Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Kerala High Court

Kerala Panchayat Raj Act vs State Of Kerala

Author: Antony Dominic

Bench: Antony Dominic

       

  

  

 
 
          Kerala Panchayat Raj Act, 1994 or not?.



     2.   The case putforth by the petitioners in W.P.(C)

No.24203 of 2008 and W.P.(C) No.25602 of 2008 is more or

less similar. The former one is filed by the Manager of the

School; whereas the latter has been filed by the Parent-

Teachers Association and two others. The learned counsel

for the petitioner School submitted that the reliefs prayed

for in the earlier O.P. are only confined to the challenge

raised against Exhibit P9 'consent to operate' given by the

Pollution Control Board.



     3.   With regard to the sequence of events, it is seen

that the fourth respondent in W.P.(C) No.24203 of 2008 and

W.P.(C) No.25602 of 2008 (hereinafter referred to as

"applicant" for the convenience of reference in all the three

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:3:-


cases) who is stated as the owner of the property in

Sy.No.1982 of Vellikulangara Village in Mukundapuram

Taluk, with intend to start a 'Crusher Unit' and a 'Quarry',

approached the statutory authorities for obtaining the

requisite NOC/Licence, reportedly after availing/arranging

necessary funds from different sources including Public

Sector Banks by way of loans and submitted an application

before the Pollution Control Board for 'consent to

establish' the Unit.



     4.   It is relevant to note at this juncture, that "three

level monitoring system" is contemplated under the

relevant provisions of the Environment (Protection) Act,

1986. Firstly, the concerned party will have to satisfy the

authority as to the "infrastructure" before getting the

"consent to establish" the Unit. After obtaining such

'consent to establish', the applicant has to comply with

the various conditions/requirements as stipulated by the

Pollution Control Board, after which alone will they be

W.P.(C) Nos.24203, 25602
& 32992 of 2008                -:4:-


issued the "consent to operate" the Unit. Even after

obtaining the "consent to operate" and on getting the

requisite sanction from the concerned Local authority, the

party has necessarily to satisfy the Pollution Control Board

that their activities are strictly in conformity with the norms

prescribed by the Pollution Control Board, failing which it is

for the Pollution Control Board, invoking such powers as

specified under statute, to bring them to the proper track

and on failure, it is very much open to cancel or revoke the

Licence already granted.



     5.   In the instant case, the applicant, on satisfying

the requisite elements, was given the 'consent to

establish' the Unit as borne by Exhibit R4(b) dated 16-11-

2006 issued by the Pollution Control Board. Subsequently,

taking note of the relevant facts and circumstances, the

Panchayath passed a resolution to give 'consent to

establish' the Unit as evident from Exhibit R4(c). When the

applicant was proceeding with further steps to establish the

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:5:-


Unit on the basis of Exhibits R4(b) and R4(c), the Pollution

Control Board intercepted the activities on the basis of

some complaints stated as obtained from different corners

including the petitioner's School and issued Exhibit R4(f)

proceedings dated 4-4-2007 directing to stop all the

construction activities with immediate effect.



     6.   While so, the applicant was granted the necessary

Licence by the authorities under the Explosive Rules, 1983

for possessing and using the explosives in connection with

the operation of the Quarry,       as borne by Exhibit R4(d)

dated   16.4.2007. Various       discussions, meetings   and

negotiations followed and upon satisfying the Pollution

Control Board as to the true state of affairs, they withdrew

Exhibit   R4(f)   'stop-memo'      and  vide  Exhibit  R4(g)

proceedings dated 16-5-2007 permitted the applicant to

proceed with the activities to 'establish the Unit' based on

Exhibit R4(b) consent, subject to some additional conditions

incorporated therein.

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:6:-


     7.   In the meanwhile, the Panchayath, taking note of

Exhibit R4(f) dated 4-4-2007 had issued a 'stop memo'

asking the applicant to keep all the construction activities in

abeyance vide Exhibit R4(h) proceedings dated 18-5-2007

based on the resolution taken in this regard on 15-5-2007.

But since Exhibit R4(f) 'stop-memo' issued by the Pollution

Control Board was already withdrawn vide Exhibit R4(g)

dated 16-5-2007, the applicant approached this Court by

filing W.P.(C) No.20026 of 2007 praying for a direction to

be issued to the Panchayath to act upon Exhibit R4(g) and

to permit them to complete the work. It was also pointed

out before this Court that, according to the applicant, they

had obtained all the requisite certificates such as NOC from

the Pollution Control Board, Additional District Magistrate,

Explosives Department, Geology Department etc. The

petitioner school also got impleaded in the above writ

petition as additional fifth respondent. After hearing all the

parties, this Court vide Exhibit R4(i) Judgment directed the

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:7:-


Panchayath to consider the matter and finalise the

proceedings as specified.



