Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 19]

Delhi High Court

M/S National Highways Authority Of ... vs M/S Oriental Structural Engineers Pvt. ... on 16 January, 2015

Equivalent citations: AIR 2015 DELHI 79, (2015) 1 ARBILR 322 (2015) 217 DLT 678, (2015) 217 DLT 678

Author: Rajiv Sahai Endlaw

Bench: Rajiv Sahai Endlaw

           *IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                     Date of decision: 16th January, 2015

+                        O.M.P. No.1640/2014

       M/S NATIONAL HIGHWAYS AUTHORITY
       OF INDIA                                 ..... Petitioner
                    Through: Mr. Sudhir Nandrajog, Sr. Adv. with
                             Ms. Tanu Priya Gupta, Adv.

                                   Versus

       M/S ORIENTAL STRUCTURAL
       ENGINEERS PVT. LTD.                                ..... Respondent
                    Through: None.

CORAM:-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

1.     This petition, under Section 34 of the Arbitration and Conciliation

Act, 1996, seeks setting aside of the unanimous arbitral Award dated 22nd

August, 2014, of the Arbitral Tribunal comprising of a nominee of the

petitioner and the nominee of the respondent and a presiding Arbitrator of

the choice of the nominees of the two parties, to the extent the same allows

the Claims No.2 to 6 of the respondent against the petitioner (claim No.1 of

the respondent against the petitioner was disallowed).




O.M.P. No.1640/2014                                              Page 1 of 35
 2.      The petition came up before the Court first on 22nd December, 2014

when after hearing extensively the senior counsel for the petitioner, orders

were reserved.

3.     The arbitral award emanates from the claims of the respondent against

the petitioner under the contract dated 29th September, 2005 for a price of

Rs.115,24,02,683/- between the parties for construction by the respondent of

New Four Lane Jhansi Bypass on National Highway 25 in the State of Uttar

Pradesh for the petitioner, with the stipulated date of start as 21st November,

2005 and the stipulated date of completion as 20 th May, 2008. The works

were however completed only on 31st August, 2010.

4.     The petitioner seeks setting aside of the arbitral award to the extent:-

       (i)     It allows the Claim No.2 of the respondent in the sum of

               Rs.89,66,783/- with interest for wrongful certification

               of Bills of Quantity for construction of reinforced earth,

               precast concrete facia panel, RCC crash barrier etc. for the

               period till 31 s t August, 2010 and holds the respondent

               entitled to further sums on similar basis for period subsequent




O.M.P. No.1640/2014                                                  Page 2 of 35
                to 31st August, 2010 and till final account in respect of wrong

               quantification;

       (ii)    It allows Claim No.3 of the respondent in the sum of

               Rs.30,65,779/-towards delay till 31st August, 2010 in payments

               of the admitted amounts;

       (iii)   It allows Claim No.4 of the respondent in the sum of

               Rs.3,21,64,657/- for non-payment of price adjustment upto 31st

               August, 2010 and in a sum of Rs.60,87,471/- towards interest

               thereon till 31st August, 2010 and further finds the respondent

               entitled to payment of correct quantification of price adjustment

               in subsequent IPCs till final account, together with interest

               thereon;

       (iv)    It allows Claim No.5 of the respondent in the sum of

               Rs.16,09,647/- towards additional cost due to increase in

               royalty on various minerals for the quantities executed till

               February, 2010 with interest @ 10% compounded monthly

               from 9th March, 2010 till the completion of the work and simple

               interest @ 10% per annum including on compound interest


O.M.P. No.1640/2014                                                  Page 3 of 35
                aforesaid, from 1st September, 2010 till the date of actual

               payment;

       (v)     It allows Claim No.6 of the respondent in the sum of

               Rs.2,68,69,295/- on account of price escalation till 31st August,

               2010 and in a sum of Rs.48,29,367/- towards interest @ 10%

               per annum thereon compounded monthly and simple interest @

               10% per annum from 1st September, 2010 till the date of actual

               payment;

5.     The petitioner seeks setting aside of the said arbitral award on the

grounds of:-

       (a)     The Arbitral Tribunal having wrongly read the Contract

               between the parties to conclude that certain works required to

               be carried out were not part of the Contract when in fact as per

               the Contract they were not to be measured separately and were

               to be deemed to be incidental to the work under the Contract.

       (b)     Allowing of certain claims of the respondent by the Arbitral

               Tribunal amounting to the respondent being paid twice for the

               same work.



O.M.P. No.1640/2014                                                  Page 4 of 35
        (c)     The delays in payment of the admitted amounts by the

               petitioner to the respondent being on account of the respondent

               failing to comply with the obligations it was required to comply

               with before receiving payment and the petitioner being thus not

               liable to pay interest and the Arbitral Tribunal having wrongly

               concluded that the petitioner had delayed the payment.

       (d)     The Arbitral Tribunal having not considered that the respondent

               had not sought any clarification to the addendum / corrigendum

               of the pre-bid meeting, thereby impliedly accepting the

               addendum and having started making representation only after

               major work were executed.

       (e)     The Arbitral Tribunal having not considered that if the

               respondent intended to claim any additional payment pursuant

               to any clause in the Contract, the respondent under the contract

               was required to within 28 days from the date of dispute notify

               the engineer with a copy marked to the petitioner, of his such

               intention and the respondent had not done so and was thus not

               entitled to the claim.




O.M.P. No.1640/2014                                                 Page 5 of 35
        (f)     The Arbitral Tribunal having awarded price adjustment at a rate

               contrary to the Contract between the parties and the

               clarifications, addendum and corrigendum issued by the

               petitioner;

       (g)     The respondent being not entitled to any additional costs due to

               increase in royalty on various minerals owing to its failure to

               notify the engineer in this regard within the time prescribed and

               the Arbitral Tribunal having not considered the said aspect.

