Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Delhi District Court

M/S. Lattice Interiors vs Technopromexport on 6 June, 2018

     IN THE COURT OF MS. TWINKLE WADHWA: LD. ADDITIONAL DISTRICT 
           JUDGE­03:PATIALA HOUSE COURT:NEW DELHI DISTRICT 

CS No. 56798/16

        M/s. Lattice Interiors
        Through its Proprietor 
        Atul Garg at­
        27 D, Sector­31 (Kasna)
        Greater Noida, UP.                                          .....Plaintiff

        VERSUS

1.

TechnoPromExport  Through it Director/Proprietor/Authorized signatory/ Site Project Manager at :

(a) 90, Poorvi Marg, Vasant Vihar, New Delhi. Also at :­
(b) BARH STTP PO Barh District Patna, Bihar 803215.
(c) Moscow, Russia

2. NTPC Ltd. 

        Through its Director 
        Scope Complex, Lodhi Road, 
        New Delhi.                                                     ....Defendants

Date of Institution     :           27.08.2015
Date of Final Arguments :           06.06.2018
Date of Decision        :           06.06.2018




CS No. 56798/16                                                           Page 1 of 5
                                          JUDGMENT 
The Case­

1. This   suit   has   been   filed   by   plaintiff   company   for   recovery   of  Rs.16,82,687.50/­ along with interest from the defendant.    Summons of the suit  were   served   upon   the   defendants   on   24.02.2016   and     29.04.2016.     Despite  opportunity, defendant had   not filed written statement and their   defence was  struck off  on 12.05.2016 and 10.06.2016.

Appearance­

2. I have Ld. Counsel for the plaintiff  Shri Kamal Jindal and have perused  the case file.  

Plaintiff's Case­

3. The case of the plaintiff as per plaint and the evidence led is that   on  09.11.2012, defendant no.1 had entered into a contract/agreement with the plaintiff  for making residential camp at Barh, STTP (site of defendant no.2) for defendant,  vide contract no.53054122700 dated 09.11.2012.  It is further the case of plaintiff  that as per contract, the plaintiff provided two bank guarantees of 5% each of the   total   cost   of   the   contract.     One   bank   guarantee   of   Rs.7,42,927.50/­   was   for  satisfactory performance of the contract and the other of Rs.7,42,927.50 for defect  liability period i.e. one year after the completion of the work.  

4. It is further the case of the plaintiff that 10% retention money was to be  deducted from the bills as per the contract.   Thereafter, the plaintiff started the  construction of the residential camp and also started to issue bills of the work  done from time to time but the defendant did not pay the money against the work  CS No. 56798/16                  Page 2 of 5 done which created unnecessary problem to the plaintiff and he had to suffer  huge   losses   but   despite   the   non­cooperation   of   the   defendant,   plaintiff   being  honest to his profession completed the entire  work of residential camp  in the first  week of January, 2014.  

5. It is further the case of the plaintiff that  plaintiff sent a bill dated 01.02.2014  of Rs.9,39,760/­ to the defendant along with the request to release the  amount of  the   retention   money   and   the   amount   of   bank   guarantee   but   the   defendant  deliberately   did   not   pay   any   heed   to   clear   the   amount   of   the   plaintiff.     On  21.01.2014, plaintiff received a letter from the defendant no.1 in response to email  dated 06.01.2014, in which some defects were complained in the working, which  the plaintiff rectified and the defendant after being satisfied, issued a certificate  dated 21.05.2014 to the plaintiff as preliminary acceptance.

6. It is further the case of the plaintiff that despite repeated demands, no  payment was made by the defendant. Hence, the present suit was filed. 

7.  Summons of the suit were served upon the defendants on 24.02.2016 and  29.04.2016.  Despite opportunity, defendant had  not filed written statement and  their  defence was struck off  on 12.05.2016 and 10.06.2016.

8. To   prove   its   case,  Plaintiff   examined   Shri   Atul   Garg   as   PW1    and  exhibited the following documents­ S.No.  No. of Exhibits Details of the documents 1 Ex. PW1/1(OSR) Contract deed   2 Ex.PW1/2 Bill dated 01.02.2014 3 Ex.PW1/3 Copy of email dated 06.01.2014 4 Ex.PW1/4 Letter dated 21.01.2014 CS No. 56798/16                  Page 3 of 5 5 Ex.PW1/5 Certificate of preliminary acceptance dated 21.05.2014 6 Ex.PW1/6(colly) Letter dated 04.02.2015 7 Ex.PW1/7 Copies of letters  8 Ex.PW1/8(OSR) Copy of letter dated 18.03.2015 9 Ex.PW1/9(OSR) Copy of letter dated 05.05.2015 10 Ex.PW1/10(OSR) Copy of Addendum dated 28.06.2016 11 Ex.PW1/11(OSR) Copy of amicable agreement dated 28.06.2016 Reasons for Decision­

9. Heard the ld. counsel for the plaintiff and gone through the record. 

10. In view of the documents which are duly exhibited on record and which are  unchallenged before this Court, it is proved by the plaintiff that before filing of the  present suit, plaintiff have already received one bank guarantee of Rs.7,42,927.50  from the defendant back.  It is also proved by way of the documents on record i.e.  invoices for the work and additional work filed on record, amicable settlement  pursuant to the disputes between the parties arrived on record and by way of  emails and letters on record, that one bank guarantee of Rs.7,42,927.50 was still  with the defendant which was to be paid to the plaintiff besides retention money.  Further according to the document Ex.PW1/2 an amount of Rs.9,39,760/­ is due  and payable to the plaintiff from the defendant. 

11. It is further proved by plaintiff on record that in the settlement, he had  agreed to waive off the amount of Rs.9,39,760/­ in order to receive early payment  as work was executed in the year 2013, though legally entitled to receive the  same.   But no payment was made by the defendant pursuant to the amicable  CS No. 56798/16                  Page 4 of 5 settlement also.  Hence, plaintiff is entitled to claim whole of the amount due. 

12. In view of the above, it is proved that plaintiff is entitled to recovery of  retention money of Rs.7,42,927.50, recovery of bank guarantee of Rs.7,42,927.50  and   an   amount   of   Rs.9,39,760/­   from   defendant   pursuant   to   the   work   done.  Hence,   plaintiff   is   entitled   to   an   amount   of   Rs.24,25,615/­   and   defendant   is  directed to make the payment of the said amount within two months from today.  As it was a commercial transaction between the parties, plaintiff is entitled to  interest @ 7% from the date of filing of the suit till actual payment/realisation.  

13. The suit of the plaintiff is accordingly decreed for a sum of  Rs.24,25,615/­  along with  interest @ 7% per annum from the date of filing of the suit till the date   of realisation. 

Decree Sheet be prepared accordingly.

File be consigned to record room.  

Announced in an open Court  On    06th   day of  June, 2018.  (Twinkle Wadhwa)              ADJ­03/PHC/NEW DELHI     06.06.2018 CS No. 56798/16                  Page 5 of 5