"On 30th & 31st March, 1993, for the first time, an attempt has been made only to check whether the production unit that is the reactor is in a position to work or not. All the operations carried out on these two dates only amount to testing the various operations and parts of the reactor and reduction system and these were found to be defective, unworkable and even incomplete in terms of fabrication reference to the clear writing by the company to M/s. Davy Power Gas on 31st March, 1993 that there were designing defects in the plant hence they could not commission it. After realising this, the plant was shut down and the shutting down procedure started from 21st March, 1993 itself (the next attempt to start up the plant is only in and April, 1993) when inert gas was sent to the reactor. Yet by fabricating and manipulating the documents, the figures and test reports, there is a deliberate attempt to claim commercial production and consequently depreciation."