       (h)     The Arbitral Tribunal having wrongly interpreted the

               contractual provision regarding additional cost; contractually,

               the respondent was entitled thereto only if the additional cost

               was on account of change in legislation; the additional cost

               claimed by the respondent and allowed by the Arbitral Tribunal

               was not on account of change in legislation. The Arbitral

               Tribunal having misinterpreted the contract between the parties;

       (i)     The Arbitral Tribunal having overlooked other contractual

               provisions and facts.

       (j)     The rate of interest @ 10% granted by the Arbitral Tribunal

               being excessive.

O.M.P. No.1640/2014                                                  Page 6 of 35
        (k)     The issue with respect to additional cost due to increase in

               royalty on various minerals involved the issue of subsequent

               legislation and which is pending consideration before the

               Supreme Court; and,

       The petitioner thus contends that the award is contrary to public

       policy and law of the land, within the meaning of Oil and National

       Gas Corporation Ltd. Vs. SAW Pipes Ltd. (2003) 5 SCC 705.

6.     The senior counsel for the petitioner during the hearing fairly

informed that the award, insofar as allowing the Claim No.5 of the

respondent towards additional cost due to increase in royalty on various

minerals, is in accordance with the judgments of the Single Judge and the

Division Bench of this Court but the issue is pending consideration before

the Supreme Court. The senior counsel also agrees that the challenge to the

award is on the grounds either of the Arbitral Tribunal having wrongly

interpreted the contract between the parties or having not considered the

defence of the petitioner to the claims of the respondent which have been

allowed. With regard to award on Claim No.3 allowing interest on delayed

payments, it is argued that the respondent had failed to furnish the

clarification sought from it and so the engineer had no option but to assess

O.M.P. No.1640/2014                                              Page 7 of 35
 the payment due on best judgment and payment was made accordingly and

thus the petitioner could not be held liable for any interest for delay. It was

argued that under the Contract the engineer was entitled to seek such

clarifications and the engineer having done so and the respondent having not

submitted the clarifications, no delay in payment could be attributed to the

petitioner. On enquiry, as to whether the payment ultimately made to the

respondent was as demanded by the respondent, it was informed that there

was a difference of 5% between what the respondent had demanded and

what was paid to the respondent. It was yet further contended that though

the respondent in the pre-bid meeting had given a discount of 7.5% on each

item and though in accordance therewith the petitioner was entitled to

discount of 7.5% on payment even if found due on increased work also but

the Arbitral Tribunal while allowing the claim of the respondent for price

escalation has not given the said discount of 7.5%. With respect to the

award on Claim No.4, it is argued that the Arbitral Tribunal did not consider

that the respondent was required to raise the said dispute within 28 days and

had raised the same just one month prior to the closure of the award.

7.     I had during the hearing enquired from the senior counsel for the

petitioner as to under which of the grounds stipulated in Section 34 of the

O.M.P. No.1640/2014                                                 Page 8 of 35
 Arbitration Act for setting aside of the award, do the aforesaid grounds

urged, fit. Attention of the senior counsel was invited to the fact that Section

34(2) provides "an arbitral award may be set aside by the Court only if" the

grounds mentioned thereunder were satisfied. It was enquired whether not

the use by the legislature of the word "only" is indicative of, the arbitral

award being not liable to be set aside on any ground other than those

specified. Such language, even under the 1940 Act, was in State of U.P. Vs.

Allied Constructions (2003) 7 SCC 396 held to be restrictive in operation.

8.     The senior counsel responded that the arbitration being an

adjudicatory mechanism, the award, if adjudicates contrary to law or

contrary to the facts, has to be held to be in conflict with the public policy of

India. Reference of course is made to Saw Pipes Ltd. (supra).


9.     Attention of the senior counsel for the petitioner has however been

invited to the judgment of the Division Bench of this Court of which the

undersigned was a member in Delhi Development Authority Vs. Bhardwaj

Brothers MANU/DE/1753/2014 and in which the earlier judgment of the

same Division Bench in State Trading Corporation of India Ltd. Vs. M/s.




O.M.P. No.1640/2014                                                  Page 9 of 35
 Toepfer International Asia Pte Ltd. MANU/DE/1480/2014 was quoted as

laying down as under:

          "5. The challenge in this appeal is on the ground that the learned
          Single Judge ignored that the interpretation of the contract
          between the parties given by the Arbitral Tribunal is contrary to
          the express terms and conditions thereof and the Arbitral Tribunal
          has given a meaning to the terms and conditions which is not
          contemplated in the contract. The senior counsel for the appellant
          thus wants us to read the contract between the parties, particularly
          the clauses relating to demurrage, and then to judge whether the
          interpretation thereof by the Arbitral Tribunal is correct or not.
          6.   In our view, the interpretation in Saw Pipes Ltd. supra (ONGC
          Ltd. Vs. Saw Pipes Ltd. (2003) 5 SCC 705) of the ground in Section
          34 of the Act for setting aside of the arbitral award, for the reason
          of the same being in conflict with the public policy of India, would
          not permit setting aside, in the aforesaid facts. A Section 34
          proceeding, which in essence is the remedy of annulment, cannot
          be used by one party to convert the same into a remedy of appeal.
          In our view, mere erroneous/wrong finding of fact by the Arbitral
          Tribunal or even an erroneous interpretation of documents
          /evidence, is non-interferable under Section 34 and if such
          interference is done by the Court, the same will set at naught the
          whole purpose of amendment of the Arbitration Act.