     8.   Pursuant to the above verdict, in spite of the

withdrawal of the stop-memo issued by the Pollution

Control Board, the Panchayath declined the request of the

applicant as per Exhibit R4(j) dated 6-10-2007. But later,

the Panchayath convened a meeting of the applicant and

people of the locality and as suggested by the Panchayath,

steps were taken to assess the damage caused, if any, to the

buildings in the locality; for which two separate Engineers

were deputed, one at the instance of the Panchayath and

other at the instance of the applicant, who submitted their

reports as Exhibit R4(k) and R4(l) respectively. It is the

stand of the applicant that, even though the damage was

not caused because of their activities, particularly when the

Units were yet to be operated, they decided to 'purchase

peace' and accordingly, the amounts shown as payable by

the Engineer/Loss assessor engaged at the instance of the

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:8:-


Panchayath were disbursed to the parties concerned,

against proper receipts like Exhibit R4(m). However, it is

pointed out by the learned counsel for the petitioner that

the petitioner school was never amenable to such course,

particularly   since    their     grievance  was    against

establishment of the Crusher Unit/Quarry in the concerned

property, which otherwise was to affect the lives of the

Teachers, Staff and Students of the School; besides causing

further damage to the buildings.



     9.   After completing the works in setting up the Unit,

the applicant approached the Pollution Control Board for

"consent to operate" the Unit. Since the matter was being

delayed, the applicant approached this Court by filing W.P.

(C) No.10932 of 2008 for appropriate reliefs. After hearing

both the sides (including the Pollution Control Board and

the Panchayath), this Court disposed of the writ petition

vide Exhibit R4(n) Judgment dated 10-4-2008 directing the

Pollution Control Board to inspect the premises and on

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:9:-


satisfaction as to compliance with the conditions imposed,

and if there was no impediment for issuing the 'consent to

establish' (presumably a mistake as "consent to operate"

was the issue involved) to grant the 'consent to operate'

and directed the Panchayath to consider the application for

the requisite licence to be given by the Panchayath on the

basis of the above proceedings.



     10. While so, the Additional District Magistrate

(A.D.M.), Thrissur issued a notice to the applicant asking to

show cause, why the NOC forwarded to the Controller of

Explosives shall not be withdrawn, instructing the applicant

to attend a meeting scheduled in this regard. The meeting

convened by the A.D.M. appears to be on the basis of a

complaint preferred by the petitioner. After hearing, the

A.D.M. passed Exhibit R4(o) dated 23-5-2008 wherein it was

observed that the request of the petitioners was to avoid

electric detonators and to reduce the capacity of the

Crusher to 500 tonnes. Taking note of the fact that the

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:10:-


Quarry was yet to be started, the parties were directed to

approach the Panchayath for further steps in this regard,

particularly in view of the proposed constitution of a

Monitoring Committee. However, the applicant chose to

challenge the said proceedings in W.P.(C) No.17782 of

2008. It is seen that the petitioner herein, though was not

originally impleaded as a respondent to the above

proceedings, later got impleaded as the additional third

respondent. During the course of hearing W.P.(C) No.17782

of 2008, it was brought to the notice of this Court that the

Pollution Control Board, after filing the writ petition, had

issued the necessary 'Consent to Operate' the Unit and

that the Panchayath was to finalise the matter, as already

directed by Exhibit R4(n). Accordingly, the said writ petition

was disposed of vide Exhibit R4(p) Judgment, directing the

Panchayath to consider the application preferred by the

applicant and to pass final orders thereon with notice to the

additional third respondent (petitioner herein) and others

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:11:-


within the time limit of four months as specified therein.



     11. After the disposal of W.P.(C) No.17782 of 2008,

the petitioner approached this Court, by filing a review

petition in W.P.(C) No.10932 of 2008 stating that much

prejudice was caused to the petitioner for having passed the

said verdict without impleading her in the party array. After

hearing, this Court as per order dated 22-10-2008 observed

that the direction was only to consider the matter by the

Panchayath and further that the grievance as to the loss of

opportunity of hearing stood substantially redressed in view

of the Judgment dated 24-7-2008 in W.P.(C) No.17782 of

2008, whereby the Panchayath was directed to finalise the

proceedings only after hearing the petitioner as well.

Thereafter, the petitioner approached this Court by filing

W.P.(C) No.24203 of 2008 challenging the validity of Exhibit

P9 'Consent to Operate' the Unit issued by the Pollution

Control Board and obtained an interim order of stay,

pursuant to which the proceedings directed to be finalised

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:12:-


by the Panchayath are stated as kept in abeyance.



     12. With regard to the challenge against Exhibit P9,

the main grievance of the petitioner is that her School is

situated very close to the applicant's Unit and that

operation of the Unit will cause much adverse consequences

by way of damage to the building and also in terms of

pollution, making the life of the teachers, students and local

public miserable. The petitioner also submits that the Unit

of the applicant is situated with much proximity to the

Forest area and that the sanction to operate the Unit will

definitely spoil the 'flora and fauna', adversely affecting the

wild life; particularly the forest being a 'Conservation

Reserve Tiger Forest'. The learned counsel for the

petitioner points out that the operation of the Unit will lead

to scarcity of drinking water in the locality and further that

it will be against the terms of the National Minor Mineral

Policy 1993; thus affecting the public at large as well.

