entities was awarded a contract by
the Mumbai Metropolitan Development Authority (MMRDA) a project of
public importance, namely the "Mumbai Trans Harbour Link Project ... petitioner
qua the advance amounts received by the petitioner from the MMRDA as
per the terms of the contract and remitted to its constituent
Respondent No.3.
Mr.Akshay P.Shinde, Advocate for Respondent No.4 MMRDA.
_______
CORAM : G. S. KULKARNI &
AARTI SATHE, JJ.
Judgment Reserved ... 2025 02:29:33 :::
10.WP.9804.2022.ODT
(e) Thereafter MMRDA-Respondent No. 4 was appointed as the
Planning Authority by the State Government
such prohibition, as it
pertains to land allotted to the petitioner by MMRDA on which the
petitioner has already constructed 7 residential towers ... which was allotted to the petitioner on
public bids being invited by MMRDA, as the said land was leased
to the MMRDA by the State
Hiralal & Co. for
petitioners.
Ms. Kiran Bhagalia for respondent no.1 - MMRDA.
Ms. Shital Mane-Tadke for respondent No.2 - MCGM.
Mr. Ajay Khaire ... short "MMRDA") which is impleaded as respondent no.1 to the
petition. The second grievance of the petitioners is of respondent
Hiralal & Co. for
petitioners.
Ms. Kiran Bhagalia for respondent no.1 - MMRDA.
Ms. Shital Mane-Tadke for respondent No.2 - MCGM.
Mr. Ajay Khaire ... short "MMRDA") which is impleaded as respondent no.1 to the
petition. The second grievance of the petitioners is of respondent
Hiralal & Co. for
petitioners.
Ms. Kiran Bhagalia for respondent no.1 - MMRDA.
Ms. Shital Mane-Tadke for respondent No.2 - MCGM.
Mr. Ajay Khaire ... short "MMRDA") which is impleaded as respondent no.1 to the
petition. The second grievance of the petitioners is of respondent
Salunkhe, AGP for
State.
Ms. Kiran Bhagalia with Mr. Mushraf Shaikh for MMRDA.
Mr. Vinod Mahadik for respondent No.4 - MCGM.
Mr. Mihir Desai, Senior ... executed between the State of Maharashtra, Mumbai Metropolitan
Regional Development Authority (MMRDA) and the developers. The
grant of land (State largesse) was made
Devansh Shah i/b Vidhi Partners for Respondent
No.2/MMRDA.
Mr. S. B. Gore, AGP a/w Mr. Manish Upadhye, AGP for State/Respondent ... respondent No.2/Mumbai Metropolitan Region Development
Authority, (for short "the MMRDA"). The acquisition was for a
public purpose namely for the Mumbai
Devansh Shah i/b Vidhi Partners for Respondent
No.2/MMRDA.
Mr. S. B. Gore, AGP a/w Mr. Manish Upadhye, AGP for State/Respondent ... respondent No.2/Mumbai Metropolitan Region Development
Authority, (for short "the MMRDA"). The acquisition was for a
public purpose namely for the Mumbai
Rehab and tenements
from 6th to 10 Floor were handed over to MMRDA as PAP. I say that
MCGM addressed a letter dated ... Executive Engineer,
SRA and Executive Engineer, MMRDA requesting to initiate action
against unauthorised alteration and unauthorised usage in R-11. A Copy
of the Letter