Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

Andhra Pradesh High Court - Amravati

Rashtriya Ispat Nigam Limited, Rinl, vs M/S. Mauria Udyog Limited on 6 February, 2025

Author: Ninala Jayasurya

Bench: Ninala Jayasurya

      IN THE HIGH COURT OF ANDHRA PRADESH :: AMARAVATI

              THURSDAY,THE SIXTH DAY OF FEBRUARY
                 TWO THOUSAND AND TWENTY FIVE


                                PRESENT

           HONOURABLE SRI JUSTICE NINALA JAYASURYA
                                  AND

           HONOURABLE SMT JUSTICE SUMATHI JAGADAM

            COMMERCIAL COURT APPEAL NO: 17 OF 2021

Between:



     Rashtriya Ispat Nigam Limited, (RINL), (a Government            of   India

    Undertaking), Visakhapatnam Steel Plant, Represented by its
    Authorised Signatory, Sri A.K.Bhalla, DGM (Marketing), Now presently
    Represented by its Authorised signatory, Sri Girish Kumar, S/o B.P.
    Singh, Occ. DGM (Marketing), Having its Registered Office at
    Administrative Building, Visakhapatnam-530 031, A.P. India.

                                                                  ...Appellant

                                  AND



  1. M/s. Mauria Udyog Limited, Sector-25, Sohna Road, Faridabad Rep. by
     its Deputy General Manager, Mr. N.K. Surekha,

 2. Smt. Kommu Suvarchala, W/o. Chiranjeevi Sastri, Hindu, Aged about.
    60 years, MIG Plot No.65, Door No. 4-68-7, Lawsons Bay Colony,
    Visakhapatnam.

 3. Hon'ble Sri. Justice O.N. Khandelwal, Father's name not known to the
    petitioner, Hindu, Aged about. 62 years. Residing at 1/17, Gomtinagar,
    Lucknow-226 010.
        4. Sri D. Tarakaram, S/o. D.A. Swamy, Hindu, Aged about. 61 years,
            Behind     Gayatri   Peetham,     HB    Colony,    Seethammadhara,
            ■Vj,sakhapatnam.

       ■V
                                                                 ...Respondents
               '   •




'r •

            .,Appeal under Section 13 of Commercial Courts Act, R/w Section 37 of
Arbitration and Conciliation Act, 1996, against the Order passed in C.A.O.P.
No. 41 of 2018, Dated 07-01-2021 on the file of the Special Judge for Trial

and Disposal of Commercial Disputes, Visakhapatnam, setting aside the
Order dated 8-06-2018/18-07-2018 in Arbitration case, passed by the
Learned Arbitral Tribunal.


Counsel for the Appellant: Sri Vivek Chandra Sekhar S

Counsel for Respondent No.1/Claimant: Sri S Rajan

Counsel for Respondent Nos.2 to 4: -

The Court made the following:
 I




    APHC010143982021


                          IN THE HIGH COURT OF ANDHRA PRADESH
                                       AT AMARAVATI                      [3494]

                                (Special Original Jurisdiction)

                        THURSDAY, THE SIXTH DAY OF FEBRUARY
                           TWO THOUSAND AND TWENTY FIVE

                                       PRESENT

              THE HONOURABLE SRI JUSTICE NINALA JAYASURYA

              THE HONOURABLE SMT JUSTICE SUMATHI JAGADAM

                       COMMERCIAL COURT APPEAL NO: 17 OF 2021

    Between:


    Rashtriya Ispat Nigam Limited, (RINL)                         ...APPELLANT

                                          AND


    M/s Mauria Udyog Limited and Others                     ...RESPONDENT(S)

    Counsel for the Appellant:

       1. VIVEK CHANDRA SEKHAR S

    Counsel for the Respondent(S):
       1.SRAJAN
                                            2




The Court made the following: (Per NJS,J)
ORDER;

       The present appeal under Section 13 of the Commercial Courts

Act, R/W Section 37 of the Arbitration and Conciliation Act 1996 (for short

"the Act"), has been preferred by the appellant-petitioner aggrieved by the

Order dated 07.01.2021 in CAOP No.41 of 2018, on the file of the Court

of the Special Judge for Trial and Disposal of Commercial Disputes

Visakhapatnam,       whereby       the   Arbitral   Award   dated   18.06.2018    /


18.07.2018 of the majority members was set aside in part only in respect

of the rate of interest.


