15313

             8/98                              16552

             9/98                              14946

             10/98                             17816

             11/98                             16748

             12/98                             15900

             1/99                              16988

             2/99                                9288

             3/99                                9972

             4/99                                9352

             5/99                                8444

             6/99                                7952

             7/99                                7668

             8/99                                9504

             9/99                                6452

             10/99                               7632

             11/99                               8276

             12/99                               9256

O.P. No. 37150/2001            -: 4 :-

             1/2000                9620

             2/2000                7844

             3/2000                8860

             4/2000              11292

             5/2000              12392

             6/2000                9212

             7/2000                8708

             8/2000                8628

             9/2000                8996

             10/2000               8592

             11/2000             PT dismantled for
                                 repairs on 27-11-2000

             12/2000             P T recommissioned
                                 on 9-1-2001

             1/2001              10056 units from 9.1.2001

                                 to 31.1.2001.

             2/2001              14496

             3/2001              13436

             4/2001              19212

             5/2001              19020

             6/2001              14152

             7/2001              14512

             8/2001              19696

             9/2001              14980

             10/2001             14764

             11/2001             15248

             12/2001             14884


From the same, it is for anybody to see that up to January, 1999, the consumption of electrical energy by the petitioner was between 14000 O.P. No. 37150/2001 -: 5 :- and 17000 units. In February,1999, the same drastically came down to 9288. Thereafter, it ranged between 6452 to 9972 until January, 2001, except for two months in April and May, 2000 in which months, the consumption was 11292 and 12390. Again, after the P.T Unit was recommissioned on 9-1-2001, from January 2001 onwards, it suddenly increased to 10056 units and thereafter ranged between 19696 and 14152. The petitioner does not dispute the readings given in Ext. R1(a). Therefore, that evidence is clear to the effect that during February 1999 to November,2000, the meter was really faulty. I am of opinion that, therefore, the petitioner is liable to pay the difference in electricity charges for that period.

7. Of course, the petitioner would strenuously contend that in view of the Supreme Court decisions on the subject (see Belwal Spinning Mills Ltd. v. U.P. State Electricity Board and others, AIR 1977 SC 2793 and M.P.E.B. & others v. Smt. Basantibai, AIR 1998 SC 71), the respondents cannot demand arrears of electricity charges without referring the dispute to the Electrical Inspector. I am of opinion that the ratio of those decisions cannot be applied to the present case insofar as in this case, the petitioner did not raise a dispute regarding the fault in the meter at all. On the other hand, as directed in Ext. P1, the petitioner readily replaced the P.T Unit by a new one, which would go to show that the petitioner was satisfied that the meter was in fact faulty. The decisions referred can be applied only in cases where the consumer had, in fact, a dispute regarding the fault in the meter. When the consumer himself did not have a dispute regarding the fault in the meter, the ratio of that decision cannot be applied. Further, it is not the respondents who made the reference to the Electrical Inspector, but the petitioner themselves. The procedure prescribed in Section 26(6) is applicable O.P. No. 37150/2001 -: 6 :- only when there is a dispute as to whether the meter is faulty or not. In any event, in view of my above findings, there cannot be absolutely any doubt whatsoever that the meter was faulty for the period between February, 1999 to November, 2000.

8. But, I am not inclined to accept the method of calculation of arrears adopted by the respondents in the matter. In the peculiar circumstances of the case, I am of opinion that the arrears should be computed on the basis of the average consumption for the period from April, 1998 to January, 1999 for calculating arrears for the period from February, 1999 to November, 2000. Fresh demand for arrears, as calculated above, shall be issued to the petitioner expeditiously, on receipt of which the petitioner shall pay the same after adjusting the amounts already paid, in ten equal monthly instalments along with the monthly bills.

The original petition is disposed of as above.

Sd/- S. Siri Jagan, Judge.

Tds/