State of Jharkhand - Section

Section 23 in The Jharkhand State Electricity Regulatory Commission (Guidelines for Establishment of Forum for Redressal of Grievances of the Consumers and Electricity Ombudsman) Regulations, 2011

23. Settlement of complaint by agreement.

(1)As soon as it may be practicable to do, but not later than one week from the date of receipt of representation, the Electricity Ombudsman shall serve a notice to the nodal officer of the Distribution licensee along with a copy of the complaint and endeavour to promote a settlement of the complaint by agreement between the complainant and the Distribution licensee named in the complaint through conciliation or mediation.
(2)For the purpose of facilitating settlement of the representation, the Electricity Ombudsman may follow such procedures, as he/she may consider appropriate. The process of mediation should be completed within 30 days from the date of issue of such notice.
(3)When a representation is reported in writing, about settlement through mutual agreement between the parties, the Electricity Ombudsman shall make a recommendation, in terms of the agreement. The copies of the case/recommendation shall be sent to the complainant and the Distribution licensee concerned not later than 7 days from the date of recording/receipt of the mutual agreement.
(4)If a complainant accepts the recommendation of the Electricity Ombudsman, he shall send a communication; in writing within 15 days from the date issue of the recommendation confirming his acceptance to Electricity Ombudsman and states clearly that the settlement reached is in full and final settlement of complaint.
(5)The Electricity Ombudsman shall send the acceptance letter received from the complainant to the Distribution licensee to comply with the terms of the recommendations immediately but not later than 21 days of the receipt of such recommendation and the Distribution licensee shall inform the Electricity Ombudsman of its compliance within 7 days of the implementation of such recommendation.