2)     For the sake of convenience, the appellant-Rashtriya Ispat Nigam

Limited is referred to hereinafter as "the RINL" and the 1®* respondent as

the claimant.


BRIEF FACTS:


3)     RINL is a Public Sector Undertaking manufacturing steel and allied

products      appointed    'the   claimant'    as   a consignment agent under

agreement number VSP/MKTG/SY/19 of 2006-2007 dated                   09.10.2009


for a period of seven years with effect from 31.03.2008 to 31.03.2015.

After the expiry of the said seven years period, RINL addressed letters

extending the consignment agency contract on certain                  terms    and


conditions,     but the    claimant vide       letter dated 20.02.2015,   as   also


subsequent communications informed 'RINL' that it would execute the

work during the extended period as per the terms and conditions of the
                                       3




Contract dated 09.10.2009, referred to above and continued to discharge

its obligations. RINL, however, withheld an amount of f30,71,428/- from

the bills on the premise that hard standing and yard development in the

stock yard was not done till December 2008. It had also withheld 10% of

the consideration amount from March 2015 to a tune of f 1,04,62,801/- as


on December, 2016 on the premise that the difference in rates between

the existing contract and the new contract would have to be recovered.

Thus, disputes arose between the parties, which ultimately          lead   to


invocation of Arbitration Clause.


4)    On entering reference, before the Arbitral Tribunal the claimant filed

claim statement for release of penalty amount of f30,71,428 with interest

of f?48,53,964.54 ps., at the rate of 18% p.a., from the date of recovery to

28.02.2017. The claimant also sought refund of f1,04,62,801/- deducted

from its bills during 2015-2016 and interest of ?15,97,746.31 ps., at the

rate of 18% per annum up to 20.02.2017. Subsequently, the claimant filed

an amended statement of claim, mentioning that the illegally withheld

10% of the bill amount as on 31 10.2017 is ?1,33,13,650/-. According to

the amended claim, the total amount of ^2,60,63,162 (gross, value of

unpaid invoice of f2,18,87,219/-, plus interest for delay-in payment of

invoices of f41,75,943) has to be paid to the claimant towards the unpaid

invoices and interest on the delayed payment of invoices, with further

interest at the rate of 18% per annum, till the date of Award.
                                        4




5)    RINL filed its defence statement, inter alia, contending          that the


claimant    being   a    consignment   agency/contractor    should     fulfill   its


obligations under the contract, in particular, those relating to hard

standing and basic infrastructure. With regard to conditional extensions, it

stated that nothing prevented the claimant to simply refuse to accept the

extensions.    While contending that the claimant is not entitled          to the


claims, muchless the interest thereon, the RINL raised a counter claim to

a tune of f 1,32,46,669/-, towards difference of rates and Rs.22,00,000/-

towards compensation.

6)    The     majority    members      of   the   learned   Arbitral    Tribunal

(Respondents 2 and 3 herein) after considering documentary evidence

vide Award dated 18.06.2018, awarded a sum of f4,29,05,335/- to the

claimant with future interest at the rate of 9% per annum from 01.07.2018

till actual date of payment to the claimant, while allowing the counter

claim partly for an amount of Rs.5,06,000/-. The 4'^ respondent passed a
separate Award dated 18.07.2018.

7)    Aggrieved by the same, RINL filed CAOP No. 14 of 2018 on the file

of the Court of Special Judge for Trial and Disposal           of Commercial


Disputes, Visakhapatnam under Section 34 of the Act.              The     learned


Commercial Court, after considering the matter, partly allowed the said

O.P., by reducing the pendent lite interest from 18% to 9% p.a.
                                      5




Aggrieved by the order of the learned Commercial Court, RINL preferred

the present Appeal.

8)     Heard Mr.S. Vivek Chandra Sekhar,         learned counsel for    the


appellant and Mr. S. Rajan, Learned counsel for the respondent-claimant.

Perused the material on record.


