State of Gujarat - Section
Section 8 in Gujarat Electricity Regulatory Commission (Licensee's Power to Recover Expenditure incurred in providing supply and other Miscellaneous Charges) Regulations, 2005
8. Miscellaneous Charges.
- (i) Subject to the provisions of the Act and these Regulations and subject to such directions, orders or guidelines the Commission may issue from time to time, every Distribution Licensee is authorized to recover any expenses to be borne by the Distribution Licensee in rendering following services to new or existing consumers.(ii)All the charges proposed below in 8.1 and 8.2 are payable in advance.| Sr. No. | Particulars | Charges |
| i | Single phase supply for Residential. | Rs.40.00 |
| ii | Three phase supply for Residential. | Rs.100.00 |
| iii | Single phase supply and Three phase supply forcommercial | Rs.100.00 |
| iv | Three phase supply for LT Agricultural | Rs.200.00 |
| v | Three phase supply for LT Industrial | Rs.400.00 |
| vi | HT and EHT supply (Applicable to demand appliedfor) | Rs.10 per KVA with a ceiling of Rs.25000.00 |
| vii | All other Categories not enumerated above | Rs.100.00 |
| Sr. No. | Particulars | Charges |
| (i) | LT services | Rs. 20/- |
| (ii) | HT and EHT services | Rs. 200/- |
| (i) | The test and inspection prior to connection of an installation for permanent supply shall be carried out free of charge but should further test and inspection be found necessary, the charge for such test and/or inspection shall be | Rs. 50/- |
| (ii) | Charges for the initial inspection and subsequent test and connection of a temporary installation | Rs. 100/- |
| Sr. No. | Particulars | Charges |
| i | Single phase supply for Residential. | Rs.40.00 |
| ii | Three phase supply for Residential. | Rs.100.00 |
| iii | Single phase supply and Three phase supply forcommercial | Rs.100.00 |
| iv | Three phase supply for LT Agricultural | Rs.200.00 |
| v | Three phase supply for LT Industrial | Rs.400.00 |
| vi | HT and EHT supply (Applicable to demand appliedfor) | Rs.10 per KVA with a ceiling of Rs. 25000.00 |
| vii | All other Categories not enumerated above | Rs.100.00 |
| viii | Reduction in demand of HT and EHT supply | Rs. 10 per KVA (Applicable to quantum of demand reduced) with a ceiling of Rs.2000 |
| Sr. No. | Particulars | Charges |
| i | Single phase supply for Residential. | Rs.20.00 |
| ii | Single phase supply for commercial and Threephase supply for Residential | Rs.100.00 |
| iii | Three phase supply for LT Agricultural | Rs.300.00 |
| iv | Three phase supply for LT Industrial and others | Rs.400.00 |
| v | HT and EHT supply | Rs.2000.00 |
| Sr No. | Particulars | Charges |
| i | Residential | Rs. 100.00 |
| ii | Commercial | Rs. 200.00 |
| iii | LT Agricultural | Rs. 200.00 |
| iv | LT Industrial & others | Rs. 900.00 |
| v | HT and EHT supply | Rs. 3200.00 |
| Sr. No. | Particulars | Charges |
| i | Residential | 50.00 |
| ii | Commercial | 100.00 |
| iii | LT Agricultural | 100.00 |
| iv | LT Industrial & others | 500.00 |
| v | HT and EHT supply | 1500.00 |
| Sr. No. | Particulars | Charges |
| 1. | Hire of single-phase meter | Rs. 10/- per meter/ month. |
| 2. | Hire of Three phase meter | Rs. 30/- per meter/ month |
| 3. | Hire of demand meter or special type of meterfor LT consumer | Rs. 225/- per meter/ month. |
| 4. | Hire of time switch with or without KWH meter | Rs. 225/- per time switch /month. |
| 5. | Hire of HT/EHT metering equipments | Rs. 750/- per meter/ month. |
| Sr. No | Particulars | Charges |
| 1 | Hire of single-phase meter | Rs. 15/- per meter/ month. |
| 2 | Hire of poly phase meter (3 phase) | Rs. 60/- per meter/ month |
| 3 | Hire of HT/EHT metering equipments | Rs.1500/- per meter/ month. |
| Particulars | Charges |
| (a) Charges for attendance of fuseman where thefailure of supply is due to a fault in the consumer'sinstallation | (1) For Low Tensionconsumers Rs. 10/-(2) For High Tension consumers Rs. 10/- forreplacement of fuse on single phase. Rs. 15/- for replacement offuse on two phases. Rs.20/- for replacement of fuse on threephases. |
| (b) Charges for attendance of fuseman atconsumer's premises during any function: (per person per shift) | Rs. 500/- |
| (c) Charges for resealing of seals other thanmeter seals which have been disturbed unauthorizedly Rs. 100/- | |
| (d) Charges forresealing of meter seals, disturbed Unauthourizedly(i) In case of residential service(ii) In case of service other than residential | Rs. 50/-Rs. 200/- |
| (e) Changing or moving a meter board | Actual cost plus 15% |
| (f) Testing meter(alltype of meters), if it should be proved to be correct within thelimits laid down by the Standards/Rules(i) Single phase meter(ii) Three phase meter(iii) Maximum Demand meter (LT)(iv) Maximum Demand meter (HT/EHT) | Rs.100/-Rs.300/-Rs.500/-Rs.1000/- |
| Note.- The supplier shall not accept anyresponsibility whatsoever for the satisfactory and correctrunning of the consumer's meter after he has taken deliverythereof subsequent to the test. | |
| (g) Installing a meter for each other class ofsupply required after the initial connection of the installationfor any other purpose or changing a meter for one of a differentsize when necessitated by a change in consumer's demand (the feedoes not include the provision of a meter board) per meter | Rs. 100/- |
| (h) CT/PT Testingcharges(i) CT Testing (LT)(ii) CT/PT unit (HT/EHT) | Rs. 100/-Rs. 100/-Rs. 500/- |