[Cites 0, Cited by 1] [Section 6] [Entire Act]

State of Gujarat - Subsection

Section 6(4) in Gujarat Regularisation of Unauthorised Development Act, 2011

(4)If, on scrutiny of the reply to the notice or the application of the applicant and after making such inquiry, as he deems fit, the designated authority is of the opinion that the unauthorised development cannot be regularised, it shall pass an order, within eighteen months of such reply to notice or application, refusing to regularise such unauthorised development, stating the grounds therefore, in the prescribed form and manner as may be prescribed.