Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 5, Cited by 0]

Bangalore District Court

/ M/S.Kalyani Steels Ltd vs ) Mysore Minerals Limited on 10 January, 2020

     IN THE COURT OF THE VI ADDL. CITY CIVIL & SESSIONS JUDGE
                   AT BENGALURU CITY
                        (CCCH.11)


           Dated this the 10th day of January, 2020

            PRESENT: Sri. Rama Naik, B.Com., LL.B.,
                     VI Addl.City Civil & Sessions Judge,
                     Bengaluru City.


                       A.S.NO:71/2014
                            And
                       A.S.NO: 89/2014


PLAINTIFF /             M/S.KALYANI STEELS LTD
APPLICANT             : Having its registered Office at
[In AS.71/2014]         Corporate Building, 2nd Floor,
                        Mundhwa, Pune - 411 036.
[Claimant before        Reptd.by its Seniro Legal Manager-
 Arbitral Tribunal]     Sri.Anand Shirsat.



                               /Vs/

DEFENDANTS            :1) MYSORE MINERALS LIMITED
RESPONDENT                A Government of Karnataka Undertaking
[In AS.71/2014]           Having its Registered Office
[Respondent before        at 39, Mahatma Gandhi Road,
 Arbitral Tribunal]       Bengaluru -560 061.

                       2) JUSTICE SHIVARAJ V PATIL
                          (Former Judge - Supreme Court of India)
                          No.254, Spursh, 18 th Cross,
                          Sadashivanagar, Bengaluru.
                                                             AS.71/2014
                                                                 &
                                                            AS.89/2014
                                     2


PLAINTIFF              :     MYSORE MINERALS LIMITED
APPLICANT                    A Government of Karnataka Undertaking
[In AS.89/2014]              Registered under the Companies Act, 1956
                             Having its Registered Office
[Respondent before           at No.39, Mahatma Gandhi Road,
Arbitral Tribunal]           Bengaluru -560 061.


                              /Vs/

DEFENDANTS/            :   1) M/S.KALYANI STEEL LIMITED,
RESPONDENTS                   Having its registered Office at
[In AS.89/2014]               Corporate Building, 2nd Floor,
[Claimant before              Mundhwa, Pune - 411 036.
 Arbitral Tribunal]
                           2) Shri.Hon'ble Justice Shivaraj V.Patil
                              Former Judge, Supreme Court of India,
                              Sole Arbitrator, Home/Office at No.254,
                               'Sparsh', 18th Cross,
                              Sadashivanagar, Bengaluru -560 080.

                                     --


                      COMMON JUDGMENT

            Plaintiffs have filed these suits under Section

    34 of the Arbitration and Conciliation Act, 1996, for

    setting aside the award dated 28.02.2014 passed

    by learned Arbitrator.



    2)      As both these suits are arising out of single

    award     dated   28.02.2014          passed   by   learned

    Arbitrator, for the convenience of the Court, both
                                                     AS.71/2014
                                                         &
                                                    AS.89/2014
                             3


these suits are taken together for passing common

judgment.



3)    Plaintiff's [Claimant in arbitral proceedings]

case in AS.No.71/2014 is that, Claimant and one

M/s.Mukand Ltd., had jointly obtained the approval

of the State Government for setting up a Steel Plant

in the industrially backward area of Koppal for

manufacture of special alloy steel blooms, billets

and   rounds   and   the   plant   was   set   up   and

commissioned in 1998. Basic raw material required

was iron ore and initially the same was met by

purchases from various mines situated in and

around Hospet, Sandur Region. Respondent is a

State Government Undertaking incorporated under

the provisions of the Companies Act, 1956 and had

applied for Mining Lease of Subbarayanahalli Iron

Ore Mines [for brevity 'SIOM']. Respondent was

under threat of winding up due to severe financial

crunch, labour problems and unrest. To overcome
                                                                AS.71/2014
                                                                    &
                                                               AS.89/2014
                                   4


the same, it floated a public tender to commercially

exploit the mines by way of joint venture with a

private     participation    to    augment       its    financial

resources. Joint offer of Claimant and M/s.Mukand

Ltd., were short listed and was accepted by

Respondent for commercially exploiting mines. Said

proposal was also approved by State Government,

pursuant to which, Claimant                 and Respondent

entered       into     Marketing         Agreement         dated

17.01.2002.     Originally, this was entered into with

M/s.Kalyani Ferrous Industries Ltd., for a period of

20 years on such terms and conditions, which was

later amalgamated with Respondent by an order of

the High Court of Bombay dated 18.01.2004.

Pursuant to such amalgamation, the name of

M/s.Kalyani Ferrous Industries Ltd was replaced with

that   of    Respondent.      Respondent         entered       into

Raising     Agreement       with       M/s.Mukand      Ltd.,    for

extraction     of    iron   ore    from    the    mines,       and
                                                               AS.71/2014
                                                                   &
                                                              AS.89/2014
                                   5


excavated Ore from the said mines and sold to

Claimant.



4)      It is stated that, as per the terms of

agreement, Claimant paid a sum of Rs.6 Crores as

Sales     Advance.     Claimant         was     the    exclusive

purchaser of all the Iron Ore that was to be

extracted by Respondent by itself or through its

raising   contractor    for    a       period   of    20   years.

Respondent was selling calibrated iron ore at

Rs.150/ to Rs.175/- per MT and that Raising cost

was in the region of Rs.300/- PMT to Rs.350/- PMT

during the period prior to entering into Marketing

Agreement.      Under the Agreement, the parties

agreed to the prices of calibrated iron ore sold to

Claimant at Rs.250/- PMT taking into account the

difference between the comparable MMTC price

which was Rs.272.03.          This price was fixed for an

initial period of three years and the agreement

provided for revision in the marketing rate on 1 st
                                                               AS.71/2014
                                                                   &
                                                              AS.89/2014
                                 6


April every year taking into consideration the

revision in prices by MMTC.



