Madras High Court

Bmr Industries Ltd vs Tamil Nadu Electricity Board on 25 June, 2019

Author: M.Dhandapani

Bench: M.Dhandapani

                                                            1

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS
                                                 DATED : 25.06.2019
                                                          CORAM
                                 THE HONOURABLE MR.JUSTICE M.DHANDAPANI
                                                 W.P.No.25747 of 2003
                                                          and
                                              W.P.M.P.No.31608 of 2003 &
                                               W.M.P.No.22631 of 2017


                      BMR Industries Ltd.,
                      (Formerly known as
                      Classwin Industries Ltd.)
                      having Registered Office at
                      Flat No.S.10-TNHB Complex
                      180 Luz Church Road, Chennai-4                                      ...Petitioner

                                                           Vs.

                      1.Tamil Nadu Electricity Board
                      rep. by its Chairman
                      800 Anna Salai, Chennai-2

                      2.The Superintending Engineer
                      Chinglepattu Electricity
                      Distribution Circle
                      Tamilnadu Electricity Board
                      Chingalpattur

                      3.The Executive Engineer / O & M
                      Maraimalai Nagar
                      Chingalpattu District                                         ... Respondents



                                 Prayer: The writ petition filed under Article 226 of the
                      Constitution of India, to issue a writ of Certiorari, to call the records
                      relating   to   the   proceedings    of    the   2nd   respondent     herein   in
                      No.Me.Po/CheMiPaVa/U.Se.Po/U.Po/U.Po/Ko.KE-375/A.No.2003                   dated



http://www.judis.nic.in
                                                           2

                      25.08.2003 confirming the proceedings of the third respondent herein
                      issued under Lr.No.EE/O&M/MMN/AE.PI/F.APTS.TOE/D 293/2001 dated
                      28.05.2001 quash the order dated 25.08.2003 in so far as the
                      application of Industrial Tariff III.B to the petitioner's Service Conection
                      No.455 provided to its Unit at No.2/154 East Coast Road, Muttukkadu
                      Chinglepattu District instead of Commercial Tariff V is concerned.


                               For Petitioner      : Mr.P.Subha Reddy
                               For Respondents     : Mr.S.K.Rameshwar (TNEB)


                                                      ORDER

The Writ Petition has been filed by the petitioner for issuance of a writ of Certiorari, to call the records relating to the proceedings of the 2nd respondent herein in No.Me.Po/CheMiPaVa/U.Se.Po/U.Po/U.Po/ Ko.KE-375/A.No.2003 dated 25.08.2003 confirming the proceedings of the third respondent herein issued under Lr.No.EE/O&M/MMN/AE.PI/F. APTS.TOE/D 293/2001 dated 28.05.2001 quash the order dated 25.08.2003 in so far as the application of Industrial Tariff III.B to the petitioner's Service Conection No.455 provided to its Unit at No.2/154 East Coast Road, Muttukkadu Chinglepattu District instead of Commercial Tariff V is concerned.

2.The learned counsel appearing for the petitioner would submit that the matter related to the theft of energy. The petitioner http://www.judis.nic.in 3 has already deposited 80% of the demanded amount in the impugned order. Subsequently, the Division Bench of this court has passed an order in similar writ petitions to proceed with the civil liability. The learned counsel would further submit on instructions that the petitioner is ready to deposit the remaining amount due as per the impugned order without BPSC and penal interest and the petitioner may be permitted to deposit the same within a reasonable time.

4.The learned counsel appearing for the respondent Board did not dispute the fact that the petitioner had paid some portion of the amount demanded in the impugned order and this court may pass appropriate orders.