9)    Learned counsel for the RINL, inter alia, contended that the learned

Commercial Court failed to appreciate that the learned Arbitral Tribunal

had not considered the contentions raised on behalf of the RINL in a

correct perspective.   He contends that the learned Tribunal i.e., majority

arbitrators erred in holding that there is no new contract stipulating the

rates and observing that there is no contract at all and the learned

Commercial Court failed to appreciate these aspects.     He also contends

that if the claimant was not agreeable for the revised rates, it should not

have accepted the material and that having accepted the same and

proceeded with the works, the claimant virtually accepted the offer and
that the learned Arbitral Tribunal as also the learned Commercial Court

went wrong in not considering the same in the right perspective.        He

contends that the learned Commercial Court failed to appreciate that

there is no stipulation for payment of interest on delayed payments as per

the contract, but the learned Arbitral Tribunal awarded interest on delayed

payments, which is not sustainable. He submits that in fact, interest was

not claimed at the first instance, but only by way of amendment of the
  claim. Making the said submissions, and that the Award to the extent as

 confirmed by the Commercial Court is perverse and contrary to the public
 policy of India, the learned counsel seeks to set aside the same and allow
 the appeal.

 10)     On the other hand, the learned counsel for the claimant made

 submissions to sustain order under challenge.                      He contends that the
 learned Arbitral Tribunal examined the claims meticulously                            duly

considering the material on record and by a majority Award allowed the
claims with supporting reasons, which are plausible and the learned
Commercial Court after thoroughly appreciating the matter with reference
to the provisions of the Act and settled legal position, was not inclined to
interfere with the conclusions arrived at by the learned Arbitral Tribunal

with regard to the merits of the case, except reducing the interest portion
from 18% to 9% p.a. He contends that the scope of interference by the
Appellate Court in the order passed under Section 34 of the Act, is much

more narrower and only in the event the findings recorded by the Arbitral

Tribunal are perverse, contrary to the terms of the agreement or the

Arbitral Award, is in conflict with the public policy of India, interference
may be warranted, which is lacking in the present case. Relying on the

decisions of the             Hon'ble         Supreme   Court   of    India   in   Reliance


Infrastructure          Ltd.,     v     State     of   Goa\    and      Bombay       Slum


^ 2023 LiveLaw (SC) 416 = 2018 (9) SCC 266
                                                   7




Redevelopment Corporation Pvt Ltd., v Samir Nariain Bhojwani^,

learned counsel seeks dismissal of the Appeal.                       He also contended that

there is no clause in the agreement prohibiting the payment of interest

and granting of the same by the learned Arbitral Tribunal is not against

law or treated as perverse or contrary to the public policy of India.

11)      On an appreciation of the rival contentions, the point that falls for

consideration        is        'Whether the order under challenge warrants

interference by this Court, in the facts and circumstances of the case?'

12)       Before dealing with the point for consideration,                      it   may     be

appropriate to mention that the learned Arbitral Tribunal on the basis of

the pleadings framed the following issues for adjudication:

      1) Whether the stipulations contained in the Respondent's extension letters /
          agreement are valid or not? Either way its effect?
      2) Whether the Claimant is entitled for the claims made?
      3) Whether the Respondent is entitled to the counter claims?
      4) Whether the parties or either of them is entitled to interest? If so at what rate
          and for which period?

      5) To what relief, if any, are the Claimants or Respondents entitled to?


13)      With regard to Issue No.1, the learned majority members noted the

period / dates concerning the several extensions of the existing contract

pending appointment of new consignment agency with stipulation to the

effect that the extensions of existing contract shall be till the specified

dates or till commencement of work by the new contractor, whichever is

lower with the existing rates or new contract rates, whichever is earlier(as

^ Civil Appeal No.7247 of 2024 (Supreme Court of India) dated 08.07.2024
  per the respective base dates as applicable) as per the board approved
 guidelines. While taking note that the claimant promptly informed that
 they are giving their acceptance for extension of existing contract as per
 the terms and conditions of the original contract agreement dated
 09.10.2009, it recorded its conclusions that RINL, in view of a claimant's
counter offer and non-receipt of unconditional acceptance, could have
stopped sending their consignments to the claimant's yard, which was
never done and probably it suited it to save the company (RINL) from
losses on account of stoppage of their work abruptly. It had also opined
that in the offer made by RINL for extension, the consideration is quiet
uncertain, that none of the parties knew as to when and what rate will be

finalized with the new contractor and further that the offer declined by the

claimant could not take the shape of an agreement, whereas its counter
offer has been accepted by the RINL by its conduct and thus the contract

was completed. The learned Arbitral Tribunal ultimately concluded that
the stipulation contained in the RINL extension letters have no validity

and not enforceable and answered the issue in favour of the claimant

holding that the amount withheld is liable to be released.