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:13:-


     13. With regard to the magnitude of challenge the

subject matter in the present writ petitions is rather to be

confined to the relative rights and liabilities between the

petitioner and that of the applicant. In other words, the

larger questions involving public interest are not supposed

to be dealt with by this Court, not being a "Public Interest

Litigation". Whether the applicant is entitled to obtain

Exhibit P9 'consent to operate' issued by the Pollution

Control Board; whether infringement of any statutory

prescription is brought to light or whether the conditions

prescribed by the statutory authorities are simply thrown to

wind by the applicant/beneficiary etc. are the questions to

be considered while examining the scope of Exhibit P9. But

then, there is an effective alternative remedy for the

petitioner to have it challenged by way of Appeal as

provided under the Statute - as pointed out by the Pollution

Control Board in their counter affidavit. Such 'fact

adjudication' can only be on the basis of the evidence to be

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:14:-


adduced; which is not possible in a writ petition filed before

this Court invoking the discretionary jurisdiction under

Article 226 of the Constitution of India.



     14. Another reason for declining interference in W.P.

(C) No.24203 of 2008 and W.P.(C) No.32992 of 2008 is that

the prohibited distance is only 50 to 100 metres (as the case

may be) as discernible from Exhibits R3(a) and R3(b)

Circulars issued by the Pollution Control Board. It is stated

that Exhibit R3(c) is the Report submitted by the Chief

Environmental Engineer, where the distance between the

petitioner's school and the Unit is shown as 629 metres. It

has been stated by the Chief Environmental Engineer in

Exhibit R3(c) that, it cannot be said that damages have

occurred to the building of the petitioner's school because

of the operation of the Unit of the applicant, in view of the

distance noted above; simultaneously adding that, for the

very same reason, no damage could be caused to the

"Kozhimuttapara" as alleged by the petitioner. The

W.P.(C) Nos.24203, 25602
& 32992 of 2008                  -:15:-


petitioner has not chosen to challenge Exhibits R3(a) and

(b) Circulars issued by the Pollution Control Board or the

observations made by the Chief Environmental Engineer as

reported in Exhibit R3(c).

     15. Yet another aspect pointed out by the senior

counsel for the applicant is that, according to the applicant,

W.P.(C) No.24203 of 2008 can only be regarded as "suit in

disguise" for damages, in so far as the actual intent and

desire of the petitioner would be explicitly clear from

paragraph 4 of the reply affidavit dated 13-9-2008 filed by

the petitioner and also from prayer 'g' of the amended writ

petition, which are extracted below for convenience of

reference:-


           Paragraph 4:- If so, fourth respondent can't start
     operation of even the Crusher before an approved
     authority finds out the actual damage incurred to
     petitioner due to fourth respondent, and till fourth
     respondent pays it to petitioner".

           "g. To prohibit 4th respondent from operating their
     quarry/crusher till an expert authority appointed by
     Government decides the loss suffered by petitioner due to
     the blasting done by 4th respondent and till that amount is
     paid by the 4th respondent."

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:16:-


As     submitted     by    the     applicant,  since      the

operation/production is yet to be started, for want of

necessary licence to be issued by the Panchayat, the

apprehension of the petitioner as to the damage likely to be

caused, if permission to operate is given is rather pre-

mature; which is more so when the petitioner is very much

entitled to pursue the remedy before the statutory

authorities, if any violation of the prescribed conditions,

norms, orders or circulars is noticed. On such an event, it is

for the petitioner to substantiate the damage as well, if any

caused because of the activities conducted by the applicant

and as to the extent of damages payable by pursing

appropriate remedies before the appropriate Forum/Civil

Court.

     16. With regard to the challenge raised in W.P.(C)

No.32992 of 2008 against Ext.P9 Quarry licence given to

the applicant by the authority under the Explosives Act and

Rules, the petitioner has raised serious attack for non-

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:17:-


compliance of the relevant rules including Rule 156(4). The

main contention of the petitioner is that the licence was

sought for and proceedings were pursued in respect of a

different property (having Sy.No.'1892') whereas the No

Objection Certificate issued by the Additional District

Magistrate and Ext.P9 licence issued by the statutory

authority were in respect of the property        comprised in

Sy.No.'1982'. The learned counsel for the petitioner submits

that the application submitted by the applicant in Form 5,

the subsequent proceedings in Form 17/Form 18, the site

plan and paper publication         of the notice contemplated

under Rule 156 (4) etc. are pertaining to the property

comprised in Sy.No.1892 and not with regard to the

property in Sy.No.1982 - as shown in Ext.P9 licence. The

learned counsel submits that since the application, site plan

and other relevant proceedings are defective, there is no

valid application; no valid site plan and hence, there cannot

be any valid licence as well.