5.This issue has been squarely covered by the decision of the Division Bench of this Court in batch of cases in W.A.Nos.1808, 1811 of 2009, W.P.Nos.29882 of 2004 and 3013 of 2014 and W.P.No.(MD) Nos.2360 and 2361 0f 2008, as follows:

28.It was also stated that Section 185 of the Act, 2003 cannot come to the rescue of the Electricity Board, as the action has been initiated only after the Act, 2003 came into existence and no proceedings initiated under the Old provisions / Repealed Act cannot be continued. Further, the Board cannot initiate proceedings under Clause 8.01 and 8.02 http://www.judis.nic.in 4 of the Terms and Conditions of Supply of Electricity (Electricity Supply Act 1948) with regard to theft of energy, as those clauses are no longer in vague as on the date of initiation of proceedings, the Old Act got repealed and the Act 2003 had came into force. Clause 8.01 and 8.02 of the Terms and Conditions of Supply of Electricity (Electricity Supply Act 1948) in the repealed Act reads as follows:
8.00 Theft of Energy and Extra Levy:
8.01 Any consumer who dishonestly abstracts or uses energy shall be deemed to have committed theft within the meaning of Indian Electricity Act, 1910 as amended by the Tamil Nadu Government and the Indian Penal Code and the existence of artificial means for such abstractions shall be prima facie evidence of such dishonest abstraction. Illegal restoration of supply to a disconnected service connection will fail under this category.
8.02 Extra levy for theft of energy by tampering of meters / meter seals will be made at the rates given below:
(a)for a period of twelve months; or
(b)for a period from the date of prior inspection if any by the APTS or MRT wing to the date of detection; or
(c)for a period from the date of replacement of meter to the date of detection; or
(d)for a period from the date of service connection to the date of detection whichever period of the above is less.

For other cases of theft of energy, the extra levy will be made for a period of twelve months or from the date of service connection to the date of detection whichever period if less at the same rates given below:

http://www.judis.nic.in 5
(i)For Energy:
(a) Low Tension Service Connection : Highest Low Tension tariff rate x3: The charges arrived at will be rounded off to the next higher rupees.
(b)High Tension Service Connection:
Highest High Tension Tariff rate x 4 the charges arrived at will be rounded off to the next higher rupee
(ii) For maximum demand: (In High Tension Service Connection):
Highest High Tension tariff rate for maximum demand x 4. Extra levy for illegal restoration of supply to a disconnected service connection will be made for a period of twelve months, immediately preceding the date of detection of the violation or for the period from the date of disconnection of the service connection to the date of detection of the illegal restoration, whichever period is less, at the rates given above..”
29.The above submission made by the learned Senior Counsel for the petitioners cannot be accepted, because once there is a saving clause provided under the New Act, then there is no impediment or bar for the Department to proceed under the Old Act in the absence of proof that it is inconsistent with the provisions of the Act, 2003. More so, quoting a wrong provision of the Act will not entitle a wrong doer to escape from the clutches of law, especially when Section 126 of the Act, 2003 extends power to the Department / Board / Authorities to ensure that the electricity consumed unauthorizedly is calculated and necessary charges are paid by the defaulter. In the decision, Hitech Mineral Industries (P) Ltd., Salem V.TNERC, Chennai, reported in 2010 (3) MLJ 697, http://www.judis.nic.in 6 it is inter alia, observed that the persons who steal energy or use energy unauthorisedly have to be punished.

6.In view of the decision held by the Division Bench of this Court and also considering the request that the petitioner is ready to deposit the remaining amount as per the impugned order without BPSC and penal interest within the time stipulated by this Court, this Court is inclined to direct the petitioner to deposit the entire due after adjusting the amount already paid by him within a period of 12 weeks from the date of receipt of a copy of this order.

7.With the above direction, this writ petition stands disposed of. No costs. Consequently, connected miscellaneous petitions are closed.

25.06.2019 kas Index : Yes / No Internet : Yes / No Speaking / Non Speaking order To http://www.judis.nic.in 7

1.Tamil Nadu Electricity Board rep. by its Chairman 800 Anna Salai, Chennai-2

2.The Superintending Engineer Chinglepattu Electricity Distribution Circle Tamilnadu Electricity Board Chingalpattur

3.The Executive Engineer / O & M Maraimalai Nagar Chingalpattu District M.DHANDAPANI, J.

kas http://www.judis.nic.in 8 W.P.No.25747 of 2003 and W.P.M.P.No.31608 of 2003 & W.M.P.No.22631 of 2017 25.06.2019 http://www.judis.nic.in