Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Entire Act]

State of Gujarat - Section

Section 4 in Gujarat Electricity Regulatory Commission (Licensee's Power to Recover Expenditure incurred in providing supply and other Miscellaneous Charges) Regulations, 2005

4. Provision for low tension Supply.

- 4.1 In case of applications for Low Tension supply, where such supply requires only laying the service line from the existing distributing main to the consumer's premises, the Distribution licensee shall estimate the cost of service line and the cost of terminal and metering arrangements at the premises of the consumer, but not including the cost of meter. The estimate of the cost of electric line, electrical plants and metering arrangements shall be based on the latest cost data as published by the Distribution Licensee.In respect of above consumers the Distribution Licensee may dispense with the process of preparation of detailed individual estimate and instead charge on the basis of per KW of contracted load and per Meter rate. Although, it will not prepare individual estimate, the Distribution Licensee shall maintain the cost incurred in respect of such categories of the consumers who are provided with electricity only through extension of service line (with out undertaking any of the work like DTR or laying of HT line). The average cost incurred (according to the latest cost data as published by the Distribution Licensee) shall be used as the yard stick for determining the per kW cost of these categories of consumers.
4.2
(i)In cases of applications where there is a need to erect new electrical plant such as distribution transformer (DTR) along with switch-gear etc., for extending supply to the applicant for Low Tension connection, the licensee shall estimate the cost of electrical plant as follows:
Cost of the works of erection of DTR including switchgear(in Rupees) = PRated capacity of DTR in KVA = QCost per KVA (in Rupees) = P/QContracted load in KVA of the applicant = KAmount payable by applicant towards electrical plant (in Rupees)= K*(P/Q)In cases of applications when the capacity of existing electrical plant (such as DTR and switchgear etc.) is require to be augmented, the differential cost of existing and new such electrical plant will form the basis of calculation of pro-rata charges.In all cases the estimate of the cost of electrical plant shall be based on the latest cost data as published by the Distribution licensee.
4.2
(ii)In cases of applications which besides erection of electrical plant (such as DTR and switchgear etc.), need laying or extension of the HT line for providing supply to the applicant, the estimate of the cost of such section of HT line shall be made on a per kilometer basis based on the latest cost data as published by the Distribution Licensee.
The Distribution Licensee shall recover the cost, as mentioned in the sub-clause 4.2(i) and 4.2(ii), from all the applicants excluding following categories:a. Agricultural consumers with the exception of Agricultural connection to be given under special schemes like "Tatkal Scheme" which may be brought out in future.b. Water Works and Sewerage Pumps operated by/for any local authority other than Municipal Corporation.c. Domestic consumersd. Commercial consumers up to 100 KVA/125 HP of contract demandChapter - V