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:18:-




     17. As      against  the contentions     raised   by the

petitioner, it is submitted by the applicant (6th respondent in

W.P.(C) No.32992 of 2008) that the case put forth by the

petitioner, trying to capitalize the mistake in Survey

Number, does not hold any water at all. So also is the

position with regard to the wild allegations of malpractices

in the office of the departmental authorities and as to the

collusion with the applicant in this regard. With regard to

the notice in respect of the Survey Number as 1892 and

subsequently in giving NOC leading to Ext.P9 licence

showing the actual Sy.No. as 1982, learned Senior Counsel

appearing for the applicant submits that there was no

dispute with the identity of the property concerned till filing

of the present Writ Petition; that absolutely no prejudice

has been caused to the petitioner in this regard; that the

allegations and apprehension as to the damage caused or

likely to be caused on operating the Unit of the applicant

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:19:-


are thoroughly wrong and misconceived; that the petitioner

had in fact participated in the meeting convened by the

Additional District Magistrate, as evident from Ext.R4(j)

(Ext.R4(o) in W.P.(C) No. 24203 of 2008) and above all that

Ext.P9 licence having been granted only in respect of a

'small quantity' of 75 Kgs of explosives, compliance with

Rule 157 alone is sufficient, since Rule 156 is not at all

attracted.

3




     18. Referring to Exts.P18(a) and (b) proceedings (the

request and application in Form No.5 submitted by the

applicant) wherein the survey number has been wrongly

shown as '1892' it is pointed by the learned counsel for the

petitioner that the wrong citation of the survey number has

got serious impact with regard to the notice contemplated

under Rule 156(4) and as to the rights of the interested

parties to prefer objections. Since the proceedings were

finalised by the Addl. District Magistrate leading to

issuance of the No Objection Certificate without giving

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:20:-


proper notice (as the paper publication did not advert to the

correct survey number as '1982' but for wrongly describing

the survey number as 1892), the petitioner contends that all

consequential proceedings including Ext.P9 licence granted

by the licensing authority are liable to be set aside.


     19. The description of the property mentioning it as

under Survey No.'1892' and the scope of notice as

contemplated under Rule 156 (4) have to be considered in a

wider perspective. The first question to be considered is

whether the mistake in the survey number will make the

notice issued under Rule 156(4) null and void. Secondly,

whether the said mistake in the survey number as contained

in the notice published has adversely affected the rights and

interests of the petitioner and thirdly, whether the licensing

authority, before granting Ext.P9 licence, had clear idea as

to the scope and ambit of the licence which was about to be

issued pursuant to the application and NOC forwarded to

him along with the relevant records.

W.P.(C) Nos.24203, 25602
& 32992 of 2008                -:21:-


     20. If Rule 157 is to be applied, which deals with the

procedure to be followed for grant of Form 22 licence to

possess "small quantity" of explosives for "own use", the

procedure is entirely different and the various stipulations

or pre-conditions imposed under Rule 156 are given a go-

bye, by virtue of the 'non-obstante clause' contained in the

said rule. For the purpose of convenience of reference,

both the above rules are extracted below:-

Rule 156(4):

          "Upon receipt of the said application the district

          authority shall forthwith cause notice to be

          published of such application and of the time and

          place at which he will be prepared to hear it, and

          calling upon     any person objecting       to the

          establishment of the factory or magazine or store

          house on the proposed site to give notice of such

          objection to him and to the applicant of not less

          than seven clear days      before the day fixed for

          hearing the application together with his name,

          address and calling and a short statement of the

          grounds of his objections. The day of hearing the

          application shall be a day following    as soon as

          practicable, after the expiration of the period of

W.P.(C) Nos.24203, 25602
& 32992 of 2008                  -:22:-


          one month referred to in sub-rule((6)."

Rule 157:-

           "Procedure to be followed for grant of a

           licence in Form 22 to possess small quantity

           of explosives for own use.-         Notwithstanding

           anything contained in sub-rule(3) to (7) of Rule

           156, where the licensing authority is the Chief

           Controller or a Controller and where the quantity

           of explosives proposed to be possessed for own use

           under a licence in Form 22 does not exceed 100

           Kgs.,   the applicant may apply to the district

           authority together with an application in Form 5,

           statement in Form 17 and the necessary plans for

           the grant of a certificate to the effect that there is

           no objection to the applicant receiving a licence for

           the site proposed and the district authority shall, if

           he sees no objection after conducting enquiries as

           required under these rules, grant, such certificate

           to the applicant who may forward it to the licensing

           authority together with his application."


     21. Rule 157 can be applied only if the quantity of

explosives proposed to be possessed for own use does not

exceed 100 Kgs. In the instance case, Ext.P18 (a) and (b)

applications show the details of explosives as given under:

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:23:-


     1.   Gelatin             100 Kgs.

     2.   E. Detonator        10,000 Nos.

     3.   O. Detonator        10,000 Nos.

     4.   Safety Fuse         2,000 Mtrs.

     5.   Anfo                500 Kg.

If all the above materials are liable to be treated as

explosives, it would take the proceedings outside the

purview of Rule 157. The contention of the applicant (as

supported by the statutory/departmental authorities) is that

the   licence having been issued only for a much lesser

quantity, bringing it within the purview of Rule 157, the

mistake in survey number and the defect in the publication

of notice are not of much significance. The learned Senior

Counsel for the applicant also points out that the provision

only says that the total quantity of explosives shall not be in

excess of 100 Kgs and that detonators are not explosives in

view of the definition of the term 'detonator' given under

Rule 2(7) of the Rules.

