Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 10, Cited by 0]

Karnataka High Court

Nirani Sugars Ltd vs Spaco Corporation on 11 December, 2025

Author: R.Devdas

Bench: R.Devdas

                                               -1-
                                                         NC: 2025:KHC-D:17929-DB
                                                         RFA No. 100181 of 2019
                                                     C/W RFA No. 100179 of 2019
                                                         RFA No. 100180 of 2019
                     HC-KAR




                   IN THE HIGH COURT OF KARNATAKA, AT DHARWAD

                    DATED THIS THE 11TH DAY OF DECEMBER, 2025
                                    PRESENT

                         THE HON'BLE MR. JUSTICE R.DEVDAS
                                       AND
                    THE HON'BLE MR. JUSTICE B. MURALIDHARA PAI

                                R.F.A. NO.100181 OF 2019 (MON)
                              C/W. R.F.A. NO.100179 OF 2019 (MON)
                                R.F.A. NO.100180 OF 2019 (MON)


                    IN R.F.A. NO.100181/2019
                    BETWEEN:

                    NIRANI SUGARS LTD.,
                    A COMPANY REGISTERED UNDER
                    THE COMPANIES ACT, 1956,
                    HAVING ITS REGISTERED OFFICE
                    AT: 4/2, 1ST FLOOR, LEFT WING,
                    SIDDHA ENCLAVE, NEHRU NAGAR,
                    BANGALORE, HAVING ITS
Digitally signed
                    SUGAR MANUFACTURING UNIT
by V N
BADIGER             AND FACTORY SITE AT SY.NO.166,
Location: High
Court of
Karnataka,
                    KULLALI CROSS, TQ: MUDHOL,
Dharwad Bench.
                    DIST: BAGALKOT, DULY REPRESENTED
                    BY MR. MAHESH P. LALAGE,
                    THE DEPUTY GENERAL MANAGER,
                    (A & O), AGE: 42 YEARS,
                    OCC: DEPUTY GENERAL MANAGER,
                    R/O. MUDHOL, TQ: MUDHOL,
                    DIST: BAGALKOT-587313.

                                                                     ...APPELLANT

                    (BY SRI SANGRAM S. KULKARNI, ADVOCATE)
                             -2-
                                      NC: 2025:KHC-D:17929-DB
                                      RFA No. 100181 of 2019
                                  C/W RFA No. 100179 of 2019
                                      RFA No. 100180 of 2019
HC-KAR




AND:

SPACO CORPORATION,
B-7/22-23, MIDC MIRAJ,
DIST: SANGLI,
MAHARASHTRA STATE,
A REGISTERED PARTNERSHIP FIRM,
REPRESENTED BY ITS PARTNER,
SHRI. N. N. GURAV,
AGE: 66 YEARS, OCC: TRADE,
R/O. B-7/22-23, MIDC, MIRAJ,
DIST. SANGLI,
MAHARASHTRA STATE-416410.
                                                ...RESPONDENT

(BY SRI NANDKUMAR ANNA VHATKAR, ADVOCATE)

       THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION
96 READ WITH ORDER 41 RULE 1 AND 2 OF CPC., PRAYING TO
SET ASIDE THE JUDGMENT AND DECREE DATED 11/01/2019
PASSED    IN   O.S.NO.13/2013   PASSED    BY   THE   COURT   OF
ADDITIONAL SENIOR CIVIL JUDGE AND JMFC, MUDHOL, BY
ALLOWING THE PRESENT APPEAL IN THE INTEREST OF JUSTICE
AND EQUITY AND ETC.



IN R.F.A. NO.100179 OF 2019
BETWEEN:

1.   NIRANI SUGARS LIMITED,
     THROUGH SHRI SANGEMESH NIRANI,
     AGE: 32 YEARS, OCC: INDUSTRIALIST,
     THE EXECUTIVE DIRECTOR,
     M/S. NIRANI SUGARS LIMITED,
     R/O. M/S. NIRANI SUGARS LIMITED,
     SY.NO.166, KULLALI CROSS,
                             -3-
                                      NC: 2025:KHC-D:17929-DB
                                      RFA No. 100181 of 2019
                                  C/W RFA No. 100179 of 2019
                                      RFA No. 100180 of 2019
HC-KAR




     VIJAYA NAGAR, TQ. MUDHOL,
     DIST: BAGALKOT-587313.

2.   SHRI MAHESH P. LALAGE,
     AGE: MAJOR, OCC: SERVICE,
     DEPUTY GENERAL MANAGER (ACCOUNTS),
     M/S. NIRANI SUGARS LIMITED,
     R/O. M/S NIRANI SUGARS LIMITED,
     SY.NO.166, KULLALI CROSS,
     VIJAYA NAGAR, TQ: MUDHOL,
     DIST: BAGALKOT-587313,
     PRESENTLY REPRESENTED BY
     SHIVANAND YARGATTI.
                                                 ...APPELLANTS
(BY SRI. SANGRAM S. KULKARNI, ADVOCATE)

AND:

THE PARTNER,
SPACO CORPORATION THROUGH
ITS SHRI N. N. GURAV,
AGE: 66 YEARS,
OCC: INDUSTRIALIST,
R/O. B-7/22-23, MIDC MIRAJ,
DIST: SANGLI-416410,
MAHARASHTRA STATE.
                                                ...RESPONDENT
(BY SRI. NANDKUMAR ANNA VHATKAR, ADVOCATE)


       THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION
96 READ WITH ORDER 41 RULE 1 AND 2 OF CPC., PRAYING TO
SET ASIDE THE JUDGMENT AND DECREE DATED 11/01/2019
PASSED    IN   O.S.NO.08/2013   PASSED    BY   THE   COURT   OF
ADDITIONAL SENIOR CIVIL JUDGE AND JMFC, MUDHOL, BY
ALLOWING THE PRESENT APPEAL IN THE INTEREST OF JUSTICE
AND EQUITY AND ETC.
                            -4-
                                     NC: 2025:KHC-D:17929-DB
                                     RFA No. 100181 of 2019
                                 C/W RFA No. 100179 of 2019
                                     RFA No. 100180 of 2019
HC-KAR




IN R.F.A. NO.100180 OF 2019
BETWEEN:

VIJAY SOUHARD CREDIT SAHAKARI LTD.,
MUDHOL, REPRESENTED BY ITS
GENERAL MANAGER,
SHRI GURURAJ MADHAV VAIDYA,
AGE: 70 YEARS, OCC: MANAGER,
VIJAY SOUHARD CREDIT LTD.,
MUDHOL, TQ: MUDHOL,
DIST: BAGALKOT-587313.
                                                 ...APPELLANT
(BY SRI SANGRAM S. KULKARNI, ADVOCATE)

AND:
M/S. SPACO CORPORATION,
REPRESENTED BY ITS OFFICER-IN-CHARGE
B-7/22-23, MIDC MIRAJ, DIST: SANGLI,
MAHARASHTRA STATE-416410.
                                               ...RESPONDENT
(BY SRI NANDKUMAR ANNA VHATKAR, ADVOCATE)


       THIS REGULAR FIRST APPEAL IS FILED UNDER SECTION
96 READ WITH ORDER 41 RULE 1 AND 2 OF CPC., PRAYING TO
SET ASIDE THE JUDGMENT AND DECREE DATED 11/01/2019
PASSED IN O.S.NO.103/2012 PASSED BY THE COURT OF
ADDITIONAL SENIOR CIVIL JUDGE AND JMFC, MUDHOL, BY
ALLOWING THE PRESENT APPEAL IN THE INTEREST OF JUSTICE
AND EQUITY AND ETC.
     THESE APPEALS, HAVING BEEN HEARD AND RESERVED
ON 29.10.2025, COMING ON FOR 'PRONOUNCEMENT OF
JUDGMENT', THIS DAY, THE COURT PRONOUNCED THE
FOLLOWING:

CORAM:    THE HON'BLE MR. JUSTICE R.DEVDAS
           AND
           THE HON'BLE MR. JUSTICE B. MURALIDHARA PAI
                                 -5-
                                          NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
 HC-KAR




                    CAV COMMON JUDGMENT

    (PER: THE HON'BLE MR. JUSTICE B. MURALIDHARA PAI)


     1.      These appeals arise from the judgments and decrees

dated 11.01.2019 passed in O.S. Nos.8/2013, 13/2013 and

103/2012, by learned Additional Senior Civil Judge and JMFC,

Mudhol (briefly 'the trial court' hereinafter).


     2.      The   dispute   involved    in    O.S.   Nos.8/2013     and

13/2013 is between same parties and arise out of same set of

facts. The matter involved in O.S. No.103/2012 is ancillary to the

dispute involved in other two suits.          As such, for the sake of

convenience all these appeals are taken up for consideration

together.


     3.      Relevant   facts   of     these     suits,   briefly   noted

hereunder:


     3.1     Undisputed/Admitted facts:


     a)      Spaco Corporation is a partnership firm (referred as

'the plaintiff' hereinafter), is the manufacturer and the supplier of

useful machineries for sugar factories.
                                -6-
                                         NC: 2025:KHC-D:17929-DB
                                         RFA No. 100181 of 2019
                                     C/W RFA No. 100179 of 2019
                                         RFA No. 100180 of 2019
HC-KAR




    b) Nirani Sugars Limited is a company registered under

Companies Act (referred as 'the defendant' hereinafter), has got

a sugar manufacturing unit in Kullali Village of Mudhol taluk.


    c) Vijay Souhard Credit Sahakari Ltd., Mudhol (referred as

'the bank' hereinafter) is a co-operative bank registered under

Karnataka Souharda Sahakari Act, 1997, which is carrying on all

banking activities including transfer of funds by RTGS through its

account with Axis Bank, Jamakhandi.


    d) The defendant required sugar bag handling and ash

handling system at their unit. As such, they obtained quotation

from the plaintiff and then issued a Letter of Intent dated

22.07.2010 to the plaintiff for manufacturing, supply, erection

and commissioning of sugar bag handling system and ash

handling at their unit. Afterwards, on 08.09.2010 the defendant

placed a Purchase Order with the plaintiff for supply of the sugar

bag handling system sizes 650 MM, width capacity 752 to 800

bags, worth Rs.95,00,000/-, to be executed in two phases of

Rs.75,00,000/- and Rs.20,00,000/- respectively, subject to

certain commercial terms and conditions.
                                      -7-
                                               NC: 2025:KHC-D:17929-DB
                                               RFA No. 100181 of 2019
                                           C/W RFA No. 100179 of 2019
                                               RFA No. 100180 of 2019
HC-KAR




    e)      Meanwhile, the defendant placed one more Purchase

Order dated 23.08.2011 with the plaintiff for ash handling

system for 90 TPH Boiler including supply of required materials

for modifications of existing belt conveyors, drive assembly,

platform and replacement of hood cover for existing belt

conveyor,   at    the    cost   of    Rs.57,00,000/-     and   subject   to

commercial terms and conditions.


    3.2     Contentions of the Plaintiff - M/s Spaco Corporation

(as per plaint averments in O.S. No.8/2013):


    a)      The plaintiff has carried out entire work of I Phase of

Bag Handling System upto Godown No.3 and Ash Handling

System;


    b)      Work of II Phase of Bag Handling was also started.

However, the defendant has not released even 30% advance

payment;


    c)      The    plaintiff    has    supplied    the   materials   worth

Rs.2,02,49,633/-        to   the     defendant    from    01.04.2010     to

10.09.2011 as per demand of the defendant;
                                 -8-
                                          NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
HC-KAR




    d)       The   defendant     has     paid   only   a   sum     of

Rs.1,72,92,081/- and     the   last    amount   received   from   the

defendant was on 12.4.2012 by RTGS. The defendant was still

due a sum of Rs.29,57,552/- to the plaintiff as on 12.04.2012;


    e)       On 9.1.2013 the plaintiff maintained the suit for

recovery of Rs.29,57,552/- from the defendant together with

interest at the rate of 18% p.a., from 12.4.2012 till realization of

entire money.