5)    It is stated that, as per agreement, initial

period expired on 31.03.2005 and revision in

marketing rate as per agreement became due on

01.04.2005. Marketing rate was fixed at Rs.314/-

PMT pursuant to discussions and exchange of letter.

'Marketing rate', which was to be revised, taking

into consideration the prices of MMTC, was fixed at

Rs.314/- PMT for calibrated iron ore and 'marketing

rate' was fixed on the basis of understanding of the

parties   of     sharing    the        difference       between

comparable MMTC price as on 31.03.2005, which

was   Rs.440/-    PMT      and       'raising   rate'    as   on

31.03.2005, which was Rs.188/- PMT. Price revision

took into consideration the fact that 20% of the

difference between the comparable MMTC price and

the raising rate was to be given to the Raising

Agent. In addition to the price revision, keeping in
                                                     AS.71/2014
                                                         &
                                                    AS.89/2014
                             7


mind the spirit of long term venture and mutual

understanding of sharing the benefits of project, the

Claimant agreed to bear 50% of statutory dues

payable    to   Government   including    afforestation

charges, lease rent, forest corpus fund, fire zone

payment, etc., as raised by Government from time

to time, though such sharing was not provided in

the original 'Marketing Agreement'.



6)    It   is   stated   that,   though      'Marketing

Agreement' provided for revision in prices every

year, in order to protect the parties from the risk of

fluctuation, parties agreed to keep the 'marketing

rate' agreed in 2005 would remain constant for a

period of two years, i.e. till 31.03.2007.    Claimant

understood that it was agreed between M/s.Mukand

Limited and Respondent that 'raising rate' fixed in

the year 2005 would also be kept constant for a

period of two years i.e. upto 31.03.2007.        There

were several letters exchanged between the parties
                                                     AS.71/2014
                                                         &
                                                    AS.89/2014
                               8


which made clear that parties had clearly agreed

that the rate so fixed on 01.04.2005 is valid upto

31.03.2007. However, on 12.04.2006, at a belated

stage, Plaintiff wrote to the effect that there is a

'printing error' in earlier letters and that marketing

rate is valid only for a period of one year i.e. upto

31.03.2006 and marketing price effective from

01.04.2006 will be intimated immediately. Claimant

protested the same and further did not intimate the

so called marketing price effective from 01.04.2006

till raising of Debit Notes dated 28.03.2007 and

30.03.2007        for        Rs.23,65,95,929/-     and

Rs.33,06,78,120/-.      Claimant replied to the effect

that the prices fixed on 01.04.2005 was agreed to

be valid for a period of two years up to March, 2007

and hence disputed the debit notes and invoked the

provision for resolutions of dispute by way of

arbitration and    parties    agreed   to   resolve the

disputes through arbitration.      During pendency of
                                                 AS.71/2014
                                                     &
                                                AS.89/2014
                           9


arbitration, revision for the year 2008 and 2009

became due.     Pursuant to direction of learned

Arbitrator, Claimant filed its additional claim on

08.03.2001 along with certain documents.



7)    It is stated that, 2nd Defendant passed an

award on 28.02.2014, holding that, price revision

which was fixed on 01.04.2005 was only for a period

of one year and was not valid for two years as

contended by Claimant.    Further, it is held that,

Claimant has failed to prove that existence and

understanding of parties to equally share the risk

and benefits of business and consequently price

cannot be determined on the basis of Annexure 'C-

19' (exhibit C-23). Learned Arbitrator further held

that, price so fixed on 01.04.2005 is valid for the

complete year and consequently the debit notes

were held to be not valid and unenforceable;

however, directed Claimant to produce inputs to
                                                        AS.71/2014
                                                            &
                                                       AS.89/2014
                                 10


Respondent within two weeks for fixation of price

for the years 2006-07 and 2007-08. On additional

issue, learned Arbitrator rejected contention of

Claimant that since there is no revision in prices of

MMTC, the price for 2008-09 should be re-fixed at

the same rate as was for previous year and held

that since Claimant has not disputed the rates

arrived at by Respondent, proceed to fix the price of

Rs.1900/-    PMT     for   the   period   01.04.2008    to

31.03.2009.      Being      aggrieved,    Claimant     has

challenged the impugned award on the following

among other grounds.

       (a)     Learned Arbitrator erred in holding
       that prices fixed on 01.04.2005 was not
       valid    up   to    31.03.2007.    Based   on
       doctrine of Indoor Management, which
       was not pleaded by Respondent given a
       finding that price fixed on 01.04.2005
       was only for one year. Thus finding is
       contrary to the admitted records and
       correspondence between the parties.
                                                 AS.71/2014
                                                     &
                                                AS.89/2014
                     11


(b)   Finding on issue as to whether or
not the price agreed to between the
marketing parties is firm for the period
of two years (2005-06 and 2006-07) or is
it only for one year (2005-06) is wholly
contrary to the admitted pleadings and
evidence     on    record     calling     for
interference by this Court under Section
34 of the Act.


(c)   In the face of copious documents
and unimpeachable evidence to show
that selling price is firm for a period of
two years coupled with fact that there is
no plea on behalf of Respondent, much
less, any evidence to the effect that
price shall be firm for a period of one
year, learned Arbitrator erred in holding
that price was fixed for only one year as
the correspondence was on the condition
that ratification by Board is required.


(d)   Only contention raised in the entire
correspondence between the parties on
the question of price being firm for a
period of two years, is not applicable is
                                                   AS.71/2014
                                                       &
                                                  AS.89/2014
                      12


that, it is a printing error. Plea that there
is a printing error is also given up at the
time      of   arguments,        under     such
circumstances, giving a finding based on
no plea or evidence is wholly outside the
scope and beyond jurisdiction of learned
Arbitrator.