W.P.(C) Nos.24203, 25602
& 32992 of 2008                  -:24:-


     22. Rule 2(7) of the Rules defines the term 'detonator'

as follows:

Rule 2(7):-

     "detonator" means a small tube of aluminium or copper

      or other materials approved by the Chief Controller -

      (a) one end of which is closed and the other-

           (i)  left open for the insertion of safety fuse for

                the purpose of initiating explosion within

                the tube; or

           (ii) fitted   with wires or other device for that

                purpose and sealed;

     (b)    which is loaded with a charge of initiating

           explosives, the charge being so designed as to

           produce an explosion that would communicate to

           other tube similarly constructed and charged;"



It is true that the term 'explosive' is not defined in the

Rules. Going by the definition of the term 'detonator', it is

difficult to ascertain whether it is an explosive or not.

Referring to the purport intent and usage of detonator, the

learned Senior counsel for the applicant submits that, it will

become an explosive, only when it is 'loaded'. This court

W.P.(C) Nos.24203, 25602
& 32992 of 2008                   -:25:-


finds it difficult to agree with the said proposition since the

term 'explosive' has been clearly defined under section 4(d)

of the Act, which includes 'detonator' (without any

distinction whether loaded or otherwise.) Section 4(d) of the

Act is extracted below:

           "Section 4(d): "Explosive" means gunpowder,

           nitroglycerine, nitroglycol, gun-cotton, di-nitro-

           toluene, tri-nitro-toluene, picric acid, di-nitro-

           phenol, tri-nitro-resorcinol (styphnic acid), cyclo-

           trimethylene-tri-nitramine,          penta-erythritol-

           tetranitrate, tetryl, nitro-guanidine, lead azide, lead

           styphynate,    fulminate of mercury or any other

           metal, diazo-di-nitrophenol, coloured fires or any

           other substance whether a single             chemical

           compound or a mixture of substances, whether

           solid or liquid or gaseous used or manufactured

           with a view to produce a practical effect by

           explosion or pyrotechnic effect; and includes fog

           signals, fireworks, fuses, rockets, percussion-caps,

           detonators,    cartridges,     ammunition      of    all

           descriptions and every adaptation or preparation of

           an explosive as defined in this clause;"


     23. While       considering        the   applicability     of  the

mandatory requirements under Rule 156(4) and as to the

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:26:-


legally reckonable infringement of the vested rights or

interests of the parties, it is very much necessary to look

into the contents of Ext. P9 licence as well. Undisputedly,

the licence granted is only for a total extent of 75 Kgs of

explosives. The material shown as 'Anfo' (500 Kgs.) in

Ext.P18(a) and (b) applications has been left out by the

licensing authority. So also, the two different types of

'detonators'   (10000 Nos. each)      as claimed    in the

applications has been considered together and only a total

number of 10,000/- 'detonators' has been licenced to be

stored/possessed; granting permission to have 2000 mtrs of

'Safety fuse'. That apart, the 2nd and 3rd respondents who

are the concerned authorities under the Act and Rules have

also filed a counter affidavit before this Court, stating in

paragraph Nos. 3 and 4 that the licence granted to the

applicant is only in respect of 75 Kgs. of 'high explosives

and accessories' which will not come within the purview of

the Rule 156 of the Rules and that compliance with Rule

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:27:-


157 alone is enough.    From the above, it is clear that the

concerned authorities had taken a conscious decision while

granting the licence and that the same was not granted just

on   the    basis   of  the   entries   as   given   in   the

application/recommendation/NOC. This court does not find

any reason to doubt the intellectual expertise of the

competent     authorities in this regard, merely for the

mistake in the survey number pointed out by the petitioner.



     24. With regard to the alleged rights of the petitioner

and other interested parties as to the loss of opportunity for

hearing in view of the mistake in the survey Number, the

crucial question to be considered is whether any prejudice

has been caused to them in this regard. As pointed out by

the learned senior counsel for the applicant, the identity of

the property was never in dispute. It is not a case where

the proceedings were finalised        behind the back of

everybody; on the other hand, the 'consent to establish'

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:28:-


the Unit was granted by the Pollution Control Board way

back in 2006. Subsequently, at the instance of the

petitioner, the Pollution Control Board had given a 'stop-

memo' directing to stop all construction works, followed by

a similar 'stop memo' issued by the Panchayath. Thereafter,

the Pollution Control Board, as per the proceedings dated

16.05.2007 had withdrawn the stop memo, permitting the

applicant to effect the construction, finally leading to the

'Consent to Operate', as borne by Ext.P9 licence in W.P.