    3.3      The contention of the defendant - Nirani Sugars

Limited (as per the plaint averments in O.S. No.13/2013):


    a) The delivery of Phase-I was within 8 weeks and of Phase-

         II was within January, 2011;


    b) The plaintiff did not complete the work of the sugar bag

         handling system properly. Therefore, a meeting was held

         between the parties on 26.11.2011 regarding the balance

         work and after discussions, the minutes of the meeting

         were reduced into writing, enlisting 9 items of work to be

         completed by the plaintiff;
                                 -9-
                                          NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
HC-KAR




   c) The plaintiff agreed to supply all the materials before the

         end of November, 2011, to complete the balance work on

         or before 15.12.2011 and to complete ash handling

         conveyor work within 5.12.2011;


   d) Regarding new ash handling system, a meeting was held

         between the parties on 25.12.2011 and a memorandum

         of minutes was prepared enlisting 7 items of work to be

         attended by the plaintiff;


   e) The plaintiff did not execute and complete the work as

         agreed upon in the memorandum of minutes and the

         meetings held between them;


   f) Therefore, on 21.5.2012 the defendant issued a fresh

         work order to Newcon Engineers of Narayanapura,

         Dharwad and got balance work done, which was not done

         by the plaintiff as agreed, to the extent of Rs.16 Lakhs;


   g) The defendant paid more than Rs.1,01,16,750/- for the

         work of sugar bag handling system and Rs.36,34,600/-

         for ash handling system and it was an additional liability

         on the defendant;
                                 - 10 -
                                         NC: 2025:KHC-D:17929-DB
                                         RFA No. 100181 of 2019
                                     C/W RFA No. 100179 of 2019
                                         RFA No. 100180 of 2019
HC-KAR




    h) The work was to be done by the plaintiff as against the

         payment received by them;


    i) The time was essence of the contract;


    j) The plaintiff did not provide good materials as per the

         specification, the quality and performance of the work

         was also not good.          The defendant had to make

         alternative arrangement;


    k) The plaintiff is liable to pay the amount spent by the

         defendant to complete the work and the loss and

         damages suffered on account of breach of contract

         committed   by   the   plaintiff.   Hence,   the   defendant

         maintained the suit against the plaintiff for recovery of

         Rs.1,37,51,350/- together with court cost and interest.


    3.4      The contention of the bank - Vijay Souhard Credit

Sahakari Limited, Mudhol (as per the plaint averments in O.S.

No.103/2012):


    a)       On 12.4.2012 by oversight, the bank transferred a

sum of Rs.24,40,461/- to the bank account of the plaintiff by

RTGS;
                                   - 11 -
                                           NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




    b)      The said mistake came to light on the same day and

it was informed to the plaintiff over phone explaining the details

of RTGS wrongly sent and requested to refund the amount;


    c)      The plaintiff did not oblige to the request of the bank.

Hence, they maintained the suit for recovery of Rs.24,40,461/-

from the plaintiff together with court cost and interest.


     4      Based on the pleadings of the parties, the trial court

has framed the following issues:

      In O.S. No.8/2013:


      1. Whether plaintiff proves that, they have supplied the
         materials of an amount of Rs.2,02,49,633/- to the
         defendant from 01-04-2010 to 10-09-2011 and
         defendant have paid Rs.1,72,92,081/- to them?

      2. Whether plaintiff proves that, they have carried out
         entire work of 1st Phase and started work of 2nd
         Phase?

      3. Whether plaintiff proves that the defendants are in
         due of Rs.29,57,552/- to their company?

      4. Whether plaintiff is entitled for the reliefs sought for?

      5. What order or decree?

In O.S. No.13/2013:

      1. Whether plaintiff proves that, the defendant was failed
         to perform his part of contract well within the time?
                                  - 12 -
                                          NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
HC-KAR



     2. Whether plaintiff proves that, due to non performance
        of contract on the part of defendant they have got
        done the remaining work through Newcon Engineers,
        Dharwad by spending an amount of Rs.1,37,51,350/-?

     3. Whether plaintiff is entitled for the reliefs sought for?

     4. What order or decree?


     In O.S. No.103/2012:

     1. Whether plaintiff proves that, they have received a
        request to Sri.M.G.Langoti for remitting an amount of
        Rs.24,40,461/- in his bank account in Syndicate Bank
        Kittur through RTGS?

    2. Whether the plaintiff further proves that, while editing
       the RTGS format in the computer by oversight only
       amount portion was edited and other details were
       pertaining to the defendant company?

    3. Whether defendant proves that this court is not having
       jurisdiction to entertain this suit as per the provisions
       of Sec 17 (2) of Securitisation and Reconstruction of
       Financial Assets and Enforcement of Security Interest
       Amendment Act 2004?

    4. Whether defendant proves that, suit is bad for non-
       joinder of necessary party?

    5. Whether plaintiff bank is entitled for the relief sought
       for?

    6. What order or decree?


    5      The parties to the suit have seriously contested all

the three suits. All these suits were tried before one court i.e,

the learned Additional Senior Civil Judge and JMFC, Mudhol. The
                                   - 13 -
                                           NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




trial court disposed of these suits by rendering separate

judgments, which were pronounced on the same date. The trial

court decreed the suit in O.S. No.8/2013 and dismissed other

two suits.


     6       Sri   Sangram    S     Kulkarni,   learned    counsel   for

defendant-Nirani Sugars Limited submitted that the trial Court

has failed to properly appreciate oral and documentary evidence

available on record in the light of the pleadings of the parties and

thereby grossly erred in dismissing their suit and decreeing the

suit of Spaco Corporation. He has drawn the attention of this

Court to the finding recorded by the trial Court in OS.No.13/2013

that due to non- completion of civil work by the defendant, the

plaintiff could not complete their work and despite proceeded to

hold that the plaintiff has completed all the works entrusted to

them. He further submitted that the trial court has drawn

adverse inference against them based on release/payment of

certain amount to the plaintiff, which was paid as per the

commercial    terms   and    conditions    in   purchase   orders.   He

submitted that the trial court has not properly considered the

contents of minutes of meeting produced at Ex.P9 and proceeded
                               - 14 -
                                       NC: 2025:KHC-D:17929-DB
                                       RFA No. 100181 of 2019
                                   C/W RFA No. 100179 of 2019
                                       RFA No. 100180 of 2019
HC-KAR




to hold that they have placed purchase order with Newcon

Engineers without intimating the plaintiff in that regard. In view

of the same, he contended that the impugned judgments and

decrees passed in these suits are liable to be set aside and the

suit in O.S.No.13/2013 is to be decreed as prayed for.