          7.   Arbitration is intended to be a faster and less expensive
          alternative to the courts. If this is one's motivation and expectation,
          then the finality of the arbitral award is very important. The
          remedy provided in Section 34 against an arbitral award is in no


O.M.P. No.1640/2014                                                         Page 10 of 35
           sense an appeal. The legislative intent in Section 34 was to make
          the result of the annulment procedure prescribed therein
          potentially different from that in an appeal. In appeal, the decision
          under review not only may be confirmed, but may also be modified.
          In annulment, on the other hand, the decision under review may
          either be invalidated in whole or in part or be left to stand if the
          plea for annulment is rejected. Annulment operates to negate a
          decision, in whole or in part, thereby depriving the portion negated
          of legal force and returning the parties, as to that portion, to their
          original litigating positions. Annulment can void, while appeal can
          modify. Section 34 is found to provide for annulment only on the
          grounds affecting legitimacy of the process of decision as distinct
          from substantive correctness of the contents of the decision. A
          remedy of appeal focuses upon both legitimacy of the process of
          decision and the substantive correctness of the decision.
          Annulment, in the case of arbitration focuses not on the correctness
          of decision but rather more narrowly considers whether,
          regardless of errors in application of law or determination of facts,
          the decision resulted from a legitimate process.

          8.   In the case of arbitration, the parties through their agreement
          create an entirely different situation because regardless of how
          complex or simple a dispute resolution mechanism they create,
          they almost always agree that the resultant award will be final and
          binding upon them. In other words, regardless of whether there are
          errors of application of law or ascertainment of fact, the parties
          agree that the award will be regarded as substantively correct. Yet,
          although the content of the award is thus final, parties may still
          challenge the legitimacy of the decision-making process leading to
          the award. In essence, parties are always free to argue that they are
O.M.P. No.1640/2014                                                        Page 11 of 35
           not bound by a given "award" because what was labeled an award
          is the result of an illegitimate process of decision.

          9.   This is the core of the notion of annulment in arbitration. In a
          sense, annulment is all that doctrinally survives the parties
          agreement to regard the award as final and binding. Given the
          agreement of the parties, annulment requires a challenge to the
          legitimacy of the process of decision, rather than the substantive
          correctness of the award.

          10. Joseph Raz in his paper "The Politics of the Rule of Law" has
          opined that the function of the rule of law is to facilitate the
          integration of a particular piece of legislation with the underlying
          doctrines of the legal system; the authority of the courts to harness
          legislation to legal doctrine arises neither from their superior
          wisdom nor from any superior law of which they are the
          custodians; it arises out of the need to bring legislation in line with
          doctrine. The courts ensure coherence of purpose of law, ensuring
          that its different parts do not fight each other. The learned author
          has further observed that a law which is incoherent in purpose
          serves none of its inconsistent purposes very well. Purposes
          conflict if due to contingencies of life serving one will in some cases
          retard the other. The second basis for the authority of the courts to
          integrate legislation with doctrine is the need to mix the fruits of
          long established traditions with the urgencies of short term
          exigencies. In ensuring the coherence of law, the courts are
          expected to ensure the effectiveness of the democratic rule. In
          giving weight to the preservation of long established doctrines i.e.,
          the traditions, they protect the long term interest of the people
          from being swamped by the short term. We have taken the liberty


O.M.P. No.1640/2014                                                         Page 12 of 35
           to quote from the aforesaid paper since the courts are being
          repeatedly called upon to adjudicate on the various provisions of
          the re-enacted arbitration law. From the various pronouncements
          in the last about 18 years since re-enactment, it appears that the
          danger of interpreting the new Act in a manner doing away with
          the whole object/purpose of re-enactment is imminent. The courts
          continue to be inundated till date, in spite of repeal of the old Act
          18 years ago, with cases thereunder also, particularly of challenge
          to the arbitral award. Provisions of the old and the new Act relating
          to inference with the arbitral award are vastly different. However,
          when the courts, in the same day are wrestling with a matter
          concerning arbitral award under the old Act and with that under
          the new Act, the chances of culling out the huge difference between
          the two are minimal. It is not to be forgotten that the courts deal
          with and rule on disputes where monies and properties of real
          persons are at stake. The courts do not decide in abstract. Thus,
          when in one case the courts interfere with the arbitral award for
          the reason of the same not rendering to the litigant what the courts
          would have granted to him, the courts find it difficult in the very
          next case, though under the new Act, to apply different parameters.

          11. Arbitration under the 1940 Act could not achieve the savings in
          time and money for which it was enacted and had merely become a
          first step in lengthy litigation. Reference in this regard can be made
          to para 35 of Bharat Aluminium Company Vs. Kaiser Aluminium
          Technical Services Inc. (2012) 9 SCC 552. It was to get over the said
          malady that the law was sought to be overhauled. While under the
          old Act, the award was unenforceable till made rule of the court and
          for which it had to pass various tests as laid down therein and
          general power/authority was vested in the court to modify the
O.M.P. No.1640/2014                                                        Page 13 of 35
           award, all this was removed in the new Act. The new Act not only
          made the award executable as a decree after the time for preferring
          objection with respect thereto had expired and without requiring it
          to be necessarily made rule of the court but also did away with
          condonation of delay in filing the said objections. The
          reason/purpose being expediency. The grounds on which the
          objections could be filed are also such which if made out, the only
          consequence thereof could be setting aside of the award. It is for
          this reason that under new Act there is no power to the court to
          modify the award or to remit the award etc. as under the old Act. A
          perusal of the various grounds enunciated in Section 34 will show
          that the same are procedural in nature i.e., concerning legitimacy of
          the process of decision. While doing so, the ground, of the award
          being in conflict with Public Policy of India, was also incorporated.
          However the juxtaposition of Section 34(2)(b)(ii) shows that the
          reference to 'Public Policy' is also in relation to fraud or corruption
          in the making of the award. The new Act was being understood so
          [see Konkan Railway Corporation Ltd. Vs. Mehul Construction Co.
          (2000) 7 SCC 201 (para 4 and which has not been set aside in S.B.P.
          & Co. Vs. Patel Engineering Ltd. (2005) 8 SCC 618)] till the Supreme
          Court in Saw Pipes Ltd. (supra) held that the phrase "Public Policy
          of India" is required to be given wider meaning and if the award on
          the face of it is patently in violation of statutory provisions, it
          cannot      be   said   to   be   in   public    interest   and     such
          award/judgment/decision is likely to adversely affect the
          administration of justice. In para 37 of the judgment it was held
          that award could be set aside if it is contrary to fundamental policy
          of Indian Law or the interest of India or justice or morality or if it is
          patently illegal. A rider was however put that illegality must go to

O.M.P. No.1640/2014                                                           Page 14 of 35
           the root of the matter and if the illegality is of trivial nature it
          cannot be held that the award is against the public policy. Yet
          another test laid down is of the award being so unfair and
          unreasonable that it shakes the conscience of the court.

