[Cites 0, Cited by 0] [Section 25] [Entire Act]

State of Tamilnadu - Subsection

Section 25(6) in Tamil Nadu Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005

(6)In case of the hydro electro Generating Stations, which have not been in existence for a period of five years, the operation and maintenance expenses shall be fixed at 1.0% of the capital cost as admitted by the Commission and shall be escalated at the rate of 4% per annum from the subsequent year to arrive at base operation and maintenance expenses. The base operation and maintenance expenses shall be further escalated at the rate of 4% per annum to arrive at permissible operation and maintenance expenses for the relevant year.