14)   In so far as the issues pertaining to the claims, as made by the
claimant and the counter claim of RINL, the learned Arbitral Tribunal dealt

with the matter elaborately and recorded a finding that RINL could not
substantiate that it suffered any kind of loss and therefore, the penalty
                                        9




levied was baseless and the claimant is entitled for refund of the same.

In so far as the counter claims, it awarded an amount of ?5,06,000/-

(towards the loss sustained by the respondent as the claimant stopped

the work for 3 days) and so far as the claim of f 1,32,46,669 towards

lower rates quoted by the incoming consignment agency, the learned

Arbitral Tribunal held that the said claim was solely based on assumption,

as no contract came into existence and therefore the RINL is not entitled

for the same.


15)   As regards, the Issue No.4 i.e., entitlement to interest, the learned

Tribunal dealt with the same item wise i.e., (i) Interest on Amount of

Penalty Deducted; (ii) Interest on withheld 10% amount from Bills; (iii)

Interest on delayed payment of invoices and (iv) Interest on unpaid

invoices and period wise. It had accordingly awarded interest on delayed

payments, pendente lite interest and future interest with               detailed


reasoning and granted the following reliefs:

   (1)The respondents shall pay to the claimant a sum of (Rs.4,34,11,355
      minus Rs.5,06,000 = Rs.4,29,05,355) (Four Crore Twenty Nine Lakh
      Five Thousand Three Flundred Fifty Five) on or before 31.07.2018.
   (2) The Respondents shall pay costs to claimant by the aforesaid date.
   (3) In case the Respondents fails to comply with the direction N0.1 and 2
      above by the appointed date, the respondents shall be liable to pay
      future interest on the sums mentioned in direction No.1 and 2 @ 9% per

      annum w.e.f. 01.07.2018 till the actual date of payment to the claimant.
                                                 10




16)     In the O.P., before the Commercial Court, it was, inter alia,

contended on behalf of the RINL, that that in the majority award rendered

by respondent Nos.2 and 3, they failed to appreciate the terms and

conditions stipulated in the letters awarding the agency                             and       have


committed an error apparent on the face of the Award in observing that

there is no concluded contract at all. It was contended that the majority

award rendered by the learned Arbitrators/respondent Nos.2 and 3 is

opposed to public policy of India as there is no stipulation for payment of

interest on delayed payment as per the contract and in the absence of the

same, granting interest at the rate of 18% p.a., is contrary to law, highly

excessive and arbitrary. On the contrary, it was argued on behalf of the

claimant that RINL failed to prove any of the ingredients stipulated under

Section 34 (2) of the Act for setting aside the Award, that the interest

granted by the arbitrators, while rendering the Award is not against Law

or    prohibited      under     Law.     The          Learned      Commercial       Court      after


considering the matter with reference to the rival                  contentions recorded its


categorical findings in the following terms -

            "22) As seen from the majority award and the minority                    award

            rendered by the learned Arbitral Tribunal they have categorically
            discussed all the submissions made by respective counsel of both
            parties at length and came to a right conclusion that a new rate
            offered    by the    petitioner   i.e.,    Rashtriya    Ispat   Nigam   Limited,

            Visakhapatnam Steel Plant was not acceptable to the first respondent
            and the new rate never came into existence by the time of completion
                                                 11




              of existence period of contract. Therefore, there is no other way to go
              except to adopt the old rates."
              "In view of the submissions made by the respective senior counsel of
              both parties as seen from the award rendered by majority arbitrators
              dt. 18.06.2018 and the minority arbitrator dt. 18.07.2018 it is evident
              that the learned Arbitral Tribunal after considering   entire material

              available on record including the documents relied upon by both
              parties and in view of the submissions made by the respective
              counsel of both parties in detail came to a conclusion that the terms
              of the contract between the parties can be proved not only by their
              words but also by their conduct. The Law is well settled that the offer
              can be accepted by conduct. The general rule is that an offer is not
              accepted by mere silence on the part of offeree, yet it does not mean
              that an acceptance always has to be given in so many words.     Under

              certain circumstances, offeree's silence coupled with his conduct,
              which takes the form of opposite act, may constitute an acceptance of
              an agreement sub-silentio.'