(C) No.24203 of 2008. Various complaints, inspections,

reports etc., were subjected to analysis before the different

authorities at different points of time in respect of the

establishment and operation of the Quarry and Crusher

Unit in the particular property of the applicant situated in

Sy.No.1982 of Vellikulangara village of Mukundapuram

Taluk, though it was wrongly mentioned as 1892

somewhere. That apart, pursuant to the complaint filed by

the petitioner herself before the Addl. District Magistrate,

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:29:-


the NOC given by the said authority earlier was sought to

be re-considered and accordingly, a notice was issued to the

applicant (which was the subject matter of challenge in

W.P.(C) 17782 OF 2008). The outcome of the said meeting

is evident from Ext. R4(j) in W.P.(C)32992 of 2008 (Ext.R4

(o) in W.P.(C) 24203 of 2008). It is revealed from the said

proceedings that the petitioner had also participated in the

above meeting with regard to the issuance of NOC for

obtaining the explosives licence under the Act/Rules. The

submission of the petitioner before the Addl. District

Magistrate      on the date of hearing scheduled on

21.05.2008, was more confined to avoid electric detonators

and to reduce the capacity of the Crusher to 500 tonnes.

The petitioner having admittedly participated in the above

proceedings pertaining to issuance of NOC, is not justified

to take a 'u-turn' and say that the mistake in the survey

number (as given in the paper publication) has resulted in

loss of opportunity for hearing and      in raising proper

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:30:-


objections before the concerned authorities.



     25. Learned counsel for the petitioner, referring to

Ext.P41 counter affidavit filed by       the Addl. District

Magistrate in W.P.(C) No. 17782 of 2008, submits that the

very same authority who had issued the NOC for securing

the Explosive licence by the applicant had conceded before

this Court that the NOC required to be cancelled in view of

the complaints received from different corners. The

circumstances, which led to issuance of the NOC have been

explained by the Addl. District Magistrate in the counter

affidavit filed in W.P.(C) 32992 of 2008, (which has been

clarified in Exhibit 41 counter affidavit as well), thus

showing that there is no contradiction at all, submits the

learned Senior Government Pleader.




     26. The learned counsel for the petitioner submits,

with reference to the information obtained from the office

of the Deputy Superintendent of Police, the office of the Fire

W.P.(C) Nos.24203, 25602
& 32992 of 2008               -:31:-


and Rescue Department and RDO, that the said authorities

have not issued any NOC in connection with the issuance of

licence to the applicant. The learned senior Government

Pleader made available the relevant files containing the

entire proceedings for perusal of this court. The file

discloses that NOC was issued from the office of the

Superintendent of Police, Thrissur by way of Proceedings

No.D2(B) 45431/06 R, stated as received in the collectorate

on 07.11.2006.     Similarly NOC bearing No.A.28-4919/06

dated 10.10.2006 has been issued from the office of the

Asst. Divisional Officer, Fire and Rescue Service, Thrissur to

the District Collector, Thrissur. In the former certificate,

the    survey number of the property belonging to the

applicant whose particulars have been given thereunder

has not been mentioned, whereas in the latter certificate,

the survey number has been mentioned as '1892' as given in

the site plan.

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:32:-


     27. In the report/NOC bearing No.C.36464 /06/K.Dis

dated 31.10.2006 issued by the Tahsildar of Mukundapuram

Taluk, the survey number has been correctly mentioned as

'1982'. So also, in the permit issued by the concerned

Geologist and in the Mahazar dated 16.10.2006 attached to

the location sketch prepared by the Village Officer, the

survey number has been correctly mentioned as '1982'.

The files including those produced by the Pollution Control

Board contain copies of the relevant records produced by

the applicant such as title deeds, possession certificate,

basic tax receipts etc, all of which show that the property

was comprised in Sy.No.'1982'. It is pointed out by the

learned Standing Counsel for the Pollution Control Board

and also by the Senior Government Pleader          that the

concerned application has to be accompanied with copies of

all the relevant documents as prescribed      and all such

documents including title deed, possession certificate and

basic tax receipt etc revealed the particulars of the actual

W.P.(C) Nos.24203, 25602
& 32992 of 2008                 -:33:-


property owned, possessed and enjoyed by the applicant

and that there was absolutely no reason to doubt the

identity of the property involved herein.            Viewed in the

above circumstances, the point with regard to the

prejudice, if any caused to the petitioner, stands answered

in the negative.



     28. The learned counsel for the petitioner further

referred to the violation of Rule 156(5) of the Explosives

Rules stating that no notice whatsoever was issued by the

concerned authority before finalising the proceedings, to

the Town Planning/Municipal authority, which otherwise

would have enabled the Panchayath to bring the correct

position to the notice of the said authority so as to have had

the licence denied. Rule 156(5) of the Explosives Rules is

extracted below:-

Rule 156(5):-

           "Where the site of the proposed factory of magazine
     lies within 1.5 km. of the limits of the jurisdiction of any
     town planning municipal authority or port authority, the

W.P.(C) Nos.24203, 25602
& 32992 of 2008                 -:34:-


     applicant shall prepare, for service on such authority a
     notice of the application and of the said day of hearing."



