State of Gujarat - Section

Section 3 in Gujarat Electricity Regulatory Commission (Licensee's Power to Recover Expenditure incurred in providing supply and other Miscellaneous Charges) Regulations, 2005

3. Duty of the Distribution Licensee to Supply Electricity on Request and Recovery of Expenditure.

- (i) The Distribution Licensee shall, subject to the provisions contained in Section 43 of the Act, fulfill his obligation to supply electricity to the premises of consumers.
(iii)Subject to the provisions of the Act and these Regulations and subject to such directions, orders or guidelines as the Commission may issue from time to time, every Distribution Licensee is allowed to be recovered from an applicant, requiring supply of electricity, any expenses that the Distribution Licensee shall be required to reasonably incur to provide any electric line or electrical plant specifically for the purpose of giving such supply to the applicant.
(vi)The Licensee shall lay free of charge a service line (overhead line or underground cable depending upon the type of distribution system existing) up to a length of 30 meters from its nearest distributing main on public roads, outside the limits of the property in respect of which requisition for electricity supply is received.
(vii)The entire service line, notwithstanding that a portion thereof has been paid for by the Consumer, shall be the property of the Distribution Licensee and by whom it shall be maintained and the Distribution Licensee have a right to use it for the supply of energy to any other person by taping the service or otherwise except if such supply is detrimental to the supply to the consumer already connected therewith.