     7     Sri Nandakumar Anna Vhatkar, learned Counsel for

the plaintiff has supported the findings recorded by trial Court as

well as the conclusion arrived at by the said court on the ground

that the plaintiff has adduced ample evidence before the trial

Court to prove their case. He submitted that the defendant has

not adduced any acceptable evidence before trial Court either to

show that the plaintiff has not completed the work entrusted to

them or to show any deficiency in the work carried out by the

plaintiff. He further submitted that the defendant has admitted

the plaintiff having supplied the materials as per the purchase

orders and the plaintiff could not complete the work because of

non-completion of civil work by the defendant. In the said

circumstances, he contended that the impugned judgments and

decrees do not need any interference at the hands of this Court.
                                      - 15 -
                                                NC: 2025:KHC-D:17929-DB
                                              RFA No. 100181 of 2019
                                          C/W RFA No. 100179 of 2019
                                              RFA No. 100180 of 2019
HC-KAR




       8         On behalf of the bank, learned counsel Sri Sangram

S Kulkarni submitted that the trial court has failed to understand

the contention put forth by the plaintiff, who set up a claim of

adjustment against the amount, which was wrongly credited to

their account by the bank and submitted that the trial court has

grossly erred in not taking into account separate entity of the

bank       and    the    defendant     as     well     as   absence    of     any

communication from the defendant to the bank to make such

payment on their behalf. In view of the same, he contended that

the    trial     Court   ought    to     have        decreed   their   suit    in

O.S.No.103/2012 as prayed for.


       9         On hearing the parties to the proceedings and

considering the materials on record, the following points would

arise for the consideration this Court:


            1. Whether the trial court is justified in holding that
                 Spaco Corporation has proved that they have
                 completed entire work entrusted to them and Nirani
                 Sugars Limited was due a sum of Rs.29,57,552/- to
                 them as on the date of the suit?

            2. Whether the trial court is justified in holding that
                 Nirani Sugars Limited has failed to prove, having
                 incurred an additional liability of Rs.1,37,51,350/-
                                      - 16 -
                                                NC: 2025:KHC-D:17929-DB
                                              RFA No. 100181 of 2019
                                          C/W RFA No. 100179 of 2019
                                              RFA No. 100180 of 2019
 HC-KAR



               on account of non completion of the work entrusted
               to Spaco Corporation?

            3. Whether the trial court is justified in holding that the
               transfer of Rs.24,40,461/- by Vijay Souhard Credit
               Sahakari    Limited     to     the   account   of   Spaco
               Corporation was at the instance of Nirani Sugars
               Limited and towards their out-standing dues?

            4. What Order?


     10       On examining the case papers, it becomes evident

that the dispute involved in these suits primarily concerns the

plaintiff   and    the    defendant      regarding     the    completion   or

otherwise of the work entrusted by the defendant to the

plaintiff, pursuant to the purchase orders dated 08.09.2010 and

23.08.2011. The materials on record indicate that referring to

the pleadings of both the plaintiff and the defendant would aid in

understanding their respective contentions and help minimize

the scope of the dispute.


     11       The averments of the plaint in O.S.No.8/2013 and

the written statement filed in O.S.No.13/2013 go to show that

the sum and substance of the contention of the plaintiff is as

under:
                                    - 17 -
                                                 NC: 2025:KHC-D:17929-DB
                                            RFA No. 100181 of 2019
                                        C/W RFA No. 100179 of 2019
                                            RFA No. 100180 of 2019
HC-KAR




    a) As per Purchase Order dated 22.07.2010, the plaintiff

         was required to supply the materials within a period of 8

         weeks i.e. by 22.09.2010. Nonetheless, the plaintiff has

         dispatched the materials to the defendant on 01.09.2010

         itself as per the letter of intent.

    b) The defendant did not pay 30% advance amount as per

         commercial terms and conditions mentioned in letter of

         intent. Therefore, the plaintiff did not supply goods of

         phase II.


    c) The defendant issued final Purchase Order on 08.09.2010

         i.e. after the material of Phase I was already supplied to

         them.

    d) Though        the    plaintiff       supplied   the   materials    on

         01.09.2010, it was lying idle on site of the defendant for

         about    one      year   due       to   non-completion    of    civil

         construction work of sugar go-down of the defendant and

         thereby the plaintiff has suffered severe loss.


    e)    The plaintiff has completed all the work in time.

         However, installation was depending on completion of

         civil work on the part of the defendant.
                                   - 18 -
                                           NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




    f) The plaintiff has completed Phase I work immediately

         after completion of civil job by the defendant.


    g) The plaintiff could not start Phase II work due to non

         receipt of advance amount.


    h) Insofar as ash handling system after issuance of letter of

         intent dated 23.07.2011 the plaintiff dispatched the

         materials on 10.08.2011.


    i) The defendant issued final Purchase Order on 23.08.2011

         i.e., after the materials were already supplied to them.


    j)   The    plaintiff   has    supplied   the   materials   worth

         Rs.2,02,49,633/- to the defendant from 01.04.2010 to

         10.09.2011.


    k) The defendant has paid only a sum of Rs.1,72,92,081/-

         till 12.04.2012.


    l) The defendant is still due a sum of Rs.29,57,552/-.