(e)     In letters dated 15.07.2005 and
11.08.2005, sharing of certain statutory
dues in the form of NPV, Forest Lease
Rent,     Afforestation     charges,     Forest
Corpus Fund, Fire zone payment, etc.,
was discussed and it was stated that
modification in respect of that aspect will
be incorporated in the agreement after
ratification by the Board of Respondent.
In the same letter, it is stated that
pursuant       to   several       rounds     of
discussions, prices are revised which
agreed price to be valid till 31.03.2007,
which     is   admitted     by    Respondent.
Hence, learned Arbitrator        has erred in
holding that price fixed from 01.04.2005
is valid till 31.03.2006.
                                                      AS.71/2014
                                                          &
                                                     AS.89/2014
                           13


(f)    So    called       ratification   is   only
referable to the statutory prices likely to
be raised by Government being alien to
the Contract needed modification by
incorporation       in    the    agreement     on
ratification by the Board.


(g)    This aspect gains further strength
from        their        subsequent      conduct
expressed through their letters dated
12.04.2006 when the second year had
already commenced from 01.04.2006,
wherein it is stated in no unmistakable
terms that the price payable was only up
to 31.03.2006 and not till 31.03.2007 as
the same appears a printing error.


(h)    There is no issue framed with
respect to the dispute relating to board
ratification. Learned Arbitrator assumes
this power and traverses beyond the
scope of reference.


(i)    Main dispute referred to learned
Arbitrator by the parties, being fixation
of price based on evidence and inputs
                                                        AS.71/2014
                                                            &
                                                       AS.89/2014
                          14


furnished by both the parties, learned
Arbitrator having found that Debit Notes
issued by Respondent is unsustainable
and having held that Respondent is not
entitled    to    the     same,        instead    of
answering the reference, in favour of
Claimant,      relegated       the     parties    to
resolve    the    dispute      by    making      the
Claimant       submit     to     the     unilateral
decision of Respondent for fixing the
price by further directing the Claimant to
submit its       inputs. This        approach     of
learned Arbitrator amounts to failure to
decide the reference sought for by the
parties        making          the      arbitration
proceedings futile and redundant.


(j)   Findings given by learned Arbitrator
is based on defense which are not urged
by Respondent and, hence resulted in an
award      dealing      with    a    dispute     not
contemplated by and not falling within
the   terms       of     submission       to     the
arbitration.
                                                     AS.71/2014
                                                         &
                                                    AS.89/2014
                             15


      For all these reasons, Claimant prays for

setting aside the award.



8)    Plaintiff's      [Respondent     in     arbitral

proceedings]    case    in   AS.No.89/2014   is   that,

impugned award is one sided and is passed

without appreciation of facts and documents,

hence, not sustainable in law.       Respondent has

challenged the award on the following grounds :

      a)    Guidelines made at para 14.17 is
      not correct and correct method of fixing
      the prices of marketing Iron Ore is
      Schedule 'D' of the marketing agreement
      and Ex.R.8 to R.14. Guidelines given for
      fixing the prices of marketing iron ore
      based on para 14.18 is not correct,
      discussion in this para based on Ex.C20
      and examination of CW.1 is not correct.
      Deductions for arriving at ex pit head
      price of iron ore fines i.e. Transportation
      charges, royalty, cess, forest permits
      charges, loading charges, moisture and
      terminal handling charges has already
                                                     AS.71/2014
                                                         &
                                                    AS.89/2014
                        16


been considered, therefore, once again
taking into consideration does not arise,
therefore, understanding of Ex.C1 is not
proper and guide made in the said para is
not sustainable.


b)      Guidelines made at para 14.19 is
totally   misunderstanding     of    para-5    of
Marketing Agreement. Clause 5 of Raising
Agreement       dated   17.01.2002    has     not
given     the   meaning      that    prices    of
marketing of iron ore be fixed based on
MMTC      procurements       and    based     on
variation in four parameters of Schedule
'D', therefore, guideline at Para 14.19 is
not correct and is against the Raising
Agreement, procedure and law.


c)      Guidelines at para 14.20 is not
correct and is illegal and bad in the
interest of Respondent. Further, guidelines
made at para 14.21 and 14.22 is not
correct and the relief claimed by Claimant
is not sustainable in the eye of law,
therefore, allowing arbitration claim partly
and imposing time for consideration and
                                                    AS.71/2014
                                                        &
                                                   AS.89/2014
                             17


     fixing the revised rate of marketing does
     not arise.
      For all these reasons, Respondent prays for

setting aside the award.


9)    Claimant,   in   its   written   statement   to

A.S.No.89/2014, has contended that, Respondent

has not at all averred any ground enshrined under

Section 34 of the Arbitration and Conciliation Act,

the application under said provision ought to be

restricted to grounds that are mentioned under the

said provision itself. Respondent has averred vague

grounds which would amount to re-appreciating

the facts and evidence before this Court. Said

provision mandates that, application is permissible

only on the grounds available under Section 34(2)

and this Court cannot sit in appeal on the award

rendered by learned Arbitrator, hence, prays for

dismissal of suit filed by Respondent.
                                                       AS.71/2014
                                                           &
                                                      AS.89/2014
                                18


10)     Heard. Perused the pleadings and records

placed in these suits.



11)     Points that arise for my consideration are:

        (1)    Whether Plaintiffs have made out
               any of the grounds as enumerated
               in Section 34 of the Arbitration and
               Conciliation Act, 1996 to set aside
               the   award,    dated    28.02.2014
               passed by learned Arbitrator?

        (2) What order?




