passed by Consumer Grievance Redressal Forum (hereafter referred to as "CGRF") denying refund of Rs. 14.44 lacs to respondent no. 3. The Ombudsman ... aside the order of CGRF to the extent it denies refund of Rs. 14.44 lacs to petitioner and has held that petitioner is not liable
order dated 31.08.2009
passed by the Consumer Grievance Redressal Forum (CGRF) for NDPL
on a complaint filed by the respondent No.1/Consumer for refund ... Consumer filed a complaint case before the Consumer Grievance
Redressal Forum (CGRF) praying inter alia for refund of the excess
amount
order dated 13.04.05 was
passed in a petition challenging the order of CGRF.
Therefore, the Commission has exercised appellate
jurisdiction over an order of CGRF ... There is no dispute that
the CGRF which was constituted on 12.05.04 was the right
forum which heard the Respondent's application regarding
order dated 31st August, 2009 of the Consumer Grievance Redressal Forum
(CGRF) holding the complaint preferred by the appellant to CGRF to be not
barred ... limitation.
2. The appellant had approached the CGRF in the year 2009 with the
complaint that the appellant had on 27th July, 1992 approached
which the
Consumer Grievance Redressal Forum (herein after referred to as CGRF)
had called upon the petitioner to appear before the CGRF ... receipt of this notice, the petitioner had made an application to the
CGRF raising a preliminary objection with regard to the maintainability
of the complaint
liberty to the consumers to approach the Consumer
Grievance Redressal Forum ("CGRF") for redressal of
individual grievances.
Page ... Accordingly, the Applicant filed an application
before the CGRF claiming refund of about Rs. 26 lacs.
deposited as arrears on the demand raised
whether the Petitioner is entitled to claim HT-I, Tariff, the CGRF
held that the activity of bottling plant of LPG was not a manufacturing ... activity.
8 Aggrieved by the aforesaid order of the CGRF, the Petitioner
filed Representation No.82 of 2011 under Section 42(6) of the Electricity
petitioner approached the Consumer Grievance Redressal
Forum, Kozhikode (for short 'CGRF') by filing O.P. No. 44/2011-
12. The CGRF ... findings entered into by the CGRF is as follows:
" As per the prevailing rules electricity cannot be
denied to a consumer for long
EXHIBITS
---------------------------------------
EXHIBIT P1: TRUE COPY OF THE ORDER PASSED BY THE CGRF IN O.P.42/2012
DATED 27.12.2012.
EXHIBIT P2: TRUE COPY ... property had approached the Consumer
Grievance Redressal Forum ( for short "CGRF" only), the
order in which was challenged before the Ombudsman
and then
other matters which would fall outside the jurisdiction of CGRF and the
Special Court established under Section 153 of the 2003 Act, such as
matters ... Supply Code 2005 details the disputes which fall
within the jurisdiction of CGRF. These Supply Code Regulations 2005
has not been challenged