    12         Per Contra, the contention of the defendant as per

the averments of the plaint in O.S. No.13/2013 and the written

statement in O.S. No.8/2013 is as follows:
                               - 19 -
                                       NC: 2025:KHC-D:17929-DB
                                       RFA No. 100181 of 2019
                                   C/W RFA No. 100179 of 2019
                                       RFA No. 100180 of 2019
HC-KAR




   a) As per the terms of order the plaintiff was required to

         deliver Phase-I without eight weeks and Phase-II within

         January-2011.

   b) The plaintiff did not complete the work of sugar bag

         handling system properly and as such a meeting was

         held on 26.11.2011 in connection with its balance work

         and minutes of such meeting was reduced into writing.


   c) The plaintiff had assured to complete the balance work as

         enumerated at Sl.Nos.1 to 9 in the minutes of the

         meeting within the specifications and stipulations made

         therein.


   d) Regarding new ash handling system, a meeting was held

         on 25.12.2011 and a memorandum of minutes was

         recorded on the same date.


   e) The plaintiff had assured to complete the pending work

         as enumerated at Sl.Nos.1 to 7 of the minutes of the

         meeting.


   f) In spite of assurance given in such meetings the plaintiff

         did not execute and complete the work as agreed upon.
                                   - 20 -
                                            NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




   g) In       the   above    circumstances,       on   21.05.2012    the

         defendant issued a fresh work order to Newcon Engineers

         for   designing,    fabrication,   modifications,    alterations,

         erection    and    commissioning     of   existing   sugar   bag

         assembling, etc.


   h) The defendant got the balance work done through

         Newcone Engineers, which was not done by the plaintiff

         as agreed upon, to an extent of Rs.16,00,000/-.


   i) As the plaintiff did not perform their part of contract, the

         defendant had to pay more than Rs.1,01,16,750/- for the

         work of sugar bag handling system and Rs.36,34,600/-

         for ash handling system.


   j) The plaintiff did not execute the work as against the

         payments received by them and as such the defendant

         incurred additional liability of more than Rs.1,37,51,350/.


   k) As per the terms of the contract between the plaintiff and

         the defendant, the time was essence of the contract.
                                   - 21 -
                                            NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




    l) The plaintiff has not provided good materials as per the

          specifications. The quality and the performance of the

          work by the plaintiff was also not good.


    m) The defendant incurred heavy expenditure for making

          alternative arrangement and compelled to get the work

          done through some other agency.


    n) The plaintiff was liable to indemnify the defendant for the

          loss and damage caused on account of breach of contract

          committed by them.


     13       The pleadings of the plaintiff, as narrated above,

make it clear that even according to the plaintiff, they had not

commenced the work of Phase-II due to non-receipt of the

advance     amount.    Further,   they     have   contended   that   the

materials supplied by them on 01.09.2010 remained idle at the

defendant's site for over a year owing to the alleged non-

completion of the civil construction work of the defendant's

sugar go-downs. Thus, it becomes evident that the plaintiff's

claim of having completed all their work on time is not correct.
                                 - 22 -
                                           NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
HC-KAR




     14    In   addition   to   the      above,   the   defendant   has

specifically averred in their pleadings that two meetings were

held between the representatives of the plaintiff and the

defendant on 26.11.2011 and 25.12.2011 regarding the non-

completion of the work entrusted to the plaintiff. In support of

this contention, the defendant has produced the minutes of

these meetings before the Court. The plaintiff has not seriously

disputed the genuineness of these documents; instead, they

have merely contended that Sri N. N. Gurav, a partner of the

plaintiff firm, was not present at those meetings.


     15    Admittedly, the documents in question bear the

signatures of the representatives of both parties. In these

documents, the plaintiff was represented by Sri Belgar and Sri

Umare. The contents of the documents indicate that after

discussions between the representatives of both sides, the

balance work to be attended to by the plaintiff was recorded,

along with an assurance from the plaintiff's side to complete the

said work within the time specified therein. It is not the case of

the plaintiff that they have completed the work as agreed upon

in the meetings held on 26.11.2011 and 25.12.2011. In view of
                                 - 23 -
                                         NC: 2025:KHC-D:17929-DB
                                         RFA No. 100181 of 2019
                                     C/W RFA No. 100179 of 2019
                                         RFA No. 100180 of 2019
 HC-KAR




the same, it should be held that the plaintiff has utterly failed to

establish their contention of having executed the entire work

entrusted to them by the defendant.


     16      It is the definite case of the plaintiff that pursuant to

the purchase orders, they have supplied the materials worth

₹2,02,49,633/- to the defendant between 01.04.2010 and

10.09.2011. In support of this contention, the plaintiff has

produced     several   documents     including   extracts   of   ledger

accounts, invoices, bills, delivery challans, gate pass receipts,

and copies of letters addressed to the defendant. To start with,

the total value of the purchase orders placed with the plaintiff is

only ₹1,52,00,000/- (i.e., ₹95,00,000/- plus ₹57,00,000/-). In

contrast, the plaintiff claims to have supplied materials worth

₹2,02,49,633/-, which far exceeds the total value of the

purchase orders. Further, it is the case of the plaintiff that the

materials relating to the suit transactions were dispatched to the

defendant for the first time on 01.09.2010. Whereas, the

statement of accounts produced by the plaintiff commences with

an entry showing an opening balance as on 01.04.2010 and

reflects   transactions   between 01.04.2010       and 18.08.2010.
                                   - 24 -
                                           NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
 HC-KAR




Added to above, a majority of the documents placed on record

by the plaintiff pertain to the year 2009. Thereby, it is evident

that the plaintiff has failed to substantiate their claim.


     17     According to the plaintiff, the defendant had paid a

total sum of Rs. 1,72,92,081/- to them up to 12.04.2012. The

defendant has not disputed this assertion of the plaintiff except

with regard to the alleged last payment made on 12.04.2012

through RTGS. The defendant has also admitted having received

certain   materials    supplied       by   the   plaintiff.   In   these

circumstances, it was incumbent upon the plaintiff to adduce

sufficient evidence to establish the actual quantity of materials

supplied to the defendant, their corresponding value, and the

payments received, in order to substantiate the alleged balance

dues. However, the materials on record reveal that the plaintiff

has failed to discharge the initial burden cast upon them in this

regard.


     18     Coming to the contention of the plaintiff regarding

the receipt of Rs. 24,40,461/- from the defendant towards the

alleged dues by way of RTGS, the defendant has out-rightly

denied having transferred any such amount to the plaintiff.
                                - 25 -
                                        NC: 2025:KHC-D:17929-DB
                                        RFA No. 100181 of 2019
                                    C/W RFA No. 100179 of 2019
                                        RFA No. 100180 of 2019
HC-KAR




Further, the bank has stated that the said amount was credited

to the plaintiff's account by mistake and constituted a wrong

credit. In the suit filed by the bank for recovery of the said

amount, the plaintiff has taken the stand that the credit was not

erroneous but a valid transfer made under the instructions of

the defendant. However, during cross-examination, Sri N. N.

