contract or assign his obligations or any benefit or interests in the Contract or any part thereof in any manner whatsoever. Any such assignment shall not absolve the Contractor from his obligations and responsibilities under this Contract.

5.10.2 If the Company is satisfied that the entire Works have been completed as specified in 5.10.1 above and have successfully passed all tests provided in the Contract then the Company shall issue within fourteen working days a Certificate of Completion and Acceptance which certificate shall be effective from the completion date which the Contractor had notified to the Company subject to the Company's Representative certifying that the entire Works were completed by the Contractor without any defect on the said notified completion date except for the Punch List items.


                 Scope of EPC (LSTK) within RFSU
                      Preparation of the Process Design Package
                      Residual Basic Engineering
                      Detailed Engineering
                      Management Control of all procurement activities
                       of all materials
                      Fabrication, construction, installation, testing etc.
                      Trial run and Pre-commissioning
                      Obtaining statutory approvals as far as in
                       Contractor's scope and required prior to
                       Commissioning
                      Project Management and Support services
                      Carrying out of function tests of individual
                       equipment
                      Preparation of start up and operating manuals
                      Management of HSE including Hazop, DMP etc.

                 Scope of EPC (LSTK) Contractors after RFSU
                     Commissioning of the Plant
                     Performance Test Runs for the Plants
                     Remaining training activities



                       Providing as built drawings
                      Supply of all test report,
                      Post commissioning services for six months as per
                       Clause 2.4.11
                      Working for punch list item,
                      Working for any warranty obligations
                      Training of operators within Post Commissioning
                       Services"