17)      Referring to the jurisdiction under Section 34 of the Act and the

decisions of the           Hon'ble Supreme Court of India                in M/s Dyna

Technologies Pvt Ltd., v M/s. Cromption Greaves Ltd.,^ McDermott

international Inc. v Burn Standard C. Ltd., and Ors.,^; Steel Authority

of India v Gupta Brothers^, the learned Commercial Court categorically

recorded its findings opining that the majority Arbitrators dealt with all the

aspects while allowing the additional claim made by the claimant during

the pendency of the arbitration proceedings and that no grounds are
made out to interfere with the Award.




^2019 see Online Se 1656
" (2006) 11 see 181
^ (2009) 10 see 63
                                        12




 18)     In so far the claim for interest is concerned,           the    learned

 Commercial Court formulated a separate point for consideration and
 referring to Section 31 (7)(a) of the Act, Section 3 of the Interest Act as

also the decision of the Hon'ble Apex Court in Reliance Cellulose

Products V ONGC Ltd.,^ recorded its conclusions at para 34 of the
judgment and inter alia held that in the present case, agreement is silent
with regard to stipulation for payment of interest. However, so far as the

award of the majority Arbitrators granting interest @18% p.a., on unpaid
bills and pendent lite interest, it reduced the same to 9% p.a., holding that

awarding rate of interest at 18% p.a., is highly excessive and arbitrary.
19)     Assailing the order of the learned Commercial Court to the extent it

is adverse to the interest of the appellant, Mr. Vivek Chandra Sekhar
advanced arguments as noted in para-9 of the order.             However, the

learned Arbitral Tribunal and the learned Commercial Court thoroughly

discussed about the claimant accepting the extension of the existing

contract as per the terms and conditions of the original                contract


agreement dated 09.10.2009 and continuation of consignments by the
RINL to the claimant without any demur. The majority members of the
Arbitral Tribunal on the basis of material available on record, recorded

their conclusion to the effect that the stipulation contained in the letters of
extension by the RINL are not enforceable and it acted upon the counter

offer of the claimant to continue on the existing rates by its conduct. The
 (201gj.^ see 266
                                        13




 said conclusions arrived at by the learned Arbitral Tribunal, were not

 interfered with by the learned Commercial Court in view of the settled

 legal position that the scope under Section 34 of the Act, is limited. It is

 equally settled that in an appeal under Section 37 of the Act, the scope is

 much narrower.


20)       In Parsa Kente Collieries Ltd., v Rajasthan Rajya Vidyut Nigam
Ltd.,^ it was inter alia contended that the interpretation by the learned
arbitrator of the clauses of the agreement was plausible and merely

because some other view was possible, the High Court is not justified in
interfering with the interpretation s/findings recorded by the sole arbitrator

and that too in exercise of power under Section 37 of the Act.          Partly

allowing the said case, the Hon'ble Supreme Court of India inter alia held

that it was pure and simple case of interpretation of the agreement, which

does not involve any public policy. The Hon'ble Supreme Court of India
also referred to the earlier decisions in Mc.Dermott International Inc.,

case (4 supra) and Rashtriya Ispat Nigam Ltd., v Devan Chand Ram

Saran^ including the decision in Associate Builder v D.D.A.^ wherein it

was held that when a Court is applying the public policy test to an
arbitration award it does not act as a court of appeal and consequently,
errors of facts cannot be corrected.




' (2019) 7 see 236
'(2012) 5 see 306
® (2015) 3 see 49
                                             14




 21)     In so far as the contentions with regard to awarding of interest, this
 Court see no reason to hold that the order of the learned Commercial
 Court is perverse.       In fact, it reduced the interest on unpaid bills as
 awarded by the majority arbitrators @ 18% per annum to 9% p.a., holding
that the same is highly excessive and arbitrary. Though no reasons were
assigned, the learned Commercial Court in its discussion reduced the

rate of interest. Be that as it may.

