Section 200(3) in The Coal Mines Regulations, 2011
(3)In the case of an opencast working, where any permanent building or structure of permanent nature, lies within the danger zone, the aggregate maximum charge per delay and per round shall be fixed by a scientific study and permission in writing for such blasting shall be obtained from the Chief Inspector, who may specify the conditions for such blasting.