          12. The courts have thereafter been inundated with challenges to
          the award. The objections to the award are drafted like appeals to
          the courts; grounds are urged to show each and every finding of the
          arbitrator to be either contrary to the record or to the law and thus
          pleaded to be against the Public Policy of India. As aforesaid, the
          courts are vested with a difficult task of simultaneously dealing
          with such objections under two diverse provisions and which has
          led to the courts in some instances dealing with awards under the
          new Act on the parameters under the old Act.

          13. The result is that the goal of re-enactment has been missed.

          14. The re-enactment was not only to achieve savings in time and
          prevent arbitration from merely becoming the first step in lengthy
          litigation but also in consonance with the international treaties and
          commitments of this country thereto. Since the enactment of the
          1940 Act, the international barriers had disappeared and the
          volume of international trade had grown phenomenally. The new
          Act was modeled on the model law of international commercial
          arbitration of the United Nations Commission on International
          Trade Law (UNICTRAL). It was enacted to make it more responsive
          to contemporary requirements. The process of economic
          liberalization had brought huge foreign investment in India. Such
          foreign investment was hesitant, owing to there being no effective
          mode of settlement of domestic and international disputes. It was
          with such lofty ideals and with a view to attract foreign investment

O.M.P. No.1640/2014                                                       Page 15 of 35
           that the re-enactment was done. If the courts are to,
          notwithstanding such re-enactment, deal with the arbitration
          matters as under the old Act it would be a breach of the
          commitment made under the treaties on international trade.

          15. Applying the aforesaid test, we are afraid, the arguments of the
          senior counsel for the appellant are beyond the scope of Section 34.

          16. The senior counsel for the respondent has in this regard rightly
          argued that the scope of appeal under Section 37 is even more
          restricted. It has been so held by the Division Benches of this Court
          in Thyssen Krupp Werkstoffe Vs. Steel Authority of India
          MANU/DE/1853/2011 and Shree Vinayak Cement Clearing Agency
          Vs. Cement Corporation of India 147 (2007) DLT 385. It is also the
          contention of the senior counsel for the respondent that the
          argument made by the appellant before the learned Single Judge
          and being made before this Court, that the particular clause in the
          contract is a contract of indemnification, was not even raised
          before the Arbitral Tribunal and did not form the ground in the
          OMP filed under Section 34 of the Act and was raised for the first
          time in the arguments.

          17. The Supreme Court in Rashtriya Ispat Nigam Ltd. Vs. Dewan
          Chand Ram Saran (2012) 5 SCC 306 refused to set aside an arbitral
          award, under the 1996 Act on the ground that the view taken by
          the Arbitral Tribunal was against the terms of the contract and held
          that it could not be said that the Arbitral Tribunal had travelled
          outside its jurisdiction and the Court could not substitute its view
          in place of the interpretation accepted by the Arbitral Tribunal. It
          was reiterated that the Arbitral Tribunal is legitimately entitled to
          take the view which it holds to be correct one after considering the

O.M.P. No.1640/2014                                                       Page 16 of 35
           material before it and after interpreting the provisions of the
          Agreement and if the Arbitral Tribunal does so, its decision has to
          be accepted as final and binding. Reliance in this regard was placed
          on Sumitomo Heavy Industries Ltd. Vs. ONGC Ltd. (2010) 11 SCC
          296 and on Kwality MFG. Corporation Vs. Central Warehousing
          Corporation (2009) 5 SCC 142. Similarly, in P.R. Shah, Shares &
          Stock Broker (P) Ltd. V. B.H.H. Securities (P) Ltd. (2012) 1 SCC 594
          it was held that a Court does not sit in appeal over the award of an
          Arbitral Tribunal by reassessing or reappreciating evidence and an
          award can be challenged only under the grounds mentioned in
          Section 34(2) and in the absence of any such ground it is not
          possible to reexamine the facts to find out whether a different
          decision can be arrived at. A Division Bench of this Court also
          recently in National Highways Authority of India Vs. M/s. Lanco
          Infratech Ltd. MANU/DE/0609/2014 held that an interpretation
          placed on the contract is a matter within the jurisdiction of the
          Arbitral Tribunal and even if an error exists, this is an error of fact
          within jurisdiction, which cannot be reappreciated by the Court
          under Section 34 of the Act. The Supreme Court in Steel Authority of
          India Ltd. Vs. Gupta Brother Steel Tubes Ltd. (2009) 10 SCC 63 even
          while dealing with a challenge to an arbitral award under the 1940
          Act reiterated that an error by the Arbitrator relatable to
          interpretation of contract is an error within his jurisdiction and is
          not an error on the face of the award and is not amenable to
          correction by the Courts. It was further held that the legal position
          is no more res integra that the Arbitrator having been made the
          final Arbiter of resolution of dispute between the parties, the award
          is not open to challenge on the ground that Arbitrator has reached
          at a wrong conclusion.

O.M.P. No.1640/2014                                                         Page 17 of 35
           18. If we were to start analyzing the contract between the parties
          and interpreting the terms and conditions thereof and which will
          necessarily have to be in the light of the contemporaneous conduct
          of the parties, it will be nothing else than sitting in appeal over the
          arbitral award and which is not permissible."

and it was further held:


       (I)     That a Division Bench of this Court in New Delhi Apartment

               Group     Housing       Society     Vs.    Jyoti    Swaroop          Mittal

               MANU/DE/9107/2007 has held that Saw Pipes Ltd. cannot be

               read as permitting a Court exercising powers under Section 34

               to sit in appeal over the findings of fact recorded by the Arbitral

               Tribunal or on interpretation placed by the Arbitral Tribunal of

               the provisions of the Agreement.