22)     In Reliance Infrastructures case (1 supra) the Hon'ble Supreme
court of India at para 14 inter alia held as follows:

               14. As far as interference with an order made under Section 34 as
              per Section 37, is concerned, it cannot be disputed that such
              interference under Section 37 cannot travel beyond the restrictions
              laid down under Section 34.        In other words, the court cannot
              undertake an independent assessment of the merits of the award   and

              must only ascertain that the exercise of power by the court under
              Section 34 has not exceeded the scope of the provision."

23)     In Bombay Slum Redevelopment Corporation Pvt Ltd., case (2
supra) the Hon'ble Supreme Court of India after referring to the various
legal precedents including MMTC Ltd., v Vedanta Ltd.,
                                                                     10
                                                                          UHL Power

Company Ltd., v State of Himachal Pradesh^^ at para 16 inter alia held
thus:


           "The jurisdiction of the Appellate Court dealing with an appeal under
           Section 37 against the judgment in a petition under Section 34 is more
           constrained than the jurisdiction of the court dealing with a petition

 (2019) 4 see 163
 (2022) 4 see 116
                                           15




            under Section 34. It is the duty of the Appellate court to consider
                                                                             of
            whether Section 34 Court has remained confined to the grounds
                                                                              The
            challenge that are available in a petition under Section 34.
            ultimate function of the Appellate Court under Section 37 is to decide
            whether the jurisdiction under Section 34 has been exercised rightly
                                                                     exercise the
            or wrongly. While doing so, the Appellate court can
                                                                        with the
            same power and jurisdiction that Section 34 Court possesses

             same constraints.


                                                                         court referred
 24)      In the light of the expression of the Hon'ble Supreme
                                                                          on the touch
 to above, this Court considering the matter in its entirety and

 stone    of Section 34 of the Act holds that the learned Commercial Court is
 well within its jurisdiction and was right in its approach , the order under
                                                                       no interference
 challenge is well within jurisdiction and as such warrants
 by this Court in the appellate jurisdiction under Section 37 of the Act. The
 point is accordingly answered against RINL - Appellant.
  25)      In the result, the Appeal is dismissed. No order as to. costs.

  26)      Consequently, the Miscellaneous Applications pending, if any, shall
  also stand dismissed.
                                                                Sd/- S.V.S.R.MURTHY
                                                                   JOINT regis;frar
                                    //TRUE COPY//

                                                                    SE          OFFICER
To,
      1. The Special Judge for Trial and Disposal of Commercial Disputes,
        Visakhapatnam, Visakhapatnam district
      2. M/s. Mauria Udyog Limited, Sector-25, Sohna Road, Faridabad Rep. by
        its Deputy General Manager, Mr. N.K. Surekha,
      3. Smt. Kommu Suvarchala, W/o. Chiranjeevi Sastri, Hindu, Aged about.
        60 years, MIG Plot No.65, Door No. 4-68-7, Lawsons Bay Colony,
        Visakhapatnam.
      4. Hon'ble Sri. Justice O.N. Khandelwal, Hindu, Aged about. 62 years,
         Residing at 1/17, Gomtinagar, Lucknow-226 010.
        5. Sri D. Tarakaram, S/o. D.A. Swamy, Hindu, Aged about. 61 years,
          Behind   Gayatri    Peetham,    HB       Colony,   Seethammadhara,
          Visakhapatnam.

       6. One CC to Sri. Vivek Chandra Sekhar S Advocate [OPUC]
       7. One CC to Sri. S Rajan Advocate [OPUC]
      8. Two CD Copies
Stu
sree
                      HIGH COURT

                     DATED:06/02/2025
                          .9.

                           •       •


                           '.1 •
    .       •

                »t
                                       \
    I
                      I




•       .




                     ORDER
COMCA.No.17 of 2021

O^ANDH^ 'x \ 9 FEB 2C2j J ^ Current Section ^^5.£esi»ATC«SS DISMISSING THE APPEAL