Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 3]

Delhi High Court

D.D.A. & Ors. vs P.C. Sharma & Co. & Anr. on 2 February, 2009

Author: Mukul Mudgal

Bench: Mukul Mudgal, Vipin Sanghi

*     IN THE HIGH COURT OF DELHI AT NEW DELHI
+          FAO(OS) NO.143/2006 & C.M. No.4443/2006

                                        Date of Decision: 02.02.2009

      D.D.A. & ORS.                              ..... Appellants
                           Through:   Ms. Monica Sharma, Advocate

                  versus

      P.C. SHARMA & CO. & ANR.                   ..... Respondents
                     Through:         Mr. Sandeep Sharma, Advocate

CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE VIPIN SANGHI

1. Whether the Reporters of local papers may be
   allowed to see the judgment?

2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the
   Digest?

%                            JUDGMENT (Oral)

      The appeal is taken up for hearing with the consent of learned

counsel for the parties.

      This appeal challenges the Judgment of the learned Single Judge

dated 08.11.2005, dismissing the objection petition filed by the DDA

against the award dated 24.06.1989 made by the sole arbitrator Shri

A.P. Paracer, except in respect of claim No.5, and reducing the rate of

interest to simple interest @ 12% per annum.

      The only argument before the learned Single Judge was in

respect of claim Nos.14, 16 & 17 and was confined before the learned

Single Judge in the following term:
             "9.    Learned counsel for the respondent also
            further fairly stated that other than claims no.
            14, 16 & 17 either the claims have been
            disallowed or withdrawn or are based on
            appreciation of evidence, the same are not to
            be seriously contested. Thus the submissions
            were made only in respect of claims no. 14, 16
            & 17 under one head. The grievance of the
            respondent is that there is overlapping claims
            which have been awarded under these
            clauses."

      The appellant's counsel has contended before us that the claim

Nos.14, 16 & 17 were overlapping and could not have been awarded

separately. The learned Single Judge has dealt with the above issues

and held as follows:

A.    The claim No.14, is founded upon the factum of prolongation of

contract beyond the stipulated date of completion on account of non-

fulfillment of the obligation by the DDA. The said claim is analogous to

the claim arising under clause 10CC incorporated by the DDA in

subsequent contracts. Claim No.14 dealt with increase in material and

labour costs during the period beyond the stipulated date of

completion of work under the contract.

B.    Claim No.17 is specific about the site expenses and other

overheads incurred by the respondent beyond the stipulated date of

completion; and

C.    Claim No.16 is in respect of loss of profitability. Claim No.16 was

based on the premise that had the contract been concluded within the

stipulated period the establishment and the energy of the contractor
 would have been put to execution of a new contract, which was denied

to the contractor on account of use of manpower and resources for

completion of the contract beyond the stipulated date on account of

fault of the appellant itself.

      In our view, the aforesaid form three distinct heads of damages

that a contractor would be legally entitled to claim, subject, of course,

to the same being duly established, where the work gets prolonged

due to the fault of the employer and not the contractor.

      The learned Single Judge has distinguished the judgment relied

upon by the appellant in "Union of India v. Jain Associates & Anr."

(1994) 2 SCC 665, and, in our view, correctly so.      That was a case

where the award was a non-speaking award, and the question being

considered was whether the award suffered from non-application of

mind, on account of the fact that there was overlapping claims which

had been allowed in toto.

      The learned counsel for the appellant has failed to point out any

fallacy in the reasons given by the learned Single Judge. Accordingly,

the appeal is dismissed.



                                          MUKUL MUDGAL, J.

VIPIN SANGHI, J. FEBRUARY 02, 2009 rsk