12)     My answer to the above points are :

               Point No.1 - In the Negative;

               Point No.2 - As per final order, for
                            the following :



                      REASONS

13)     Point No.1 :        Being    aggrieved   by   the

arbitral award, dated 28.02.2014, both Claimant

and Respondent have filed these suits for setting

aside    the     arbitral   award    dated   28.02.2014,

whereby, learned Arbitrator was pleased to allow
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                              19


the claim petition in part filed by Claimant, directing

Respondent     to   determine      and   re-fix   the   rate

payable by Claimant effective from 01.04.2006,

based on the MMTC procurement price prevailing on

31.03.2006, in accordance with and in the light of

paragraphs 14.17 to 14.22 of the award and to

modify Ex.C.12 and Ex.C.14, Debit Notes dated

28.03.2017 and to determine and re-fix the rate

payable by Claimant effective from 01.04.2007,

based on the MMTC procurement price prevailing on

31.03.2007, in accordance with and in the light of

paragraphs 14.17 to 14.22 of the award.



14)    Claimant contends that learned Arbitrator

erred in holding that prices fixed on 01.04.2005 was

not   valid   up    to   31.03.2007.     Documents      and

unimpeachable evidence go to show that the selling

price is firm for a period of two years, however,

learned Arbitrator has held that price was fixed for
                                                    AS.71/2014
                                                        &
                                                   AS.89/2014
                           20


only one year. Findings based on no plea or

evidence and are outside the scope and beyond

jurisdiction of learned Arbitrator. Said aspect gains

further strength from letter dated 12.04.2006 at

Ex.C.7, wherein, it is stated that price payable was

only up to 31.03.2006 and not till 31.03.2017 as the

same appears a printing error.



15)    It is contended that, dispute referred to

learned Arbitrator being fixation of price based on

the evidence and inputs furnished by both the

parties, however, learned Arbitrator, having found

that   Debit   Notes   issued    by   Respondent    is

unsustainable and having held that Respondent is

not entitled to the same, instead of answering the

reference in favour of Claimant, relegated the

parties to resolve the dispute, which would lead

Respondent to take unilateral decision for fixing the

price, whereby, Respondent is entrusted with rights

beyond the terms of the marketing agreement.
                                                   AS.71/2014
                                                       &
                                                  AS.89/2014
                           21


16)   On the other hand, Respondent contends

that, fixing the prices for marketing Iron Ore

keeping the facts of procurement of MMTC is

different than fixing the prices for marketing the

Iron Ore based on MMTC procurement. Learned

Arbitrator has not appreciated Ex.C.12 and Ex.C.14.

Hence, guidelines made at para 14.17 is not correct.

Correct method of fixing the prices of marketing

Iron Ore is Schedule 'D' of the marketing agreement

and Ex.R.18 to R.14.



17)   It is contended that, the deductions for

arriving at ex pit head price of iron ore fines   i.e.

transportation charges, royalty, cess, forest permit

charges, loading charges, moisture and terminal

handling charges has already been considered,

therefore, once again taking into consideration does

not arise. Hence, discussion in para 14.18 based on

Ex.C20 and examination of CW1 is not correct.
                                                            AS.71/2014
                                                                &
                                                           AS.89/2014
                                22


18)     Per    contra,      Claimant     contends         that,

Respondent     has    not      made    out    any      grounds

enshrined in Section 34 of the Arbitration and

Conciliation   Act,   and      grounds       claimed    would

amount to re-appreciating the facts and evidence,

which is not permissible under Section 34 petition.

This Court cannot sit in appeal over the award

rendered by learned Arbitrator. Claimant, in support

of its contention, has placed reliance on judgment

in the case of P.R.Shah & Stock Broker (P) Ltd.,

V. M/s.B.H.H Securities (P) Ltd. [AIR 2012 SC

1866], wherein, the Hon'ble Supreme Court was

pleased to hold that :

         " 15. A court does not sit in appeal over
         the award of an arbitral tribunal by re-
         assessing or re-appreciating the evidence.
         As award can be challenged only under the
         grounds mentioned in Sec.34(2) of the
         Act".



19)     Claimant, having challenged the award, on

the other hand, has justified the award contending

that,   Respondent       has   not    taken    any     specific
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                                 23


grounds as enumerated in Section 34 of the

Arbitration and Conciliation Act and that ground

urged     by     Respondent      would     amount   to   re-

appreciating the facts and evidence, which is not

permissible under Section 34 petition. Having gone

through        the     contentions    of    Claimant     and

Respondent in their respective plaint, it is crystal

clear that, in both the suits, they have not taken

any specific ground as set out in Section 34 of the

Arbitration and Conciliation Act. Ratio laid down in

the above judgment relied upon by Claimant is

equally applicable to Claimant also.          Be that as it

may.



20)     Contentions as raised by Claimant, as well as

Respondent are to be looked into on the anvil of the

ratio laid down in the judgment supra. Claimant

sought     for       following   reliefs   before   learned

Arbitrator.
                                                        AS.71/2014
                                                            &
                                                       AS.89/2014
                               24


         " (a) Declare that the Debit Notes dated
         28th March 2007 and 30th March 2007
         issued by the Respondent are illegal,
         arbitrary, bad in law, void ab initio and
         contrary to the terms agreed between the
         parties;

         (b) Direct that the said Debit Notes be
         cancelled by the Respondent by and under
         the directions of this Hon'ble Tribunal;

         (c) Declare that the 'marketing rate' for
         the purpose of the 'Marketing Agreement'
         for the current year and in future be
         determined in accordance with and on the
         basis of the particulars contained in
         ANNEXURE-C19."



21)    Relevant    issues     as    framed   by    learned

Arbitrator are as follows :

        "1a. Whether the claimant proves that
        the revision and re-fixing of prices every
        year between the parties to the agreement
        should take into consideration, the revision
        (if any) in the prices of MMTC for
        procurement of iron ore suitably adjusted
        to arrive at a comparable MMTC's
        procurement price?