Gurav, the partner of the plaintiff firm, categorically admitted

that there was no communication from the defendant indicating

the transfer of Rs. 24,40,461/- towards their dues. Hence, it

becomes evident that the transfer of Rs. 24,40,461/- to the

plaintiff's bank account was nothing but a wrong credit given by

the bank through oversight.


    19     The   plaintiff   has   sought   to   justify   the   above

contention on the ground that although the amount in question

was transferred to their account on 12.04.2012 through RTGS,

there was no communication from the bank regarding any

alleged wrong credit for a considerable period and that the bank

has failed to adduce sufficient evidence to establish that the

transfer was made by mistake. However, the materials on
                                  - 26 -
                                          NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
 HC-KAR




record clearly indicate that this contention of the plaintiff is

palpably false.


     20       It is because admittedly the plaintiff has written a

letter on 18.4.2012 to the Executive Director of the defendant

on 18.04.2012 and has sent a copy of the said letter to the

bank.     The said letter has been produced before the Court by

the bank as Ex.P8 in O.S.No.103/2012. It reads as follows :


          "Kind attention Mr. Sangamesh Nirani

Dear Sirs,

      We acknowledge with thanks the receipt of an amount of
Rs.24,40,461-00 (Rupees Twenty Four lakhs Forty Thousand Four
hundred Sixty One only) from Vijay Souhard Credit Sahakari Limited
towards our outstanding payment.

      We have credited the said amount to your account with us and
we are kindly requested to please credit the said amount to M/s. Vijay
Souhard Credit Sahakari Limited (emphasis supplied) and obliged.


          Thanking you,
                                                  Yours Faithfully,
                                                 For Spaco Corporation
                                                        Sd/-
                                                     (N.N.Gurav)
                                                 Authorised Signatory"

     21       The highlighted portion of the letter indicates an

implied admission on the part of the plaintiff that as on

18.04.2012, they were aware of the wrong credit made to their
                                   - 27 -
                                             NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




account by the bank, as well as of the bank's request to refund

the said amount. Otherwise, there would have been no occasion

for the plaintiff to request the defendant to credit the amount to

the bank. Moreover, if the plaintiff had in fact received Rs.

24,40,461/- through a valid transfer made at the defendant's

instructions, there would have been no necessity for them to

address a letter to the defendant requesting that the said

amount be credited to the bank. Thus, the materials on record

clearly indicate an implied admission on the part of the plaintiff

of having received the said amount as a result of a wrong credit.

Despite such knowledge, the plaintiff not only failed to refund

the amount to the bank but also unlawfully retained it by

advancing untenable contentions. Consequently, it is held that

the bank has established its entitlement to recover a sum of Rs.

24,40,461/- from the plaintiff along with interest thereon at the

rate of 18% per annum from 12.04.2012 till realization, as

prayed for in the suit.


     22     Coming    to    the   suit     filed by   the   defendant   in

O.S.No.13/2013,      they     have         sought     for   recovery    of

Rs.1,37,51,350/- from the plaintiff together with court cost and
                                    - 28 -
                                            NC: 2025:KHC-D:17929-DB
                                            RFA No. 100181 of 2019
                                        C/W RFA No. 100179 of 2019
                                            RFA No. 100180 of 2019
HC-KAR




interest on the ground that the failure on the part of the plaintiff

to complete the work within stipulated time and failure to

provide good materials as per the specification, caused heavy

loss to them. The defendant has quantified their loss under

following heads:


         " Part-I (Ash Handling)

          a. There was a loss of 50 hours for which
             the unit was stopped for non-
             performance of work entrusted to the
             defendant in ash handling. Export is
             14,000/- units per hours and for 50
             hours it is 7 lakhs units and ppa rate is
             rs.2.968 per unit. Therefore, the total
             loss for 7 lakhs unit is                    Rs.50,77,600/-
          2. Labour charges borne by plaintiff
             company for 10 days with average 10
             casual labour X 3 shift at the rate of
             190 per man per day.                          Rs.57,000/-
          3. The     amount     given    to  Newcon
             Engineeer, as per work order dated
             21.05.2012 for items No.3 and 4 of
             the said work order.                        Rs.15,00,000/-
                                                Total    Rs.36,34,600/-

      Part-II (Sugar handling system)

          1. The amount borne by the plaintiff
             company     towards    payment    to
             Newcon Engineers as per work order
             No.87 dated 21.05.2012 item No.3
                                                         Rs.30,00,000/-
             and 4 of the said work order.
          2. There was a 50 hours stoppage of
             crushing and due to that there was a
             loss of approximate bags for 50
             hours.                                      Rs.70,31,250/-
          3. Payment made to labour for 50 days
             at the rate of 3 casual labour X 3
                                - 29 -
                                        NC: 2025:KHC-D:17929-DB
                                        RFA No. 100181 of 2019
                                    C/W RFA No. 100179 of 2019
                                        RFA No. 100180 of 2019
HC-KAR



            shift at the rate of 190 per man for
            50 days.                                    Rs.85,500/-
                                           Total    Rs.1,01,16,750/-
            The total amount of Part-I and II
            mentioned           above       i.e.,
            Rs.1,01,16,750/-=Rs.36,34,600/-         Rs.1,37,51,350/-



     23    Before proceeding further, it would be beneficial to

refer to the legal position relating to the claim of the damages.

