Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

Karnataka High Court

M/S Nandi Builder And Developer vs Mrs. Saraswathamma on 25 July, 2025

Author: S.G.Pandit

Bench: S.G.Pandit

                                1



      IN THE HIGH COURT OF KARNATAKA AT BENGALURU

          DATED THIS THE 25th DAY OF JULY, 2025
                           PRESENT
            THE HON'BLE MR JUSTICE S.G.PANDIT
                               AND
            THE HON'BLE MR JUSTICE T.M.NADAF
        WRIT PETITION NO.27452 OF 2024 (GM-CON)
BETWEEN:
1 . M/S NANDI BUILDER AND DEVELOPER
    NO.177/A, 22ND CROSS
    7TH B MAIN, 3RD BOCK
    JAYANAGAR
    OPP. NMKRV COLLEGE
    BANGALORE - 560 011

2 . MR. K S MURALI
    S/O K M SATYANARAYANA SHETTY
    AGED ABOUT 53 YEARS
    PROPRIETOR
    M/S NANDI BUILDER AND DEVELOPER
    NO.177/A, 22ND CROSS
    7TH B MAIN, 3RD BLOCK
    JAYANAGAR
    OPP NMKRV COLLEGE
    BANGALORE - 560 011
                                             ...     PETITIONERS
(BY SRI. RAJESH A, ADVOCATE)

AND

MRS. SARASWATHAMMA
W/O LATE A SURYA NARAYANASETTY
AGED ABOUT 84 YEARS
RESIDING AT NO.277,
WEST OF CHORD ROAD
2ND STAGE,12TH A CROSS,
MAHALAKSHMIPURAM
BANGALORE - 560 086
                                         ...         RESPONDENT

(BY SRI. VARDHAMAN V GUNJAL, ADVOCATE)
                                   2


     THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF
THE CONSTITUTION OF INDIA PRAYING TO i) ISSUE A WRIT OF
CERTIORARI OR ANY OTHER WRIT, ORDER OR DIRECTION TO QUASH
THE IMPUGNED ORDER DATED 27/05/2024 PASSED BY THE HON'BLE
NATIONAL CONSUMER DISPUTE REDRESSAL COMMISSION, NEW DELHI
VIDE ANNEXURE-A AND ALLOW THIS WRIT PETITION AND ALLOWING
THE FIRST APPEAL NO.95/2017 FILED BY THE PETITIONER BY SET ASIDE
THE FINAL ORDER PASSED ON 18/11/2016 IN COMPLAINT NO.214/2014
BY KARNATAKA STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
BANGALORE AND; ii) GRANT SUCH OTHER RELIEF OR RELIEFS AS THIS
HON'BLE COURT DEEMS FIT TO GRANT IN THE FACTS AND
CIRCUMSTANCES OF THE CASE, IN THE INTEREST OF JUSTICE AND
EQUITY.

    THIS PETITION HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT ON 16.07.2025 AND COMING ON FOR 'PRONOUNCEMENT OF
JUDGMENT' THIS DAY, T.M. NADAF J., PRONOUNCED THE FOLLOWING:

CORAM:     HON'BLE MR. JUSTICE S.G.PANDIT
           AND
           HON'BLE MR. JUSTICE T.M.NADAF

                            CAV ORDER

           ( PER: THE HON'BLE MR JUSTICE T.M.NADAF )


     This writ petition under Article-226 of the Constitution of India

is by unsuccessful respondents / opponent parties calling in question

the order dated 27.05.2024 passed by the National Consumer

Disputes Redressal Commission, New Delhi (for short 'National

Commission') vide Annexure-A and the order dated 18.11.2016 in

Complaint No.214/2014 passed by the Karnataka State Consumer

Disputes    Redressal   Commission,   Bengaluru   (for   short   'State

Commission') vide Annexure-D, whereby the National Commission

except modifying the payment of rent at Rs.10,000/- per month, for
                                   3



each apartment from 09.04.2014 to 17.02.2017 and at the rate of

Rs.20,000/- per month per apartment from 18.02.2017 till handing

over the possession of the same, after due rectification, of the said

deficiencies, and in all other respondents confirmed the order

passed by the State Commission.


     2.    A brief outline of facts leading to filing of the present

petition are as under:


     Under a Joint Development Agreement dated 09.05.2012 (for

short 'JDA') executed between the respondent herein and the

petitioners, the petitioners have agreed to construct a multi-storied

residential apartment offering respondent 50% of total super built-

up area, along with proportionate car parking area, common area,

terrace area, garden space and 50% of the benefits accrued from

the project.


