Search Results Page

Search Results

1 - 10 of 20 (0.30 seconds)

Board Of Control For Cricket In India vs Deccan Chronicle Holding Limited on 16 June, 2021

3. Learned counsel for the petitioner further submits that a counter claim in the sum of Rs.7.5 crores was also passed in favour of the petitioner. Learned counsel on instructions submits that he is challenging the finding of the learned arbitrator regarding grant of Rs.15.9 Crores on account of mesne profit for withholding the possession for the period from 01.07.2019 to 30.11.2023 @ Rs.30 lakhs per month. Learned counsel for the petitioner submits that the learned arbitrator has mentioned that no evidence has been led in this behalf by either of the parties and therefore the learned arbitral tribunal has wrongly resorted to guess work for reaching the figure of Rs.30 lakhs per month. Learned counsel for the petitioner submits that therefore the award to this extent is liable to be set aside. Learned counsel for the petitioner in support of his contention has relied upon Board of Control for Cricket in India vs. Deccan Chronicle Holdings Ltd. 2021 SCC OnLine Bom 834, National Radio & Electronic Co.Ltd.
Bombay High Court Cites 94 - Cited by 5 - G S Patel - Full Document

Fateh Chand vs Balkishan Das on 15 January, 1963

It is apparent from the aforesaid reasoning recorded by the Arbitral Tribunal that it failed to consider Sections 73 and 74 of the Indian Contract Act and the ratio laid down in Fateh Chand case [Fateh Chand v. Balkishan Dass, AIR 1963 SC 1405 : (1964) 1 SCR 515] wherein it is specifically held that jurisdiction of the court to award compensation in case of breach of contract is unqualified except This is a digitally signed order.
Supreme Court of India Cites 7 - Cited by 574 - J C Shah - Full Document

Edifice Developers And Project ... vs M/S. Essar Projects (India) Ltd on 3 January, 2013

In Edifice Developers & Project Engineers Ltd. v. Essar Projects (India) Ltd., 2013 SCC OnLine Bom 5, the Division Bench of Bombay High Court was considering an appeal against the order of learned Single Judge. Learned Single Judge while deciding the challenge against the arbitral award, affirmed the award of Arbitral Tribunal in so far as it allowed the claim in respect of the retention money in the amount of Rs.1,01,43,000/- holding that the claim arose out of the contract and the conclusion which was arrived at by the learned arbitrator was a possible conclusion to be drawn on the basis of the material. Learned Single Judge while considering the challenge against the arbitral award besides affirming the award under the head of claim in respect of retention money, set aside the arbitral award in respect of remaining claims. It is pertinent to mention here that appellant claimed This is a digitally signed order.
1   2 Next