Delhi High Court - Orders
Skyline Engineering Contracts (India) ... vs Orchid Infrastructure Developers ... on 8 August, 2025
Author: Jyoti Singh
Bench: Jyoti Singh
$~67
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(MISC.)(COMM.) 614/2025
SKYLINE ENGINEERING CONTRACTS (INDIA) PRIVATE
LIMITED ....Petitioner
Through: Mr. Divyanshu Singh, Advocate.
versus
ORCHID INFRASTRUCTURE DEVELOPERS PRIVATE
LIMITED .....Respondent
Through: Mr. Ninad Dogra, Advocate.
CORAM:
HON'BLE MS. JUSTICE JYOTI SINGH
ORDER
% 08.08.2025 I.A. 19303/2025 (Exemption)
1. Allowed, subject to all just exceptions.
2. Application stands disposed of.
I.A. 19304/2025 (u/S 151 of CPC)
3. This application is filed on behalf of the Petitioner seeking condonation of delay of 18 days in re-filing the petition.
4. Issue notice.
5. Mr. Ninad Dogra, learned counsel accepts notice on behalf of the Respondent.
6. For the reasons stated in the application, the same is allowed. Delay of 18 days in re-filing the petition stands condoned.
7. Application stands disposed of.
O.M.P.(MISC.)(COMM.) 614/2025 Page 1 of 2This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/08/2025 at 22:27:55 O.M.P.(MISC.)(COMM.) 614/2025
8. This petition is filed on behalf of the Petitioner under Section 29A (4) and (5) of the Arbitration and Conciliation Act, 1996 ('1996 Act') seeking extension of the mandate of the learned Sole Arbitrator by a period of 12 months.
9. Disputes having arisen between the parties in relation to Contract dated 09.03.2010, Petitioner filed a petition under Section 11(6) of 1996 Act in this Court being ARB.P. 130/2017, which was allowed on 09.04.2017 appointing a Sole Arbitrator. From time to time, mandate of the Arbitrator was extended and lastly upto 31.03.2025. It is stated in the petition that arbitral proceedings are at the stage of cross-examination of Respondent's witness.
10. Issue notice.
11. Mr. Ninad Dogra, learned counsel accepts notice on behalf of the Respondent and on instructions, submits that Respondent has no objection to the extension of mandate of the Arbitrator, however, a direction be issued to the learned Arbitrator to expedite the proceedings since arbitration has been unduly prolonged.
12. With the consent of the parties, mandate of the Arbitrator is extended by a period of 06 months from 08.08.2025 and period between 01.04.2025 to 07.08.2025 is regularized. Learned Arbitrator is requested to make every endeavour to conclude the proceedings as expeditiously as possible.
13. Petition is allowed and disposed of in the aforesaid terms.
JYOTI SINGH, J AUGUST 8, 2025/S.Sharma/shivam O.M.P.(MISC.)(COMM.) 614/2025 Page 2 of 2 This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/08/2025 at 22:27:55