       (II)    That the parties having agreed to be bound by the arbitral award

               and by declaring it to be final, also agree to be bound by the

               wrong interpretation or an erroneous application of law by the

               Arbitral Tribunal and once the parties have so agreed, they

               cannot apply for setting aside of the arbitral award on the said

               ground. Reliance in this regard was placed on Tarapore and

               Co. Vs. Cochin Shipyard Ltd., Cochin (1984) 2 SCC 680, U.P.
O.M.P. No.1640/2014                                                         Page 18 of 35
                Hotels Vs. U.P. State Electricity Board (1989) 1 SCC 359 and

               N. Chellappan Vs. Secretary, Kerala State Electricity Board

               (1975) 1 SCC 289, though all under the Arbitration Act, 1940;

               and,


       (III) "11.     We are further of the view that the scope of judicial review of
               an arbitral award is akin to review under Article 226 of the
               Constitution of India of the decisions of bodies, where it is a settled
               principle of law (See State of U.P. Vs. Maharaja Dharmander Prasad
               Singh (1989) 2 SCC 505 and State of U.P. Vs. Johri Mal (2004) 4 SCC
               714) that the judicial review is of the decision making process and not
               of the decision on merits and cannot be converted into an appeal. This
               is quite evident from the various Clauses of Section 34 (2)(a) which
               prescribe the grounds of challenge on the lines of violation of the
               principles of natural justice in making of the award or invalidity of the
               arbitral agreement and non-arbitrability of the disputes arbitrated
               and of the composition of the Arbitral Tribunal or arbitral procedure
               being not in accordance with the agreement between the parties.
               Section 34(2)(b) adds the ground of the arbitral award being in
               conflict with the public policy of India. None of the said grounds are
               the grounds of challenge on the merits of the award. The ground of
               challenge of the award being in conflict with the public policy of India
               is explained as the award being induced or affected by fraud or
               corruption or being in violation of Section 75 or Section 81. Thus the
               grounds of challenge are akin to the grounds of judicial review under
               Article 226 and not to grounds of appeal or revision.           We are
               reminded of the merits legality distinction in judicial review as culled

O.M.P. No.1640/2014                                                        Page 19 of 35
                out by Lord Hailsham in The North Wales Vs. Evans (1982) 1 WLR
               1155 by observing "the purpose of judicial review is to ensure that the
               individual receives fair treatment, and not to ensure that the
               authority, after according fair treatment, reaches on a matter which it
               is authorized by law to decide for itself a conclusion which is correct
               in the eyes of the Court". Lord Brightman in the same judgment held
               that judicial review, as the words imply, is not an appeal from a
               decision, but a review of the manner in which the decision was made
               and it would be an error to think that the Court sits in judgment not
               only on the correctness of the decision making process but also on the
               correctness of the decision itself. It was clarified that only when the
               issue raised in judicial review is whether a decision is vitiated the
               judicial review of the decision making process includes examination,
               as a matter of law, of the relevance of the factors. In our opinion the
               same is an apt test also for judicial review of the arbitral awards and
               just like a mere wrong decision without anything more is not enough
               to attract the power of judicial review, the supervisory jurisdiction
               conferred on the Court under the Arbitration Act is limited to see that
               the Arbitral Tribunal functions within the limits of its authority and
               that the arbitral award does not occasion miscarriage of justice. The
               Supreme Court in Mc. Dermott International Inc. Vs. Burn Standard Co.
               Ltd. (2006) 11 SCC 181 commenting on the radical changes brought
               about by the re-enactment of the arbitration law observed that the
               role of the Courts under the new law is only supervisory, permitting
               intervention in few circumstances only, like, in case of fraud or bias by
               the arbitrators, violation of natural justice etc. and the Court cannot
               correct the errors of arbitrators and can only quash the award leaving
               the parties free to begin arbitration again.



O.M.P. No.1640/2014                                                        Page 20 of 35
                12.      Of the finality of arbitral awards, there is no doubt under our
               arbitration law. The Supreme Court as far back as in Union of India Vs.
               A.L. Rallia Ram AIR 1963 SC 1685 held that:-

                      "An award being a decision of an arbitrator whether a lawyer or a
                      layman chosen by the parties, and entrusted with power to decide a
                      dispute submitted to him is ordinarily not liable to be challenged on
                      the ground that it is erroneous. In order to make arbitration effective
                      and the awards enforceable, machinery is devised for lending the
                      assistance of the ordinary Courts. The Courts are also entrusted
                      with power to modify or correct the award on the ground of
                      imperfect form or clerical errors, or decision on questions not
                      referred, which are severable from those referred........The Court
                      may also set aside an award on the ground of corruption or
                      misconduct of the arbitrator, or that a party has been guilty of
                      fraudulent concealment or wilful deception. But the Court cannot
                      interfere with the award if otherwise proper on the ground that the
                      decision appears to it to be erroneous. The award of the arbitrator is
                      ordinarily final and conclusive, unless a contrary intention is
                      disclosed by the agreement. The award is the decision of a
                      domestic tribunal chosen by the parties, and the civil courts which
                      are entrusted with the power to facilitate arbitration and to effectuate
                      the awards, cannot exercise appellate powers over the decision.
                      Wrong or right the decision is binding, if it be reached fairly after
                      giving adequate opportunity to the parties to place their grievances
                      in the manner provided in the arbitration agreement."