     3.    Under the said agreement, it was agreed that in

exchange of 50% of benefits stated supra, the respondent has

agreed to transfer, 50% undivided property share, right, title and

interest. In furtherance of the JDA, the respondent executed a

General Power of Attorney (for short 'GPA') in favour of petitioner

No.1, in turn the petitioners have executed a sharing agreement in

favour of the respondent entitling her to specific flats and car
                                         4



parking areas. As there was default committed by the petitioners,

the respondent approached the State Commission by filing a

complaint    being   No.214/2014,           seeking   directions      against   the

petitioners to handover 50% of super built-up area, car parking

area, garden area and terrace as per JDA supra and rent at

Rs.20,000/- per month for each apartment, damages and costs as

well.


        4.   In   response   to   the       notice    issued,   the    petitioners

appeared and filed their statement of objections contending that the

respondent is not a consumer as defined under Section-2(d)(ii) of

the Consumer Protection Act, 1986 (for short 'Act of 1986'). The

JDA has been executed in furtherance of MOU dated 14.03.2012, in

the said MOU, there is a clause for referring the matter to

arbitration. Further contended that they have agreed to hand over

50% of super built-up area, however, the delay caused is due to the

respondent not producing original documents for obtaining sanction

plans and licenses, as well as force majeure such as, lorry strike and

other related situations, in ongoing project. Despite the problems

faced by the petitioners, they have completed the construction.

However, on repeated requests, the respondent has not come

forward to take possession of the property. They further denied the

assessment of rent at 20,000/- per month for each flat.
                                          5



     5.       So far as the sharing agreement is concerned, the

petitioners stated that they have acknowledged their obligation to

handover the specific flats and car parking spaces, but asserted that

the share of the respondent was ready for delivery of possession,

but there is a failure on the part of the respondent to take delivery

of possession. They have contended that there is no cause of action

for filing the complaint.


     6.       The State Commission, considering the pleadings as well

as evidence both oral and documentary, proceeded to allow the

complaint in part by its order dated 18.11.2016, with the following

directions:


                                     "ORDER"

      The Complaint is hereby allowed with cost of Rs.25,000/-

      The OPs are hereby directed to complete the project by
      rectifying    the     lapses    that    are     narrated   in    the
      Commissioner Report and to handover 50% of the super
      built up area as agreed in the Joint Development
      Agreement along with 50% of car parking area, 50% of
      garden area and 50% in terrace as described in the
      schedule.


      The complainant is entitled to recover rent at the rate of
      Rs.15,000/-     per     month     for    each    apartment      from
      09.04.2014, till the date of handing over of the possession
                                      6


        of the same by rectifying the mistakes that are pointed
        out in the Commissioner Report.


        The OPs are directed to comply with the order within a
        period of three months from the date of receipt of the
        order."


        7.   Aggrieved by the order passed by the State Commission,

both the petitioner, as well as respondent preferred separate

appeals      being   F.A.No.95/2017       and   F.A.No.2031/2018.          The

petitioners in appeal F.A.No.95/2017 sought to set-aside the order

passed by the State Commission, whereas the respondent in

F.A.No.2031/2018      sought   for   a    direction   to   pay   a   sum    of

Rs.40,00,000/- along with interest @ 18% per annum from the date

of filing of the complaint, till the date of actual payment, which is

balance goodwill amount payable to the respondent as per clause-2

of MOU dated 14.03.2012, so also for enhancement of rental

amount awarded by the State Commission from Rs.15,000/- to one

lakh.


        8.   By a common order, the National Commission disposed

of both the appeals, partly modifying the rate fixed towards rent by

the State Commission. This petition is filed only against the appeal

filed by the petitioners before the National Commission. The

petitioners before the National Commission have again contended
                                                7



that the respondent is not a consumer, within the definition

provided under the Act of 1986 and there is an arbitral clause

provided in the MOU dated 14.03.2012, and contended that the

State Commission has failed to consider the same and sought to

allow the appeal.


          9.     So far as the delay in construction is concerned, they

have urged the very same grounds, as they have urged before the

State Commission. The respondent herein contended before the

National Commission that the petitioners owe the respondent a sum

of Rs.29,52,434/- as on the date of delivery of possession of four

flats on 26.06.2018. Further, after the said order, the petitioners-

builders made a partial payment of Rs.1,00,000/- by way of Cheque

bearing No.76951, dated 26.11.2079 and Rs.2,00,000/- by Cheque

No.07967          dated      29.12.2017        and    also   deposited    a    sum   of

Rs.7,20,000/- before the State Commission in Execution No. 30 of

2017 and sought to dismiss the appeal.


