Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 9, Cited by 0]

Karnataka High Court

Gravity One Living Space Pvt. Ltd vs Naagamma on 9 February, 2023

Author: R Devdas

Bench: R Devdas

                                         -1-
                                                       CMP No. 418 of 2021




               IN THE HIGH COURT OF KARNATAKA AT BENGALURU
                    DATED THIS THE 9TH DAY OF FEBRUARY, 2023
                                      BEFORE
                        THE HON'BLE MR JUSTICE R DEVDAS
                       CIVIL MISC. PETITION NO. 418 OF 2021
             BETWEEN:
             GRAVITY ONE LIVING SPACE PVT. LTD.,
             A COMPANY INCORPORATED AND REGISTERED UNDER
             COMPANIES ACT 2013,
             WITH ITS REGISTERED OFFICE AT
             NO. 1062, VISHNUVARDHANA ROAD,
             OPP. ZILLA PANCHAYATH, CHAMARAJPURAM,
             MYSURU - 570 005.
             REPRESENTED BY ITS DIRECTOR
                                                    ...PETITIONER
             (BY SRI. RUPESH KUMAR .S, ADVOCATE)
             AND:
             NAAGAMMA,
             AGED ABOUT 56 YEARS,
             W/O LATE CHAMARAJU,
Digitally
             R/AT MARATIKYATHANAHALLI,
signed by    JAYAPURA HOBLI,
JUANITA
THEJESWINI   MYSURU TALUK - 570 026.
Location:
HIGH                                                        ...RESPONDENT
COURT OF
KARNATAKA    (BY SRI. B. S. NAGARAJ, ADVOCATE)
                    THIS CIVIL MISC. PETITION IS FILED UNDER SEC.11(5)
             OF THE ARBITRATION AND CONCILIATION ACT 1996, PRAYING
             THIS HONBLE COURT TO A. APPOINT A SOLE ARBITRATOR
             NAMELY HON'BLE RETIRED DISTRICT JUDGE, KAMALA OR ANY
             OTHER RETIRED DISTRICT JUDGE TO ADJUDICATE UPON THE
             LIS   BETWEEN   THE   PARTIES     AROSE   UNDER   THE   JOINT
                                  -2-
                                            CMP No. 418 of 2021




DEVELOPMENT      AGREEMENT        DATED    13/03/2013     AS   PER
ANNEXURE-F.     B.     PASS    SUCH    OTHER    ORDERS    AS   ARE
NECESSARY IN THE CIRCUMSTANCES OF THE CASE.


     THIS PETITION, COMING ON FOR ADMISSION, THIS DAY,

THE COURT MADE THE FOLLOWING:

                               ORDER

R.DEVDAS J., (ORAL):

The petitioner has filed this civil miscellaneous petition under Section 11(5) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator to adjudicate the dispute between the parties under the joint development agreement dated 13.03.2013.

2. It is not disputed by the respondent that the parties have indeed entered into a joint development agreement dated 13.03.2013 wherein the respondent, the owner of the land permitted the petitioner herein to develop the same into the residential layout. In terms of the joint development agreement dated 13.03.2013, the petitioner herein was required to complete the development within a period of 18 months from the date -3- CMP No. 418 of 2021 of the joint development agreement, subject to any intervening circumstances either at the instance of the government or by act of god. It is also not disputed that subsequently, the parties entered into continued joint development agreement dated 07.11.2014 wherein the time period for completion of the development stood extended by another period of twelve months on the same condition.

3. Leaned counsel for the respondent submits that in terms of the continued joint development agreement dated 07.11.2014 the time period of completion of the development work came to an end on 06.11.2015. Learned counsel submits that the cause of action for the petitioner arose immediately after the completion of the period of contract, i.e., on 07.11.2014 and within a period of three years from there the petitioner should have invoked the arbitration clause and sought for resolution of the dispute by an appointment of arbitrator. However, a notice was issued by the petitioner only on 17.08.2021 -4- CMP No. 418 of 2021 long after the expiry of the period of limitation and therefore, the learned counsel for the respondent submits that the prayer made in the civil miscellaneous petition cannot be granted.

4. Per contra, learned counsel for the petitioner seeks to place reliance on a decision of the Hon'ble Supreme Court in the case of BHARAT SANCHAR NIGAM LIMITED AND ANOTHER VS. M/S NORTEL NETWORKS INDIA PRIVATE LIMITED reported in (2021) 5 SCC 738. Learned counsel would contend that in terms of the said decision although Article 137 of the schedule provided in the Limitation Act would became applicable, nevertheless, the period for construing the three years as provided in Article 137 would commence only when the arbitration notice is issued and not before that.

5. In the considered opinion of this Court, the decision of the Hon'ble Supreme Court makes it very clear -5- CMP No. 418 of 2021 that there are two aspects to the question of limitation that would arise in an arbitration proceedings.

6. Having regard to the admitted facts, this Court finds that the Hon'ble Supreme Court considered the issue as to whether the Court may refuse to make the reference under Section 11 where the claims are ex-facie time barred. The Hon'ble Supreme Court held that the period of limitation for issuing notice of arbitration would not get extended by mere exchange of letters or by mere settlement discussions, where a final bill is rejected by making a deduction or otherwise. Sections 5 to 20 of the Limitation Act, 1963, do not exclude the time taken on account of settlement discussions. It was noticed that Section 9 of the limitation act, makes it clear that where once the time has begun to run, no subsequent disability or inability to institute a suit or make an application stops it. The Hon'ble Supreme Court held that the period of limitation that filing an application under Section 11 of the Act, would be governed by Article 137 of the 1st schedule -6- CMP No. 418 of 2021 of the Limitation Act, 1963. In terms of Article 137, the period of limitation prescribed is three years.

7. Having regard to the settled position of law, this Court is of the considered opinion that the petitioner issued the arbitration notice on 17.08.2021 beyond the period of three years as prescribed in Article 137 of the Limitation Act. That being the position, the prayer made by the petitioner to appointment an arbitrator to resolve the dispute under the agreement dated 13.03.2013 cannot be granted.

Accordingly, the civil miscellaneous petition stands dismissed.

Sd/-

JUDGE rv