In   Consolidated    Construction       Consortium      Limited        Vs

Software Technology Parks of India, reported in 2025 INSC

574, the Hon'ble Supreme Court of India while dealing with

similar dispute, has explained the legal position as under:


       "18. Section 55 of the Indian Contract Act says that
      when a party to a contract promises to do a certain
      thing within a specified time but fails to do so, the
      contract or so much of it as has not been performed,
      becomes voidable at the option of the promisee if the
      intention of the parties was that time should be of the
      essence of the contract. If time is not the essence of
      the contract, the contract does not become voidable by
      the failure to do such thing on or before the specified
      time but the promisee is entitled to compensation from
      the promisor for any loss occasioned to him by such
      failure. Further, if in case of a contract voidable on
      account of the promisor's failure to perform his
      promise within the time agreed and the promisee
      accepts performance of such promise at any time other
      than that agreed, the promisee cannot claim
      compensation for any loss occasioned by the non-
      performance of the promise at the time agreed, unless,
      at the time of such acceptance he gives notice to the
      promisor of his intention to do so.
                                - 30 -
                                        NC: 2025:KHC-D:17929-DB
                                        RFA No. 100181 of 2019
                                    C/W RFA No. 100179 of 2019
                                        RFA No. 100180 of 2019
HC-KAR



     19. Sections 73 and 74 deal with consequences of
     breach of contract. Heading of Section 73 is
     compensation for loss or damage caused by breach of
     contract. When a contract is broken, the party who
     suffers by such breach is entitled to receive from the
     party who has broken the contract compensation for
     any loss or damage caused to him thereby which
     naturally arose in the usual course of things from such
     breach or which the parties knew when they made the
     contract to be likely to result from the breach of it. On
     the other hand, Section 74 deals with compensation for
     breach of contract where penalty is stipulated for.
     When a contract is broken, if a sum is mentioned in the
     contract as the amount to be paid in case of such
     breach or if the contract contains any other stipulation
     by way of penalty, the party complaining of the breach
     is entitled whether or not actually damage or loss is
     proved to have been caused thereby, to receive from
     the party who has broken the contract reasonable
     compensation not exceeding the amount so named or
     the penalty stipulated for.

     20. A conjoint reading of Sections 55, 73 and 74
     would indicate that in a contract whether time is of the
     essence or not, if the contractor fails to execute the
     contract within the specified time, the contract
     becomes voidable at the option of the promisee and
     the promisee would be entitled to compensation from
     the promisor for any loss occasioned to him by such
     failure. However, in case of a contract where time is of
     the essence, the contract becomes voidable on account
     of the contractor's failure to execute the contract
     within the agreed time. The promisee cannot claim
     compensation for any loss occasioned by such breach
     of the contract unless he gives notice to the promisor
     of his intention to claim compensation. This is made
     more specific in Section 73. Section 74 contemplates a
     situation where penalty is provided for and quantified
     as compensation for breach of contract. In such a case,
     the party complaining of the breach is entitled to
     compensation whether or not actual damage or loss is
     proved to have been caused thereby but such
     compensation shall not exceed the quantum of penalty
     stipulated."
                               - 31 -
                                       NC: 2025:KHC-D:17929-DB
                                       RFA No. 100181 of 2019
                                   C/W RFA No. 100179 of 2019
                                       RFA No. 100180 of 2019
HC-KAR




    24     In the present case, there is no dispute between the

parties regarding the entrustment of certain works by the

defendant to the plaintiff under the purchase orders dated

22.07.2010 and 08.09.2010. However, it is an admitted position

that there was no written contract or agreement between them

stipulating the terms and conditions governing the consequences

of failure to perform their respective obligations. Therefore, the

present claim of the defendant is required to be considered in

the light of Sections 55 and 73 of the Indian Contract Act.


    25     The first and foremost contention of the defendant is

that time was the essence of the contract. However, the

materials on record do not support this contention. As per the

understanding between the parties, the plaintiff was required to

complete the installation of the sugar bag handling system

within a period of eight weeks from the date of the purchase

order. Based on the admissions of the parties, the said work

ought to have been completed on or before 22.11.2011. It is not

the case of the defendant that upon expiry of the stipulated

period, they withdrew the work entrusted to the plaintiff or

raised any formal protest. On the contrary, even according to
                               - 32 -
                                       NC: 2025:KHC-D:17929-DB
                                       RFA No. 100181 of 2019
                                   C/W RFA No. 100179 of 2019
                                       RFA No. 100180 of 2019
HC-KAR




the defendant, a joint meeting was convened on 26.11.2011 to

discuss the pending work, during which the plaintiff assured

completion of the balance work by 05.12.2011. It is significant

to note that the minutes of the meeting dated 26.11.2011

contain no reference to the time stipulated for completion being

treated as the essence of the contract.


    26     It is well settled that when time is of the essence in

a contract, the contract becomes voidable if the promisor fails to

perform within the stipulated period. In such a case, the

promisee cannot claim compensation for any loss caused by the

breach unless a notice is given to the promisor expressing the

intention to claim such compensation. In the present case, the

defendant has not stated anything about having given notice to

the plaintiff regarding their intention to claim compensation,

either during the discussion held on 26.11.2010 or at any

subsequent time.


    27     In the aforesaid decision, the Hon'ble Supreme Court

of India has held that a conjoint reading of Sections 55, 73, and

74 of the Indian Contract Act indicates that in a contract,

whether or not time is of the essence, if the promisor fails to
                                  - 33 -
                                            NC: 2025:KHC-D:17929-DB
                                          RFA No. 100181 of 2019
                                      C/W RFA No. 100179 of 2019
                                          RFA No. 100180 of 2019
HC-KAR




execute the contract within the stipulated period, the contract

becomes voidable at the option of the promisee. In such a

situation, the promisee would be entitled to claim compensation

from the promisor for any loss sustained by such failure.

Accordingly, it becomes necessary for this Court to examine

whether the defendant's claim for compensation is directly

attributable to the alleged breach of contract.


     28       The defendant's claim reveals that compensation has

been sought under several heads namely loss of 50 hours of

operational    time   due   to   stoppage    of   the   unit, for   non-

performance of the work entrusted to the defendant in ash

handling, labour charges incurred by them, the amount paid to

Newcon Engineers for completing the work under the work order

dated 21.05.2012, and loss on account of 50 hours of stoppage

in crushing operations. A prima facie examination of these

claims indicates that most of them bear no direct nexus with the

alleged non-completion of the work order. Moreover, it is

incumbent upon the defendant to place sufficient evidence on

record to establish the actual loss, if any, suffered due to the
                                     - 34 -
                                              NC: 2025:KHC-D:17929-DB
                                             RFA No. 100181 of 2019
                                         C/W RFA No. 100179 of 2019
                                             RFA No. 100180 of 2019
 HC-KAR




plaintiff's    alleged     non-performance           of     the     contractual

obligations.