          10. The National Commission, in view of the law laid down by

the       Hon'ble      Apex      Court    in    the   case    of   M/S.       IMPERIA

STRUCTURES LIMITED Vs. ANIL PATNI AND ANOTHER1 held

that the remedies under the Act of 1986 are in addition to the

1
    (2020) 10 SCC 787, dated 02.11.2020
                                         8



remedies available under the Special Statutes. So also, stating

Section-3 of the Act of 1986 which provides that the provisions of

this Act shall be in addition to and not in derogation of any other

law for the time being enforced. Further, referring to the order of

the Commission in AFTAB SINGH vs. EMAAR MGF LAND

LIMITED AND ANOTHER in Consumer Case No.701 of 2015,

vide Order dated 13.07.2007 (which was upheld by the Hon'ble

Apex Court) held that the 'Arbitration clause in the buyer's

agreement does not bar the jurisdiction of the Consumer Fora.

Accordingly, rejected the contention of the petitioners that the

complaint is not maintainable in view of the arbitration clause.


     11.   So    far   as   the   argument      on     delay,   the   National

Commission      referring   to    its   order   in   SIVARAMA         SARMA

JONNALAGADDA           AND        ANOTHER        Vs.     M/S.     MARUTHI

CORPORATION LIMITED & ANOTHER, decided on 21.09.2021,

held that the ground of force majeure is not available to deny the

delivery of possession and amounts to deficiency of service and

unfair trade practice. So far as the contention that, the respondent

is not a consumer, the National Commission relying on the

judgment of Hon'ble Apex Court in the case of BUNGA DANIEL

BABU    Vs.     M/S.   SRI,      VASUDEVA       CONSTRUCTIONS            AND

OTHERS in Civil Appeal No.944 of 2016 decided on 22.07.2016 held
                                     9



that a person who is a party to a MOU for construction and JDA

comes within the purview of definition of 'consumer' and they can

invoke the provisions under Act of 1986. The National Commission

after considering the entire case materials held that there is a

deficiency on the part of the petitioners. However, taking into

consideration the fact that there is no document produced on record

to establish the rates of rent in the area, proceeded to pass the

order confirming the judgment of the State Commission by its order

dated 27.05.2024, except with some minor modification towards

rent, which we reproduce as follows:


                              "ORDER

     I. The Opposite Parties are directed to complete the
     project after duly rectifying all deficiencies listed in the
     Court   Commissioner    Report     and   to    handover    the
     Complainant 50% of the super built up area as per the
     Joint Development Agreement along with 50% of car
     parking area, 50% of garden area and 50% in terrace as
     described in the schedule, within a period of two months
     from the date of this order, unless already handed over.

     II. The Opposite Parties are directed to pay Complainant.
     compensation in the form of rent @ of Rs.10,000/- per
     month    per   each    apartment    from      09.04.2014    to
     17.02.2017. Further rent @ Rs.20,000 per month per
     apartment from 18.02.2017 till the date of handing over of
                                    10


     the possession of the same, after due rectification of the
     said deficiencies.


     III. In the event of the apartments not being handed over
     till date, the OPs are directed to handover the possession
     of the property as per (1) above within a period of two
     months from the date of this order and the rent liability
     from the date of this order shall be @ Rs.50,000 per
     apartment per month till the date of handing over.


     IV. The OPs are also liable to pay the Complaint Rs.50,000
     as costs."


     12.   Calling in question both the orders passed by the State

Commission as well as the National Commission, the petitioners

have filed the present petition.


     13.   Heard Sri.Rajesh.A, learned counsel for the petitioners

and Sri.Vardhaman V. Gunjal, learned counsel for the respondent.


     14.   Sri.Rajesh, taking us through the papers produced in the

writ petition, has submitted that as per clause-21 of the JDA, both

the State Commission and National Commission, has no jurisdiction

to entertain the complaint, as there is a remedy provided by way of

specific performance of contract and so far as the claim of recovery

of money for the losses and damages caused, the respondent has to

approach Competent Civil Court by paying necessary court fee to

the same. He has further submitted that the National Commission
                                      11



having observed on the Court Commissioner's Report that the flats

are by and large complete when the Commissioner visited the spot

and only minor aspects listed therein were pending, erred in holding

that there is deficiency of service and directed the petitioners to pay

the rent at a reduced rate. He submits that both the State

Commission, as well as the National Commission failed to consider

that as per the commissioner report, the flats are ready for delivery

of possession, but with certain minor aspects which requires the

permission of respondent to make good. However, it is the

respondent who is not coming forward to take the delivery of

possession and sought to allow the petition setting-aside the orders

impugned and dismiss the complaint.