        1b. Whether the respondent proves that
        the price fixation method should be as per
        the agreement by taking into consideration
        of revision in MMTC prices on 1st April of
        each year on mutual discussion?

        4. Whether the respondent prove that the
        debit notes raised by it in the month of
        March, 2007 on the claimant for
        Rs.23,65,95,929/- and on Mukand Limited
        as   nominee     of  the    claimant  for
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                                25


        Rs.33,06,78,120/-        on    account     of
        differential price are legal and valid?

        5. Whether the respondent is entitled to
        claim calibrated iron ore price on the basis
        of MMTC's procurement prices on the date
        of delivery as stated in the respondent's
        letter dated 30th Mach, 2007 read with
        clause 5 of the marketing Agreement
        dated 17th January, 2002?

        7. Whether the respondent proves that
        the price cannot be fixed on mutual
        discussion     without    taking  into
        consideration de hors MMTC price?

        9. Whether the respondent proves that
        marketing price fixing is on Ex-Pit basis
        and excluding all statutory payments, such
        as Royalty, FDT, Cess and taxes etc?"




22)    Findings of learned Arbitrator on the above

Issues read thus :

         " 14.17    In Ex.C12 and C14 as also in
         Ex.C17, the respondent sought to fix the
         rate solely on the basis of MMTC
         procurement prices and no other factor
         was taken into consideration.      In the
         communications at Ex.C15 and C16, the
         claimant does not dispute the MMTC rates.
         The disputes are raised only as to method
         of arriving at the rate and the
         adjustments/deductions to be made from
         the MMTC "Procurement Price" to arrive at
         the comparable ex pit head price payable
         by the claimant.      As per the Ex.C1
         agreement, the rate had to be fixed
         annually. The price was to be effective
         from 1st April and remain constant till 31 st
         March of the following year. Rate so fixed
                                                 AS.71/2014
                                                     &
                                                AS.89/2014
                       26


could not be revised on day to day basis or
periodically on the dates of delivery. Since
rate had to be fixed with effect from 1 st
April, rates prevailing on said day or
thereafter were not relevant. The rate as
on 31st March, i.e. the previous day being
most proximate can form reasonable basis
in fixing the price to be effective from 1st
April. Exs.C12 and C14 do not indicate the
MMTC prices as on 31/3/2006 or
31/3/2007. As per Ex.C21 produced by the
claimant the MMTC price on 31/3/2006 was
Rs.1028 PMT and on 31/3/2007 was
Rs.1058 PMT. Hence, the respondent shall
take    into   consideration    the    MMTC
procurement      rate   of   Rs.1028/-     to
determine the price payable by the
claimant to be effect from 1st April 2006.
Similarly the respondent shall take into
consideration the MMTC procurement rate
of Rs.1058/- PMT to determine the
comparable ex pit price payable by the
claimant to be effect from 1st April 2007.

14.18      In evidence the claimant has
stated    that     MMTC      declares     the
procurement price for various mineral
products including calibrated iron ore, on
free on rail (FOR) basis on dry weight of
mineral product after adjusting the
moisture content. Claimant has produced
Ex.C20 which is a copy of the letter of
MMTC to the respondent dated 10/8/2007
showing the deductions for arriving at ex
pit head price of iron ore fines, i.e.
transportation charges, royalty, cess,
forest permit charges, loading charges,
moisture and terminal handling charges.
Clause 5 itself makes it clear that the price
payable is on ex pit head basis. Further,
under clause 5, the royalty cess, etc.
payable for ore supply is to the account of
the respondent. From the MMTC price
royalty, Cess etc., payable for the iron ore
supplied from the SIOM, has to be reduced.
                                                 AS.71/2014
                                                     &
                                                AS.89/2014
                       27


These cannot be imposed on the claimant.
In    cross-examination     of   CW1,     the
respondent has not disputed the heads of
deductions as per Ex.C20 to arrive at ex pit
head price, but has only suggested that
the same pertains to iron ore fines.
Therefore from the MMTC procurement
prices of Rs.1028/- and Rs.1058/- PMT
prevailing on 31/3/2006 and 31/3/2007,
respectively, the transportation charges,
royalty, cess, forest permit charges,
loading charges, moisture and terminal
handling charges are to be deducted, to
arrive at comparable ex pit head price
payable by the claimant. For calibrated
iron ore the parties have not placed on
record any material to establish the rates
of such deductions. As such, the Tribunal
is left with no choice but to direct the
respondent to ascertain the rates of
deduction to be made from MMTC price
towards transportation charges, forest
permit charges, loading charges, moisture
and terminal handling charges, to arrive at
the ex pit head price of calibrated iron ore.
To the extent explained above, Ex.C1
contemplates suitable adjustments by way
deductions to arrive at a comparable ex pit
head price, FDT, and NPV being a part of
ex pit head price will not be deducted from
the MMTC's procurement price, if included
in it. But all the same time it cannot be
charged to the claimant, in addition to the
comparable pit head price arrived based
on MMTC procurement price.

14.19      Based on the same principles as
stated above, the rate of iron ore fines
effective from 1/4/2006 and 1/4/2007 will
have to be determined. In respect of iron
ore fines, since there is no dispute as to
the rates of deduction to be made from the
MMTC procurement price to arrive at the
comparable ex pit head price, the same
                                                 AS.71/2014
                                                     &
                                                AS.89/2014
                       28


are to be made at the rates mentioned in
Ex.C20.

14.20      In addition, in case of any
revision of four parameters specified in
clause 5 from time to time, the rates will
have to be revised. In other words, the
rates fixed on the basis of four parameters
may not be constant for the entire period
i.e. 1/4/2006 to 31/3/2007 and 1/ 4/2007 to
31/3/2008. Whenever there is any change
in the rates of the four parameters, they
will have to be taken into consideration to
revise the price.