     29        It is the definite case of the defendant that on

21.05.2012, they issued a fresh work order to Newcon Engineers

for designing, fabrication, modification, alteration, erection, and

commissioning of the existing sugar bag and ash handling

systems. A copy of the said work order has been produced

before the trial court. It is pertinent to note that the work order

dated 21.05.2012 does not make any reference to the work

allegedly left unfinished by the plaintiff. Furthermore, in their

pleadings, the defendant has not made any mention of having

issued a work order for completion of the unfinished work of the

plaintiff. This aspect creates an impression that the work

entrusted to Newcon Engineers was an independent contract

undertaken by the defendant as per their own requirement.


     30        In addition to the above, the said work order

specifies     that   the   labour   charges    for        design,   fabrication,

modification, alteration, erection, and commissioning were fixed

at Rs.80,00,000/-. However, the defendant has claimed a total

amount of Rs.1,37,51,350/- under various heads including
                               - 35 -
                                       NC: 2025:KHC-D:17929-DB
                                       RFA No. 100181 of 2019
                                   C/W RFA No. 100179 of 2019
                                       RFA No. 100180 of 2019
HC-KAR




losses said to have been occasioned due to stoppage of crushing

operations and non-utilization of the unit. The defendant

examined one of the technicians of Newcon Engineers, Sri Kunal

as PW-3 in support of their case. During his deposition, PW-3

merely stated that the defendant had entrusted the work of the

sugar bag handling system in 2012, which had been left

incomplete by the plaintiff and that Newcon Engineers had

completed it. However, PW-3 has not given any definite

statement regarding either the total cost of the said work or the

actual amount paid by the defendant to Newcon Engineers.

Further, neither the defendant nor PW-3 has produced any

supporting document before the trial court such as quotations,

purchase orders, or other records, to show the actual cost of the

work entrusted to Newcon Engineers.


    31     It is relevant to note that in paragraph 8 of the plaint

in O.S. No.13/2013, the defendant specifically averred that the

balance work, which was not completed by the plaintiff as

agreed, had been executed at a cost of Rs.16,00,000/-. This

averment was reiterated by Sri Mahesh, the Deputy General

Manager of the defendant, during his evidence. Thus, the
                                - 36 -
                                             NC: 2025:KHC-D:17929-DB
                                        RFA No. 100181 of 2019
                                    C/W RFA No. 100179 of 2019
                                        RFA No. 100180 of 2019
 HC-KAR




materials on record probabilise that the defendant incurred only

a sum of Rs.16,00,000/- towards completing the work left

unfinished by the plaintiff to make the facility operational.


     32      The question of awarding compensation would arise

only when the promisee establishes that they have sustained a

loss due to breach of contract by the promisor. As already

pointed out, it appears from the record that the defendant

incurred only a sum of Rs.16,00,000/- to complete the work left

unfinished by the plaintiff. However, this by itself cannot be

construed as a loss suffered by the defendant. This is because

the defendant has neither claimed to have made full payment to

the plaintiff in advance nor shown that engaging another agency

to complete the unfinished work compelled them to incur any

additional expenditure.    Hence,       it   must   be   held   that   the

defendant has not established having spent any additional

amount to complete the balance work left unattended by the

plaintiff.


     33      The defendant has also attempted to contend that

the work executed by the plaintiff did not conform to the agreed

specifications and quality standards. However, it is not the case
                                     - 37 -
                                               NC: 2025:KHC-D:17929-DB
                                             RFA No. 100181 of 2019
                                         C/W RFA No. 100179 of 2019
                                             RFA No. 100180 of 2019
HC-KAR




of the defendant that during the meetings held on 26.11.2011

and    25.12.2011,         any    discussion     took    place    regarding

deficiencies    in   the   specifications,     quality   of   materials,   or

workmanship of the plaintiff. In light of the above, this

contention of the defendant cannot be accepted.


      34       The defendant has claimed that they are entitled to

compensation under Section 74 of the Indian Contract Act. The

said provision is attracted only when there exist a written

agreement between the parties stipulating a penalty for breach

of contract. In the present case, the defendant has not produced

or even pleaded the existence of any such contract containing

specific terms and conditions regarding penalties for breach. For

the foregoing reasons, it is held that the defendant has failed to

establish any valid ground to claim compensation from the

plaintiff for their failure to complete the entrusted work within

the stipulated period.           Accordingly, Point Nos.1 and 3 are

answered in the negative and Point No.2 in the affirmative.


      35       In the result, this Court proceeds to pass the

following:
                                   - 38 -
                                             NC: 2025:KHC-D:17929-DB
                                           RFA No. 100181 of 2019
                                       C/W RFA No. 100179 of 2019
                                           RFA No. 100180 of 2019
HC-KAR




                                  ORDER

i. The appeals in RFA Nos.100179/2019 and 100180/2019 are allowed with cost throughout. ii. The appeal in RFA No.100181/2019 is dismissed.

iii. The judgment and decree dated 11.01.2019 passed in O.S. No.8/2013 by learned Additional Senior Civil Judge and JMFC, Mudhol is set aside and consequently the said suit, i.e. O.S. No.8/2013, is dismissed. iv. The judgment and decree dated 11.01.2019 passed in O.S. No.13/2013 by learned Additional Senior Civil Judge and JMFC, Mudhol, is confirmed.

v. The judgment and decree dated 11.01.2019 passed in O.S. No.103/2012 by learned Additional Senior Civil Judge and JMFC, Mudhol is set aside and consequently, the said suit, i.e. O.S. No.103/2012, is decreed.

- 39 -

NC: 2025:KHC-D:17929-DB RFA No. 100181 of 2019 C/W RFA No. 100179 of 2019 RFA No. 100180 of 2019 HC-KAR vi. The defendant in O.S. No.103/2012 namely Spaco Corporation is directed to pay a sum of Rs.24,40,461/- to the Plaintiff therein namely Vijay Souhard Credit Sahakari Limited together with interest thereon at the rate of 12% per annum from 12.04.2012 till the date of its realization.

Sd/-

(R.DEVDAS) JUDGE Sd/-

(B. MURALIDHARA PAI) JUDGE VB, CKK/ CT-AN List No.: 1 Sl No.: 1