The above sub-rule '5' says, where the site of the proposed

factory or magazine lies within 1.5 km. of the limits of the

jurisdiction of the "town planning municipal authority or

port authority", the applicant shall prepare, for service on

such authority a notice of the application and of the said

day of hearing. This Rule obviously does not say that notice

has to be issued by the licencing authority under the

Explosives Rules to all Local Authorities in whose

jurisdiction the Unit is sought to be established. On the

other hand, it specifically denotes service of notice to the

"town planning municipal authority or port authority"

situated within a radius of 1.5 kms. Since existence of any

Town Planning Municipal Authority or Port Authority within

a radius of 1.5 kms. is not established, the above sub-rule is

not at all attracted to the present case.

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:35:-


     29. The learned counsel for the petitioner, referring

to the term "own use" as it appears under Rule 157 of the

Rules submits that the benefit of Rule 157 will be available

only if the 'small quantity' of the explosives not exceeding

100 kgs. is subjected to "own use" and further when the

end product obtained by using the said explosives is also

put to "own use/domestic purpose" of the applicant. In the

instant case, the learned counsel for the petitioner submits

that applicant has conceded in the counter affidavit that

they have already entered into a contract with another

person for the supply of granite rubbles for the construction

of N.H.47. The learned counsel for the petitioner submits

that the end product is subjected to a "commercial use" i.e.

for sale and not for the domestic/personal use and hence

there is violation of the Rule. Even on a plain reading of the

said Rule, it is absolutely not possible to arrive at any such

inference in so far as the Rule only envisages a simplified

procedure, if the 'small quantity' of explosives is required

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:36:-


for the "own use" of the applicant. The term "own use"

qualifies the term 'explosives' and not the 'end product'. The

explosives procured adopting a simplified procedure

invoking Rule 157 are not liable to be diverted to any other

channel than as envisaged therein. In the instant case, the

petitioner does not have a case that the explosive is for a

different use than for being used in the Quarry/Crusher Unit

of the applicant. In so far as the limited quantity of the

explosives procured under the licence stated as issued

under Rule 157 is put to 'own use' by the applicant, the

challenge raised by the petitioner referring to the sale of

the 'end product' is devoid of any merit.



     30. Referring      to   the    different    interlocutory

applications, also seeking to implead the Centre for Earth

Science Studies (additional sixth respondent) the learned

counsel for the petitioner submits that no licence could have

been granted without conducting an 'Environmental Impact

Study' by the Centre for Earth Science Studies the

W.P.(C) Nos.24203, 25602
& 32992 of 2008             -:37:-


additional sixth respondent. This Court as per interim order

dated 3-11-2008 had directed the Pollution Control Board to

file a statement as to whether, in terms of the notification

issued by the Government of India in exercise of the powers

under    the   Environment    (Protection)  Act,   1986   an

'Environmental Impact Assessment' was necessary before

consent    is  granted   for   the  establishment    of   the

Quarry/Crusher Unit in the nature of the one, which is

proposed to be set up by the applicant. Accordingly, the

Pollution Control Board filed a statement/report dated

12.11.2008 stating that as per the existing Rules,

'Environmental Impact Assessment Study' was not required

for setting up the project and that the details of Project or

Activities requiring prior environmental clearance are

indicated in the schedule of the Notification of the Ministry

of Environment and Forests dated 14-9-2006. It is made

clear therein that such study is generally carried out before

setting up of the project and that too, for the projects and

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:38:-


activities mentioned under the schedule. A copy of the

relevant notification and schedule have also been produced

by the Pollution Control Board as Exhibits R3(a) and R3(b)

along with the said report, which shows that the contention

of the petitioner is wrong and misconceived.




     31. The learned senior counsel for the applicant

submits that no specific plea of malafides has been raised or

established in the above proceedings. The files produced by

the learned senior Government Pleader and also by the

Standing Counsel for the Pollution Control Board do not

reveal any adverse entry or proceedings whereby it could

be gathered that there was any attempt from the part of the

applicant    to  mislead   the    authorities concerned   by

describing the Survey number wrongly as '1892' (in the

place of 1982); especially when copies of all the supporting

documents including the Title Deed, the Tax Receipt, NOC

issued by the Tahsildar, Permit issued by the Geology

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:39:-


Department, etc. produced along with the application

revealed the correct survey number as '1982'. The learned

counsel also referred to the power of the licencing authority

to sustain, cancel or revoke the licence, if the same has

been obtained by suppression of any material fact or in

dubious manner. The learned counsel for the petitioner also

relies on such power conferred on the licencing authority

under Section 6E(3)(c) of the Act and submits that the

petitioner has already preferred Exhibit P26 dated 22-8-

2008 before the Deputy Controller of Explosives, Kakkanad

and Exhibit P27 dated 31-8-2008, before the Joint Chief

Controller of Explosives, Egmore, Chennai in this regard. It

is for the petitioner to pursue the matter before the said

authorities, if found fit and proper for redressal of the

grievance, if any.