14.21      The respondent shall determine
the rates payable by the claimant within
two month from the date of this award.
For the said purpose, the claimant shall be
entitled      to      provide       relevant
material/inputs, if any to the respondent
within two weeks from the date of this
award, which shall be duly considered.
The respondent may take assistance of
independent Chartered Accountant/Cost
Accountant, if required for the purpose.

14.22      In this view the Issue Nos.1a,
1b, 4, 5, 7 and 9 are answered,
accordingly. It is held that the revision and
re-fixing of prices every year should take
into consideration, the revision (if any) in
the prices of MMTC for procurement of iron
as on 31st March. Said prices of MMTC have
to be suitably adjusted by deducting
transportation charges, royalty, cess,
forest permit charges, loading charges,
moisture and terminal handling charges to
arrive at and fix a comparable ex pit head
price payable by the claimant. The rate
has to be fixed annually basis on the price
prevailing on 31st March of the year, with
effect from 1st April of each year on ex-Pit
head basis. The price so fixed shall remain
constant for entire period of one year (i.e.
                                                               AS.71/2014
                                                                   &
                                                              AS.89/2014
                                 29


         from 1st April till 31st March of the following
         year).     The debit notes raised by the
         respondent for Rs.23,65,95,929/- on the
         claimant and for Rs.33,06,78,120/- on
         Mukand Limited, are not valid to the extent
         contrary to the conclusions recorded supra
         and consequently need to be modified.
         The respondent is not entitled to claim
         calibrated iron ore price on the basis of
         MMTC's procurement prices on the date of
         delivery as stated in the respondent's
         letter dated 30th March, 2007".
                                      (underlined by me)




23)    Respondent contends that, fixing the prices

for   marketing    iron    ore    keeping     the     facts   of

procurement of MMTC is different than fixing the

prices for marketing the iron ore based on MMTC

procurement.      In   other     words,     Respondent         is

claiming marketing price on the basis of MMTC

procurement price as against Clause 5 of Ex.C1,

Agreement, which envisages that "prices shall be

reviewed and re-fixed on 1st April each year, taking

into consideration the revision in prices, if any, by

MMTC."    Said contention of Respondent has been
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                                30


duly assailed by learned Arbitrator and findings of

learned Arbitrator are as follows :

         " 14.6     What follows from the above
         decisions     is     that      if    certain
         price/amounts/rates are to be fixed having
         regard to specified factor the same does
         not preclude the taking into account of
         other relevant factors, keeping in view the
         objective of fixing such price.      In the
         instant case having regard to the terms of
         the Ex.C1 contract between the parties,
         clause 5 therein mentions MMTC price only
         as a benchmark to represent the prevailing
         market rate. It cannot be lost sight that
         MMTC is central government undertaking
         and required to procure mineral at market
         price through transparent process. In the
         present case the prices have to be
         reviewed and re-fixed "taking into
         consideration the revision in prices, if any,
         by MMTC". On the fact it "Taking into
         consideration" are not words of limitation
         but of general guidance. If the price were
         to be same as that of MMTC, clause 5
         ought to have stated so. The fixation of
         price under clause 5 has to be done by
         taking into consideration the revision in
         benchmark price of MMTC. In addition to
         MMTC        price,       similar/comparable
         benchmark can be used as an input to
         determine reasonable price payable.

         14.10      The next issue for consideration
         is whether the Respondent is entitled to
         claim marketing price on the basis of
         MMTC's procurement price on the date of
         delivery. The plain language of clause 5
         requires that prices be reviewed and "re-
         fixed" every year. The purpose of fixing
         and keeping the price constant is to
         insulate the claimant from the fluctuation
         in price during a year. At the same time by
         requiring annual review and re-fixation, it
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                                31


         is ensured that prices remain consistent
         with change in market. The price must not
         only be revised but also "re-fixed". If the
         price is permitted to fluctuate based on
         the rate MMTC procurement price on the
         date of delivery the stipulation for review
         and re-fixing the price every year become
         redundant. If the price is to fluctuate for
         each delivery, there is no need for review
         every year. Even the conduct of
         respondent is keeping the price for the
         year 2005-06 firm for the entire year also
         shows that price to be fixed as on 1 st of
         April had to remain firm till 31st March of
         the next year. Hence, it is held that the
         respondent cannot claim marketing price
         on the basis of MMTC's procurement price
         on the date of delivery but the price has to
         be fixed every year as on 1st April and has
         to remain firm till 31st March of next year."



24)    Respondent contends that, deductions for

arriving at ex pit head price of Iron Ore fines i.e.

transportation charge, royalty, cess, forest permit

charges, loading charges, moisture and terminal

handling charges has already been considered,

therefore, once again taking into consideration of

these facts do not arise.        It is important to note

that, learned Arbitrator has held that for calibrated

iron ore, the parties have not placed on record any

material to establish the rates of deductions, as
                                                       AS.71/2014
                                                           &
                                                      AS.89/2014
                             32


such, Tribunal is left with no choice but to direct the

Respondent to ascertain the rates of deductions to

be made as per MMTC price towards transportation

charges, forest permit charges, loading charges,

moisture and terminal handling charges to arrive at

the ex pit head price of calibrated iron ore. In that

context, findings of learned Arbitrator are to be

looked into.



25)    Claimant's    contention    is   that,   learned

Arbitrator erred in holding that prices fixed on

01.04.2005 was not valid up to 31.03.2007, which is

contrary to admitted pleadings and evidence on

record, calling for interference by this court under

Section 34 of the Arbitration and Conciliation Act.



26)    Having gone through the arbitral award, it

makes it clear that, learned Arbitrator was pleased

to assail the contention of claimant in detail, after
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                               33


appreciating   the    materials     placed    before    him.