     15.   Sri.Gunjal   with   all   vehemence   contended   that   the

petitioners made the respondent, an octogenarian, to run around

pillar to post to seek for her rightful claim under the JDA. As per the

JDA, The petitioners ought to have completed the construction by

October'2013, with another 6 months as grace period, i.e., on or

before 09.04.2014. However, till date they have not handed over

the possession.   For the past 11 years, the respondent who has

seen 74 summers as on the date of filing of the complaint, was

made to run around commission after commission to get her rightful

claim, now she is aged 85, an octogenarian, with all age-related
                                        12



infirmities. Both State Commission as well as National Commission,

after considering the materials on record, have come to a irresistible

conclusion that there is a deficiency of service in handing over 50%

of super-built up area as per the JDA, along with 50% car parking

area, 50% garden area and 50% of terrace as prescribed in the

schedule. Both the Commissions are in concurrence so far as delay

in handing over possession of the property, rightly directed the

petitioners    to   pay   rent   in   respect   of each   apartment   from

09.04.2014 till the date of handing over possession. There are no

infirmities in the orders passed by both the commission and

accordingly sought to dismiss the petition.


     16.      Having heard the learned counsel for the parties and

perused the entire writ petition papers, the only point that would

arise for our consideration is:

     "Whether both the petitioners have made out a case,
     which calls for interference of the orders impugned at
     the hands of this Court?

     17.      Our answer to the above point is in 'negative' for the

following reasons:


     The admitted facts are that there is a JDA and earlier to that

there is a MOU, where under the petitioners have agreed to

construct a multi-storied apartment by October'2013, with a grace
                                   13



period of 6 months, thus on or before 09.04.2014, to complete the

project and hand over 50% of share i.e., 4 flats to the complainant

along with other emoluments stated supra. As per the orders passed

by both the Commissions, there is no delivery of possession of the

flats. The contention of the petitioner is that the Commission lacks

jurisdiction on the ground that there is a clause for specific

performance of contract, is to be rejected, in terms of the law laid

down by the Hon'ble Apex Court in the case of IMPERIA

STRUCTURES supra wherein the Hon'ble Apex Court has held that

the remedies under the Act of 1986 were in addition to the remedies

available under the Special Statutes. That apart, Section-3 of the

Act of 1986 clearly envisages that the provisions of this Act shall be

in addition to and not in derogation of any other law for the time

being in force.


     18.   In that view of the matter, the contentions of the learned

counsel for the petitioners that there is a clause for specific

performance and so also for recovery of amount, the respondent

has to approach the appropriate forum, by paying appropriate court

fee have no legs to stand and accordingly rejected.


     19.   In view of the concurrent findings recorded by both the

Commissions, so far as the deficiency is concerned, the judicial
                                     14



review by this Court under Article-226 of the Constitution of India is

very limited. We find that both the Commissions have properly

adjudicated the lis between the parties relying on the judgments of

the Hon'ble Apex Court, stated supra, holding that there is a

deficiency   of   service   and   negatived   the   contentions   of   the

petitioners regarding force majeure etc. We find no infirmities in the

order passed by both the Commissions.


     20.     The petitioners despite under JDA to construct the

building by October'2013 with a grace period of 6 months ought to

have completed the constructions by 09.04.2014 and delivered 50%

of the Super-Built-up area along with other emoluments. However,

as could be gathered from the records, the petitioners instead of

handing over the possession started alienating the properties in

favour of others. Though a contention has been taken that they

have alienated the properties which fallen to their share, clearly

shows that the petitioners with a deliberate intention to harass a

lady, a widow an octogenarian, made her run around commission

after commission and now before this Court, for her rightful claim,

amounts to abusive of process of law. The petitioners ought to have

honored their commitment when they have taken property way back

in the year 2012 or atleast in 2014. But the stage is same despite

13 years have passed. In these circumstances, we feel that the
                                       15



petition should be dismissed with exemplary cost which shall not be

less than Rs.1,00,000/- (Rupees One Lakh Only). Accordingly, we

proceed to pass the following:


                                   ORDER

i) Petition fails and stands dismissed with cost of Rs.1,00,000/-

(Rupees One Lakh Only) payable to the respondent within a period of four weeks from the date of this order.

ii) If the cost is not paid within the period, the Registry is directed to issue a Certificate as arrears of land revenue, recover the cost within four weeks and release the same in favour of respondent on proper identification.

Sd/-

(S.G.PANDIT) JUDGE Sd/-

(T.M.NADAF) JUDGE JJ CT: BRS