Section 20(1) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(1)In case of the thermal generating station and the transmission system, prudence check of capital cost shall include scrutiny of the capital expenditure, in the light of capital cost of similar projects based on past historical data, wherever available, reasonableness of financing plan, interest during construction, incidental expenditure during construction, use of efficient technology, cost over-run and time over-run, procurement of equipment and materials through competitive bidding and such other matters as may be considered appropriate by the Commission:Provided that, while carrying out the prudence check, the Commission shall also examine whether the generating company or transmission licensee, as the case may be, has been careful in its judgments and decisions in execution of the project.