Relevant portion of the award reads thus :

       "12.7         Keeping in mind the above
      express    understanding      as   per    Ex.C1
      Marketing Agreement, the first point that falls
      for consideration is whether the parties
      agreed for a modification so as to provide
      that the rate fixed with effect from April 2005
      shall remain constant/firm for two years, as
      contended by the Claimant.

      12.8 Parties agree that in terms of clause 5
      of the Ex.C1 Marketing Agreement the price
      revision for the first time became due on
      1/4/2005.

      12.14 A reading of Ex.C2 and C3 show that
      Claimant had requested for fixing the price
      for two years. In Ex.C4 Respondent did not
      accept the proposal for fixing the price on
      firm basis for two years. But in Ex.C5 and C6
      the Managing director of the respondent has
      stated that the revised price at Rs.314/PMT
      shall be valid till 31/3/2007.     However it
      noteworthy that this statement is made not
      on the basis of the request of the claimant or
      to insulate the claimant for fluctuation in ore
      price, but in view of erred understanding that
      as per provisions of Ex.C1 agreement the
      selling price has to be revised and re-fixed
      once in two years. This is contrary to express
      terms of clause 5 of Ex.C1 agreement which
      mandates that (from 1 / 4/ 2005) the prices
      shall be reviewed and re-fixed on 1st April
      each year.

      12.15 The respondent being a public limited
      company and government undertaking,
      functions through the board of directors. A
      letter written by one of its officer/Managing
      Director, will not suffice to change terms of
      its contract, more so when the letter itself
      contemplated ratification by the Board. In
                                                    AS.71/2014
                                                        &
                                                   AS.89/2014
                          34


U.P. Rajkiya Nirman Nigam Ltd. V. Indure
(P) Ltd., (1996) 2 SCC 667 it is held :

    "18. As found earlier, there is no signed
    agreement by a duly competent officer on
    behalf of the appellant. The doctrine of
    "indoor     management"        cannot    be
    extended to formation of the contract or
    essential terms of the contract unless the
    contract with other parties is duly
    approved and signed on behalf of a public
    undertaking or the Government with its
    seal by an authorised or competent
    officer. Otherwise, it would be hazardous
    for public undertakings or Government or
    its instrumentalities to deal on contractual
    relations with third parties."

The decision in MRF Ltd. V. Manohar
Parrikar, (2010) 11 SCC 374 is also
pertinent wherein it is held :

    "111.         The doctrine of indoor
    management is in direct contrast to the
    doctrine or rule of constructive notice,
    which is essentially a presumption
    operating in favour of the company
    against the outsider.     It prevents the
    outsider from alleging that he did not
    know that the constitution of the
    company rendered a particular act or a
    particular delegation of authority ultra
    vires.      The    doctrine     of  indoor
    management is an exception to the rule
    of constructive notice.     It imposes an
    important limitation on the doctrine of
    constructive notice.   According to this
    doctrine, persons dealing with the
    company are entitled to presume that
    internal requirements prescribed in the
    memorandum and articles have been
    observed. Therefore, doctrine of indoor
    management protects outsiders dealing
    or contracting with a company, whereas
    doctrine of constructive notice protects
    the insiders or a company or corporation
    against dealings with the outsiders.
    However, suspicion of irregularity has
    been widely recognised as an exception
                                                    AS.71/2014
                                                        &
                                                   AS.89/2014
                           35


     to the doctrine of indoor management.
     The protection of the doctrine is not
     available   where     the    circumstances
     surrounding the contract are suspicious
     and therefore invite inquiry.....

     113. This exception to the doctrine of
     indoor      management         has     been
     subsequently adopted in many Indian
     cases. They are B. Anand Behri Lal V.
     Dinshaw and Co. (Bankers) Ltd. [AIR 1942
     Oudh 417] and Abdul Rahman Khan V.
     Mufassal Bank Ltd. [AIR 1926 All 497]
     Applying the exception to the present
     scenario, there is sufficient doubt with
     regard to the conduct of the Power
     Minister in issuing the Notifications dated
     15-5-1996 and 1-8-1996. Therefore, there
     is a definite suspicion of irregularity
     which renders the doctrine of indoor
     management inapplicable to the present
     case."

12.16 Having regard to the legal position
flowing from the above decisions, the case on
hand is to be considered. It is not the case of
the claimant that the fixation of price once in
two years instead of once every year was
approved by the board of Directors of
Respondent. Claimant has also not taken
shelter under the doctrine of indoor
management. In fact Ex.C5 & Ex.C6 in clear
terms stated that "on ratification by MML
Board, the modification will be incorporated."
Thus even assuming that Ex.C5 and C6
contained stipulation as to fixation of price on
firm basis for two years in modification of
clause 5 of Ex.C1 agreement, the same was
only a proposal and subject to approval by
board of directors of MML. It is not the case
of the claimant that the proposal contained in
Ex.C5 & Ex.C6 was in fact ratified by the
Board of MML or an agreement incorporating
the modified understanding was executed by
competent officer.
                                                   AS.71/2014
                                                       &
                                                  AS.89/2014
                          36


12.17       The respondent is justified in
relying upon clause 19 of Ex.C1agreement
which states that :

             "19.      No     modifications
        alteration or amendment of this
        agreement or any of its terms or
        provisions shall be valid or legally
        binding on the parties unless made
        in writing and duly executed by
        both parties."

It is not the case of the claimant the Ex.C1
agreement was even modified ever in the
manner contemplated under clause 19
thereof to vary the understanding as per
clause 5 for review revision of price on yearly
basis. Merely based on Ex.C5 and C6 letters,
in absence of ratification by Board of MML
and execution of wring by competent officer
as contemplated in clause 19, the claimant
cannot claim variation of express terms of
clause 5.