O.M.P. No.1640/2014                                                                     Page 21 of 35
                       of course the said judgment being under the Arbitration Act, 1940
               proceeds to hold that an award is bad on the ground of error of law on
               the face of it. However the legislature while re-enacting the arbitration
               law has removed the ground of challenge of error of law on the face of
               the award. In Mc. Dermott International Inc. supra also it was held that
               the parties to the Arbitration Agreement make a conscious decision to
               exclude the Courts jurisdiction as they prefer the expediency and finality
               offered by arbitration. I am bound to respect the said change brought
               about by the legislature and cannot dogmatically review the awards on
               the grounds of challenge which have been intentionally taken away by
               the legislature.


               13.     It cannot also be lost sight of that non-conferring of finality on the
               arbitral awards not only affects the speed and expense of arbitration but
               also has a more subtle consequences of, extensive judicial review
               changing the nature of the arbitral process to an even greater extent. If
               arbitration becomes simply another level of decision making, subject to
               judicial review on merits, arbitrators may begin to decide cases and
               write opinions in such a way as to insulate their awards against judicial
               reversal producing opinions that parrot the appropriate statutory
               standards in conclusory terms, but suffer from a lack of reasoned
               analysis. Such a shift from the arbitral model, in which decision makers
               are free to focus solely on the case before them rather than on the case
               as it might appear to an Appellate Court, to the administrative model, in
               which decision makers are often concerned primarily with building a
               record for review, in my opinion would substantially undercut the ability
               of arbitrators to successfully resolve disputes. The Courts therefore have
               no business weighing the merits of the grievance, considering whether
               there is equity in a particular claim, or determining whether there is

O.M.P. No.1640/2014                                                          Page 22 of 35
                particular language in the written instrument which will support the
               claim. The agreement is to submit all grievances to arbitration, not
               merely those which the Court will deem meritorious. The Courts if start
               undertaking to determine the merits of the grievance, would be usurping
               the function which under that Arbitration Act, 1996 is entrusted to the
               Arbitration Tribunal. This plenary review by the Courts of the merits
               would make meaningless the provisions that the arbitral award is final,
               for in reality it would almost never be final. I though may admit that
               sieving out the genuine challenges from those which are effectively
               appeals on merits is not easy.


               14.    Arbitration will not survive, much less flourish, if this core
               precept is not followed through by the Courts. The integrity and efficacy
               of arbitration as a parallel dispute resolution system will be subverted if
               the Courts appear unable or unwilling to restrain themselves from
               entering into the merits of every arbitral decision that comes before it.
               The power to intervene must and should only be exercised charily,
               within the framework of the Arbitration Act. Minimal curial intervention
               is underpinned by need to recognise the autonomy of the arbitral
               process by encouraging finality, so that its advantage as an efficient
               alternative dispute resolution process is not undermined. The parties
               having opted for arbitration, must be taken to have acknowledged and
               accepted the attendant risks of having only a very limited right of
               recourse to the Courts. It would be neither appropriate nor consonant
               for the Court to lend assistance to a dissatisfied party by exercising
               appellate function over arbitral awards, save to the extent statutorily
               permitted."




O.M.P. No.1640/2014                                                        Page 23 of 35
 10.    I have enquired from the senior counsel for the petitioner whether not

at least this Court would be bound by the judgment aforesaid of the Division

Bench and as per which the grounds urged by the petitioner for setting aside

of the Arbitral Award are not within the ambit of Section 34(2) of the

Arbitration Act.

11.    The senior counsel for the petitioner has not shown any judgment to

the contrary.

12.    I may add, an indication of what the legislature, while re-enacting the

arbitration law, meant by including the ground, of the arbitral award being in

conflict with public policy of India, for setting aside of arbitral awards can

be had from the Explanation to Section 34(2) which declares that an award is

in conflict with the public policy of India if the making of the award was

induced or affected by fraud or corruption or was in violation of Section 75

or Section 81. Sections 75 as well as 81 are contained in Part III titled

„Conciliation‟. Section 75 requires the parties and the conciliator to keep

confidential all matters relating to conciliation proceedings and the

settlement agreement. Section 81 provides that the parties shall not rely on


O.M.P. No.1640/2014                                                Page 24 of 35
 or introduce as evidence in arbitral or judicial proceedings, views expressed

or suggestions made by the other party in respect of a possible settlement of

the dispute, the admissions made by the other party in course of the

conciliation proceedings, the proposals made by the conciliator, the fact that

the other party had indicated his willingness to accept a proposal for

settlement made by the conciliator. Thus, if the arbitral award is based on

what had transpired in the conciliation proceedings which ultimately failed

and not on adjudication by the Arbitral Tribunal, it would be deemed to be in

conflict with the public policy of India.       Though the explanation to

Section 34(2) containing the ground of the arbitral award being in conflict

with the public policy of India is prefaced with "without prejudice to the

generality of Section 34(2)(b)(ii)" but the declaration therein of the award

being in conflict with the public policy of India if the making of the award

was induced by fraud or corruption or was in violation of Sections 75 or 81,

in my humble view is suggestive of the expression "the public policy of

India" being required to be read as meaning grounds ejusdem generis with

the grounds of fraud or corruption or the award being based on material

exchanged in conciliation which ultimately failed. In my view, the same

cannot be read as referring to public policy of India qua adjudication of

O.M.P. No.1640/2014                                                Page 25 of 35
 disputes in Courts, where error of law or fact is a ground for interference by

higher Court. If the intent was to make the award liable to be set aside if

contrary to the substantive law applicable to the decision thereof the

legislature would have provided so. Even under the 1940 Act, neither the

error of law nor of fact in the arbitral award was a ground for setting aside

thereof. The preamble to the re-enacted Act states the purpose of the re-

enactment to make our domestic law relating to arbitration in consonance

with the United Nations Commission on International Trade Law

(UNCITRAL) Model Law and the grounds of interference with the arbitral

award under the same were/are much narrower than the grounds of

interference under the 1940 Act. If the words "in conflict with the public

policy of India" are to be read as permitting interference with the arbitral

award whenever the same is found to be contrary to the substantive law

applicable to the merits of the dispute, the same in my view would be in

violation of the preamble to the re-enacted law.


13.    I may however notice Oil and Natural Gas Corporation Ltd. Vs.

Western GECO International Ltd. (2014) 9 SCC 263 where also it was held:-




O.M.P. No.1640/2014                                                Page 26 of 35
         "35. What then would constitute the 'Fundamental policy of Indian
        Law' is the question. The decision in Saw Pipes Ltd. (supra) does not
        elaborate that aspect. Even so, the expression must, in our opinion,
        include all such fundamental principles as providing a basis for
        administration of justice and enforcement of law in this country.
        Without meaning to exhaustively enumerate the purport of the
        expression "Fundamental Policy of Indian Law", we may refer to three
        distinct and fundamental juristic principles that must necessarily be
        understood as a part and parcel of the Fundamental Policy of Indian
        law. The first and foremost is the principle that in every determination
        whether by a Court or other authority that affects the rights of a citizen
        or leads to any civil consequences, the Court or authority concerned is
        bound to adopt what is in legal parlance called a 'judicial approach' in
        the matter. The duty to adopt a judicial approach arises from the very
        nature of the power exercised by the Court or the authority does not
        have to be separately or additionally enjoined upon the fora concerned.
        What must be remembered is that the importance of Judicial approach
        in judicial and quasi judicial determination lies in the fact so long as the
        Court, Tribunal or the authority exercising powers that affect the rights
        or obligations of the parties before them shows fidelity to judicial
        approach, they cannot act in an arbitrary, capricious or whimsical
        manner. Judicial approach ensures that the authority acts bonafide and
        deals with the subject in a fair, reasonable and objective manner and
        that its decision is not actuated by any extraneous consideration.
        Judicial approach in that sense acts as a check against flaws and faults
        that can render the decision of a Court, Tribunal or Authority
        vulnerable to challenge.




O.M.P. No.1640/2014                                                          Page 27 of 35
         36.    In Ridge v. Baldwin [1963 2 All ER 66], the House of Lords was
        considering the question whether a Watch Committee in exercising its
        authority Under Section 191 of the Municipal Corporations Act, 1882
        was required to act judicially. The majority decision was that it had to
        act judicially and since the order of dismissal was passed without
        furnishing to the Appellant a specific charge, it was a nullity. Dealing
        with the Appellant's contention that the Watch Committee had to act
        judicially, Lord Reid relied upon the following observations made by
        Atkin L.J. in [1924] 1 KB at pp. 206, 207:


               Wherever anybody of persons having legal authority to
               determine questions affecting the rights of subjects, and
               having the duty to act judicially, act in excess of their legal
               authority, they are subject to the controlling jurisdiction of
               the King's Bench Division exercised in these writs.


        37.    The view taken by Lord Reid was relied upon by a Constitution
        Bench of this Court in A.C. Co. Ltd. v. P.N. Sharma and Anr. AIR 1965 SC
        1595 where Gajendragadkar, C.J. speaking for the Court observed:

               In other words, according to Lord Reid's judgment, the
               necessity to follow judicial procedure and observe the
               principles of natural justice, flows from the nature of the
               decision which the watch committee had been authorised to
               reach Under Section 191(4). It would thus be seen that the
               area where the principles of natural justice have to be
               followed and judicial approach has to be adopted, has
               become wider and consequently, the horizon of writ
               jurisdiction has been extended in a corresponding measure.


O.M.P. No.1640/2014                                                        Page 28 of 35
                In dealing with questions as to whether any impugned
               orders   could   be   revised   Under     Article 226 of   our
               Constitution, the test prescribed by Lord Reid in this
               judgment may afford considerable assistance.

        38.    Equally important and indeed fundamental to the policy of
        Indian law is the principle that a Court and so also a quasi-judicial
        authority must, while determining the rights and obligations of parties
        before it, do so in accordance with the principles of natural justice.
        Besides the celebrated 'audi alteram partem' rule one of the facets of
        the principles of natural justice is that the Court/authority deciding the
        matter must apply its mind to the attendant facts and circumstances
        while taking a view one way or the other. Non-application of mind is a
        defect that is fatal to any adjudication. Application of mind is best
        demonstrated by disclosure of the mind and disclosure of mind is best
        done by recording reasons in support of the decision which the Court
        or authority is taking. The requirement that an adjudicatory authority
        must apply its mind is, in that view, so deeply embedded in our
        jurisprudence that it can be described as a fundamental policy of
        Indian Law.


        39.    No less important is the principle now recognised as a salutary
        juristic fundamental in administrative law that a decision which is
        perverse or so irrational that no reasonable person would have arrived
        at the same will not be sustained in a Court of law. Perversity or
        irrationality of decisions is tested on the touchstone of Wednesbury's
        principle of reasonableness. Decisions that fall short of the standards
        of reasonableness are open to challenge in a Court of law often in writ




O.M.P. No.1640/2014                                                        Page 29 of 35
         jurisdiction of the Superior courts but no less in statutory processes
        where ever the same are available.


        40.    It is neither necessary nor proper for us to attempt an exhaustive
        enumeration of what would constitute the fundamental policy of
        Indian law nor is it possible to place the expression in the straitjacket
        of a definition. What is important in the context of the case at hand is
        that if on facts proved before them the arbitrators fail to draw an
        inference which ought to have been drawn or if they have drawn an
        inference which is on the face of it, untenable resulting in miscarriage
        of justice, the adjudication even when made by an arbitral tribunal that
        enjoys considerable latitude and play at the joints in making awards
        will be open to challenge and may be cast away or modified depending
        upon whether the offending part is or is not severable from the rest."


14.    I have considered the challenge aforesaid to the arbitral award on the

anvil of the above latest adjudication also. No ground, of the Arbitral

Tribunal in the instant case having not adopted a judicial approach or having

acted in violation of the principles of natural justice has been urged. It is

also not the case that the Arbitral Tribunal has not acted bona fide or not

dealt with the subject in a fair, reasonable and objective manner or that the

decision of the Arbitral Tribunal was actuated by any extraneous

consideration. Non application of mind by the Arbitral Tribunal is also not

pleaded or argued. No case of perversity or irrationality has also been made


O.M.P. No.1640/2014                                                       Page 30 of 35
 out. The entire challenge is on the ground of the findings of the Arbitral

Tribunal being factually erroneous and which is not a ground even as per the

judgment (supra) of the Supreme Court. Of course, the Supreme Court in

para 40 of the judgment has held that if the Arbitral Tribunal, from the facts

proved before it fails, to draw an inference which ought to have been drawn

or draws the inference which on the face of it is untenable, the arbitral award

would be in conflict with public policy of India and the test of "fails to draw

inference which ought to have been drawn or draws an inference which is

untenable" is very wide but the said test is qualified with the words

"resulting in miscarriage of justice". I am unable to read the judgment of the

Supreme Court as opening the doors of challenge to an Arbitral Award by a

detailed examination of all the facts and material before the Arbitral

Tribunal and to determination of whether the inferences drawn and the

consequences reached by the Arbitral Tribunal therefrom are correct or not

and whether the Court agrees with the same or not. If the same were to be

permitted, it would do away with the difference between the Court

exercising appellate power and power of judicial review of Arbitral Award

under Section 34 of the Act and would be against the several other

judgments of the Supreme Court and which, in the judgment (supra) were

O.M.P. No.1640/2014                                                 Page 31 of 35
 neither considered nor differed from. The judgment (supra) of the Supreme

Court, cannot be read in isolation, forgetting all other judgments of the

Supreme Court and none of which have been overruled.


15.    The expression "miscarriage of justice", used by the Supreme Court in

the judgment (supra) as qualifying the test laid down in para 40 thereof of

the validity of the Arbitral Award, is an expression well recognized in law

and generally associated with grossly unfair outcome in a judicial

proceeding as when a defendant is convicted despite a lack of evidence on

an essential element of a crime (per Black‟s Law Dictionary, Eight Edition).

The Supreme Court in Union of India Vs. Ibrahim Uddin (2012) 8 SCC

148 cited with approval Bibhabati Devi Vs. Ramendra Narayan Roy AIR

1947 PC 19 holding that miscarriage of justice means such a departure from

the rules which permeate all judicial procedure as to make that which

happen not in the proper sense of the word „judicial procedure‟ at all.

16.    Thus, it is not every inference drawn or not drawn by the Arbitral

Tribunal from the material before it and which the Court finds to have been

wrongly drawn or not drawn, which could be held to be resulting in

miscarriage of justice. Such inference / failure to interfere by the Arbitral


O.M.P. No.1640/2014                                                 Page 32 of 35
 Tribunal, even if in the opinion of the Court wrong, would permit

interference under Section 34 of the Arbitration Act only if it results in a

grossly unfair outcome.


17.    There is another aspect of the matter. A detailed inquiry into the

correctness of the inference drawn / not drawn by the Arbitral Tribunal

would require the Court not only to go through and dissect the arbitral record

which is often voluminous in cases as the present but to also give an

opportunity to the parties / their counsels to address on the inferences drawn

/ not drawn by the Arbitral Tribunal and to only thereafter form an opinion.

The same would again make a proceeding under Section 34 of the

Arbitration Act and hearing thereof akin to an appeal from original decrees

of the Court and would be an antithesis to the very concept of judicial

review of arbitral award, even if the Court at the end of such a marathon

hearing were to conclude that there has been no miscarriage of justice. It is

thus for the contracting party challenging the Arbitral Tribunal to, in the

memorandum of challenge itself, make out a case of miscarriage of justice

within the parameters aforesaid. No such case has been made out in the

petition in the present case. Without any such case having been made out in


O.M.P. No.1640/2014                                                Page 33 of 35
 the memorandum of petition, this Court would not embark upon an exercise

of requisitioning the arbitral record and giving an opportunity to the parties /

their counsels to address on the correctness of the inference drawn / not

drawn by the Arbitral Tribunal and on the aspect of whether there has been a

miscarriage of justice.


18.    Mention may also be made of another recent dicta in Associate

Builders Vs. DDA MANU/SC/1076/2014 where on conspectus of plethora

of cases including Western GECO International Ltd. supra, the judgment of

the Single Judge of this High Court dismissing the petition under Section 34

of the Arbitration Act was restored and the judgment of the Division Bench

in appeal thereagainst interfering with the award was set aside holding that

the Division Bench exceeded its jurisdiction in interfering with the pure

finding of facts forgetting that the arbitrator is the sole Judge of the quantity

and quality of evidence before him and that the Division Bench has no

business to enter into the pure question of fact to set aside the award. It was

further held that the same cannot be done by any Court under jurisdiction

exercised under Section 34 of the Act. The Supreme Court further held that

the expression „justice‟ when it comes to setting aside an award under the


O.M.P. No.1640/2014                                                  Page 34 of 35
 public policy ground can only mean that the award shocks the conscience of

the Court and that it cannot possibly include what the Court thinks is unjust

on the facts of a case for which the Court then seeks to substitute its own

view for the arbitrator‟s view and does what it considers to be „justice‟. The

Supreme Court observed that the Division Bench had lost sight of the fact

that it is not a first Appellate Court and cannot interfere with errors of fact.

The Supreme Court held that if the arbitrators have decided the dispute with

a sound head and a good heart and after hearing both sides, the Courts

should not interfere with their award, even if the Court disagrees with the

reasons assigned by the arbitrator.


19.    It is not the case of the petitioners that the arbitrators in the present

case have not decided with a sound head and a good heart.


20.    I therefore do not find any case for entertaining the challenge to the

Arbitral Award by way of this petition and dismiss the same.


       No costs.



                                               RAJIV SAHAI ENDLAW, J.

JANUARY 16, 2015 „gsr‟ O.M.P. No.1640/2014 Page 35 of 35