Search Results Page
Search Results
1 - 10 of 12 (0.38 seconds)The Indian Electricity Act, 1910
Section 14 in The Electricity Act, 2003 [Entire Act]
Section 9 in The Indian Contract Act, 1872 [Entire Act]
Section 7 in The Electricity Act, 2003 [Entire Act]
Section 8 in The Electricity Act, 2003 [Entire Act]
Section 9 in The Electricity Act, 2003 [Entire Act]
Section 111 in The Electricity Act, 2003 [Entire Act]
Rajasthan State I.D.I.Corpn. Ltd. & Anr vs Diamond & Gem Dev. Corpn. Ltd. & Anr on 12 February, 2013
9.11 that the power purchase agreement dated 24.02.2006
executed between KEPIP and KSEB for the supply of Power
to KEPIP was formally terminated with effect from
31.05.2013 only . Therefore it is evidently clear that till
31.05.2013 the power purchase agreement dated
24.02.2006, between KSEB and KEPIP was valid and
holding the field and KSEB was legally entitled to enforce the
PPA as a matter of right and nobody can find fault with it.
9.12 that neither the Court nor the arbitrator or any other agency
create a contract if the parties have not made it themselves
that the terms of the contract have to be construed strictly
without altering the nature of the contract, as it may affect the
interest of either of the parties adversely.
9.13 that Hon'ble Supreme Court has held in 2013 (5) SCC 470,
Rajasthan Sate Industrial Development and Investment
Page 15
ss
Appeal No. 104 of 2015
Corporation Limited Vs. Diamond and Gem Development
Corporation Limited that: