[Cites 0, Cited by 0] [Section 18] [Entire Act]

State of Tamilnadu - Subsection

Section 18(6) in Tamil Nadu Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005

(6)Scrutiny of the project cost estimates by the Commission shall be limited to the reasonableness of the capital cost, financing plan, interest during construction stage, use of efficient technology and such other matters, for determination of tariff. In respect of capital cost based projects, a 50% of potential savings, if any, in interest during construction, due to completion of project ahead of schedule, may be allowed to be retained by the Generating Company / licensee and the balance 50% passed on as a lower tariff.