12.19 In view of plain language of clause 5
of Ex.C1 agreement, in absence of
modification     thereof   in   the   manner
contemplated in clause 19, Ex.C5 and C6
having been issued on erroneous basis that
revision of price was required to take place
once every two years, the respondent is
justified in clarifying that the statement in
Ex.C5 and C6 that prices shall be valid till
31/3/2007 was an error. The contents of
Ex.C5 and C6 that the rate shall be valid for
two years could be on account of printing
error    or   on     account   of   erroneous
understanding as to what is provided in
clause 5. Be as it may, the Ex.C1 agreement
is self contained. Its clause 5 requiring
review and re-fixing of the rate every year is
clear and free from any ambiguity. The said
term can be varied only by mutual consent
of the parties and in the manner agreed
between the parties. In the present case in
absence of ratification by Board of MML and
                                                                  AS.71/2014
                                                                      &
                                                                 AS.89/2014
                                     37


       modification of Ex.C1, Ex.C5 and C6 have
       not resulted in variation of clause 5. Hence
       they are not valid and binding on the
       respondent".



27)    Contentions          as   raised        by   Claimant    that

parties agreed for modifications so as to provide the

rate fixed with effect from April 2005 shall remain

firm for two years is a pure fact which has been

decided by learned Arbitrator after considering the

evidence placed before him. This Court, under

Section      34     petition,    cannot        re-appreciate    the

evidence, which has been appreciated by learned

Arbitrator,       when     reasons        assigned    by   learned

Arbitrator        are    intelligible     in    arriving   at    his

conclusion. If it does so, same would amount to

usurpation of power of Arbitral Tribunal which is not

permissible under law.



28)    Claimant contends that learned Arbitrator

has failed to decide the reference sought for by the
                                                  AS.71/2014
                                                      &
                                                 AS.89/2014
                            38


parties, instead, he has relegated the parties to

resolve the dispute by making the Claimant to

submit to the unilateral decision of Respondent for

fixing the price by further directing the Claimant to

submit its inputs. As mentioned above, Claimant, in

his claim petition, has sought for declaration that

Debit Notes dated 28.03.2007 and 30.03.2007

issued by Respondent are illegal and contrary to the

terms of agreement and that marketing rate for the

current   year and   in future   be determined     in

accordance with and on the basis of particulars

contained in Annexure-C-19. Learned Arbitrator was

pleased to hold that, claim for rate equivalent to

MMTC rate prevailing on the date of delivery is not

just and to that extent rate claimed in Exs.C.12 and

C.14, Debit Notes for the period 01.04.2006 to

30.03.2007 are not valid.    It is further held that,

fixation of price by Respondent      for the period

01.04.2007   to   31.03.2008     based   on   MMTC's
                                                           AS.71/2014
                                                               &
                                                          AS.89/2014
                                39


procurement price on the date of delivery as

Respondent's letters in Ex.C.17 is invalid. It is to be

noted that, in Ex.C.19, claimant disputed the fixing

of selling price of calibrated iron ore as conveyed in

Ex.C.17     by   Respondent.     Consequently,        learned

Arbitrator was pleased to direct Respondent to

determine and re-fix the rate payable by Claimant

effective    from    01.04.2006         based    on    MMTC

procurement price prevailing on 31.03.2006 having

regard to the clause 5 of Ex.C1. When matter being

thus, there is no reason to say that learned

Arbitrator, instead of answering the reference in

favour of claimant, relegated the parties to resolve

the dispute.



29)     Having gone through the award, it is crystal

clear   that,    learned   Arbitrator    has    meticulously

assailed disputes referred to him in a perspective

manner having regard to the materials placed
                                                                AS.71/2014
                                                                    &
                                                               AS.89/2014
                                   40


before him.      Neither Claimant nor Respondent has

pleaded any specific ground as set out in Section 34

of   the    Arbitration      and        Conciliation   Act,    nor

canvassed any such ground on which award can be

set aside, nor made out any ground as such to set

aside the award. Claimant has emphatically stated

in written statement filed in AS.No.89/2014 that

Respondent has not made out any grounds to set

aside the arbitral award. In ONGC Ltd. V. Saw

Pipes Ltd. [(2003) 5 SCC 705], the Hon'ble

Supreme Court was pleased to hold that "award

could      be   set   aide   if    it     is   contrary   to   (a)

fundamental policy of Indian law; or (b) Interest of

India; or (c) Justice or morality; or (d) in addition, if it

is patently illegal. Illegality must go to the root of

the matter and if the illegality is of trivial nature it

cannot be held that award is against the public

policy". In the instant case, award passed is based

on reasons. Reasons assigned by learned Arbitrator
                                                          AS.71/2014
                                                              &
                                                         AS.89/2014
                               41


are intelligible. No illegality or perversity can be

attributable to award. Merely because award is not

in accordance with the wishes of the parties, same

cannot be termed as illegal. Hence, this Court

opines that, suits of Plaintiffs fail, accordingly, I

answer the above point in the negative.



30)    Point No.2 :      In    view    of   the    foregoing

discussion and answer to Point No.1, I pass the

following :

                     ORDER

(1) Suit filed by Plaintiff in AS.No.71/2014 and suit filed by Plaintiff in AS.No.89/2014 under Section 34 of the Arbitration and Conciliation Act, 1996, for setting aside award dated 28.02.2014 passed by learned Arbitrator/Respondent No.2; are hereby dismissed.

AS.71/2014 & AS.89/2014 42 (2) No order as to costs.

(3) Keep original of this judgment in AS.No.71/2014 and copy in AS.No.89/2014.

(Dictated to the Judgment Writer, transcribed and computerized by her, transcript thereof corrected and then pronounced by me in open court, dated this the 10th day of January, 2020.) (RAMA NAIK) VI Addl.City Civil & Sessions Judge, Bengaluru City.