     32. The learned counsel for the petitioner submits

that the impugned consent granted to operate the

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:40:-


Quarry/Crusher Unit interferes with the right of the

petitioner to establish and run educational institutions

guaranteed under Article 19(1)(g) and 30(1) of the

Constitution of India; besides infringement of Article 21. But

enjoyment of such rights can only be with due regard to

similar/constitutional rights and liberties available to other

citizen as well. In so far as the acts and deeds of the

'Applicant' is in conformity with the relevant provisions of

law and in tune with the terms and conditions of the

Licence, it is not assailable under any circumstance. The

learned counsel further submits that the petitioner has got

some other contentions as well, brought out through

different interlocutory applications filed in these writ

petitions. The averments and allegations in the interlocutory

applications do not form part of the pleadings raised in the

writ petitions. Reliefs sought for in the writ petitions are

based on the specific grounds raised in the writ petitions

and not on the contents of the affidavits filed in support of

W.P.(C) Nos.24203, 25602
& 32992 of 2008              -:41:-


the interlocutory applications. Such aspects, if any, are not

liable to be looked into, in so far as they are not chosen to

be incorporated in the writ petition, by amending the same.




     33. While contending that the petitioner did not know

about the proceedings for issuance of the NOC by the

Additional District Magistrate in view of the mistake in

Survey    number,    shown    in   the  public   notice/paper

publication as '1892' in the place of '1982'. The petitioner

has also a strange contention that the publication was

effected by the concerned authority in the 'Mathrubhoomi'

while the authorities very well knew that Nuns subscribe to

'Malayala Manorama' and not 'Mathrubhhoomi'. This court

does not intend to make any comment or opinion with

regard to the above submission as it does not deserve to be

dealt with for effective adjudication of this case. Specific

reference is made to paragraph 32 of the W.P.(C) No.32992

of 2008 in this regard, which is extracted below:-

W.P.(C) Nos.24203, 25602
& 32992 of 2008                   -:42:-


           "Copy of Form 22 Licence issued and Form 17
     Statement filed by fifth respondent are produced herewith
     and marked as Exhibits P9 and P10 respectively. Copy of
     notice issued under rule 156(4) is produced herewith and
     marked as Exhibit P11. Exhibit P11 was received on
     1.11.2008 and it was entrusted with petitioner's counsel
     for appropriate action. Since Exhibit P11 was misplaced by
     petitioner's counsel only now when he went through it he
     noticed the difference in the survey number and informed
     petitioner and this is the reason for filing this case now."


In view of the above categorical admission made by the

petitioner, it is difficult to hold that the matter has been

pursued on the basis of any genuine grievance as to

violation of the rights or opportunities of the petitioner,

but as a matter of exploratory/experimental litigation.



           In the above facts and circumstances, no

interference is called for in all these three writ petitions and

they are dismissed accordingly.




                              P.R.RAMACHANDRA MENON,
                                                JUDGE.
skr


? IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 8609 of 2009(U)


1. FOUZIYA RAHIMAN, AGED 14,
                      ...  Petitioner

                        Vs



1. STATE OF KERALA, REP. BY THE SECRETARY
                       ...       Respondent

2. THE REGIONAL PASSPORT OFFICER,

                For Petitioner  :SRI.K.A.SHAMSUDEEN

                For Respondent  : No Appearance

The Hon'ble MR. Justice ANTONY DOMINIC

 Dated :27/03/2009

 O R D E R

ANTONY DOMINIC, J.

================ W.P.(C) NO. 8609 OF 2009 (U) ===================== Dated this the 27th day of March, 2009 J U D G M E N T The prayer sought in this writ petition is to direct the respondents to accept Exts.P4 and P4(a) application, along with the documents produced and to issue passport to the petitioner incorporating necessary corrections sought for by her.

2. Petitioner submits that she is the holder of Indian Passport No.F4551952. She was earlier married to one Sri.Abdul Rasheed, Pokkakkillath House, Ariyannur, Trichur District, who divorced her by pronouncing Talaq on 20/1/2007. This averment is sought to be supported by referring to Ext.P7 letter dated 20/1/2007. The passport issued to her incorporated the name of Sri.Abdul Rasheed as her spouse. Subsequently on divorce, the petitioner got remarried as is seen from Exts.P1 and P2 to one Sri.Abdul Rahiman of Chalakkudy. Later on she submitted Exts.P4 and P4(a) applications to the 2nd respondent requesting for making corrections in her passport by incorporating the name of her husband. That was refused to be accepted stating that if the petitioner desires to have change of name, she should produce WPC 8609/09 :2 : divorce order passed by a Court of law. It is in these circumstances, the writ petition is filed.

3. As is seen from Ext.P7 referred to above, on the basis of the personal law that is applicable to the petitioner, she has been divorced and on that basis she got remarried also. These facts are duly supported by the documents produced by the petitioner. If that be so, I see no justification for the 2nd respondent's refusal to accept Exts.P4 and P4(a), by which the petitioner sought corrections to be carried out in her passport.

4. In view of the above, I direct that it will be open to the petitioner to submit the originals of Exts.P4 and P4(a) before the 2nd respondent, in which case, the 2nd respondent shall accept the same and pass orders in the light of the observations herein above contained. It is directed that once the petitioner files an application as above, orders in the matter shall be passed, as expeditiously as possible, at any rate within 3 weeks of production of a copy of this judgment.

Writ petition is disposed of as above.

ANTONY DOMINIC, JUDGE Rp