State of Rajasthan - Subsection

Section 5(1) in Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010

(1)Subject to the terms and conditions contained in these regulations, the 'Certificates' issued under the Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 shall also be a valid instrument along with direct purchase of renewable energy for discharge of the mandatory obligations set out in the Regulations/Orders for the obligated entities to purchase renewable energy:Provided that in the event of the obligated entity fulfilling the renewable purchase obligation by purchase of certificates, the obligation to purchase electricity from generation based on solar as renewable energy source can be fulfilled by purchase of solar certificates only, and the obligation to purchase electricity from generation based on renewable energy other than solar can be fulfilled by purchase of non? solar certificates:Provided further that fulfilling of Renewable Energy Purchase Obligation by a distribution licensee for the percentage specified for power purchase from bio-mass plant shall be fulfilled by purchase of power from biomass plant only and not by purchase of REC.