Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 19, Cited by 0]

Bombay High Court

M/S. Satra Plaza Premises Co-Op Soc. Ltd vs Navi Mumbai Municipal Corporation And ... on 4 May, 2023

Author: G. S. Kulkarni

Bench: G. S. Kulkarni

2023:BHC-AS:13678-DB




                                                                         1                 wp [email protected]


        Prajakta Vartak
                                         IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                  CIVIL APPELLATE JURISDICTION
                                           IN ITS EXTRAORDINARY CIVIL JURISDICTION
                                                              AND
                                           IN ITS JURISDICTION UNDER ART.226 OF THE
                                                     CONSTITUTION OF INDIA

                                                         WRIT PETITION NO. 1374 OF 2017

                           M/s.Satra Plaza Premises Co-op.Soc.Ltd., A Co-
                           operative Society Duly incorporated under the
                           provisions of Maharashtra Co-operative Societies
                           Act,1960, having its registered office at "Satra Plaza"
                           Plots Nos.19 & 20, Sector - 19-D, Vashi, Navi
                           Mumbai-400 703.                                         .. Petitioner
                                                            Vs.
                           1. Navi Mumbai Municipal Corporation, duly
                           constituted under Section 5 of Maharashtra Provincial
                           Municipal Corporation Act,1949, having their Office
                           at Plot No.1 Near Killegaothan, Palm Beach Junction,
                           Section - 15A, Belapur, Navi Mumbai.

                           2. Municipal Commissioner, Navi Mumbai Municipal
                           Corporation, having his Office at Plot No.1 Near
                           Killegaothan, Palm Beach Junction, Sector - 15A,
                           Belapur, Navi Mumbai.

                           3. M/s.Satra Properties (India)Ltd., a company duly
                           incorporated under the provisions of the Companies
                           Act,1956, having their registered office at Dev Plaza,
                           2nd Floor, Opp.Andheri Fire Brigade, S. V. Road,
                           Andheri (W), Mumbai-400058.

                           4. State of Maharashtra, Mantralaya, Mumbai -
                           400032.

                                                                   Page 1 of 44
                                                               -------------------------




                          ::: Uploaded on - 04/05/2023                                 ::: Downloaded on - 05/05/2023 15:02:27 :::
                                               2                 wp [email protected]


 5. City and Industrial Development Corporation of
 Maharashtra Ltd., A govt. Company duly
 incorporated under provisions of the Companies
 Act,1956 having its Administrative Office at CIDCO
 Bhavan, CBD-Belapur, Navi Mumbai-400614.           ...Respondents

                                           WITH
                               WRIT PETITION NO. 1184 OF 2017

 M/s.Satra Properties (India) Ltd.,
 Dev Plaza, 2nd floor, Opposite Andheri Fire Station,
 S. V. Road, Andheri (West), Mumbai-400058.                                .. Petitioner
                                  Vs.
 1. Navi Mumbai Municipal Corporation, through
 Hon'ble Municipal Commissioner, Head Qurter, Plot
 No.1 Near Kille Gaothan, Palmbeach Junction,
 Section 15A, C.B.D.road, Belapur, Navi Mumbai,
 Pin:400614.

 2. City and Industrial Development Corporation of
 Maharashtra Ltd., Nirmal, 2nd Floor, Nariman Point,
 Mumbai-400021.                                      ...Respondents

                                        _____________

 Mr. Atul Rajadhyaksha, Senior Advocate with Mr. Nishant Tripathi i/b.
 M/s. M. Tripathi & Co. for Petitioner in WP No.1374/17.
 Mr. Deep Dighe i/b. Mr. Amit Tungare for Petitioner in WP No. 1184/17.
 Mr. Tejesh Dande with Mr. Bharat Gadhavi for NMMC, Respondent
 Nos. 1 & 2 in WP No. 1374/17 and for Respondent No.1 in WP No.
 1184/17.
 Mr. Ashutosh Kulkarni with Mr. Sarthak Diwan for CIDCO, Respondent
 No.5 in WP No. 1374/17 and for Respondent No.2 in WP No. 1184/17.
 Mr. A.A. Alaspurkar, AGP for State, Respondent No.4 in WP No.
 1374/17.

                                        Page 2 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                            3                 wp [email protected]


                                 _____________
                                    CORAM :                      G. S. KULKARNI &
                                                                 KAMAL KHATA, JJ.
                               RESERVED ON:                      APRIL 24, 2023
                               PRONOUNCED ON:                    MAY 4, 2023

 P.C.:

 1.      The petitioner is a co-operative society registered under the

 provisions of Maharashtra Co-operative Societies Act, 1960 and pursuant

 to the mandate of the first proviso to Section 10 of Maharashtra

 Ownership of Flats (Regulation of the Promotion, Construction, Sale,

 Management & Transfer) Act, 1963 by the purchasers of offices/shops in

 the building constructed by respondent no.3 - M/s. Satra Properties

 (India) Ltd., the developers. The land on which the petitioner's premises

 are constructed is described to be Plot Nos. 19 and 20, Sector - 19-D,

 Vashi, Navi Mumbai - 400 703.


 2.      The petitioner impugns an order dated 27 December, 2016 passed

 by the Municipal Commissioner (Respondent No. 2) of respondent No.1

 - Navi Mumbai Municipal Corporation (for short "municipal

 corporation") whereby in exercise of powers vested with the Planning

 Authority, the municipal corporation has revoked/cancelled not only the


                                     Page 3 of 44
                                 -------------------------




::: Uploaded on - 04/05/2023                             ::: Downloaded on - 05/05/2023 15:02:27 :::
                                            4                 wp [email protected]


 Occupancy Certificate dated 09 February, 2012 issued to the premises of

 the petitioner, but also the revised Commencement Certificate.


 3.      The question which arises for consideration in the present

 proceeding is whether in the facts of the present case the Municipal

 Commissioner at all had any power to revoke the Occupation Certificate

 granted to the petitioner's premises.



 4.      Shortly stated the facts are:-

         Respondent No. 5-City And Industrial Development Corporation

 of Maharashtra Ltd. (for short, "CIDCO") had constructed two buildings

 for offices for the brokers of the Agricultural Produce Market Committee

 (for short "APMC") on the land in question prior to the year 2000.

 CIDCO allotted both, the buildings along with Plot No.19 and adjacent

 vacant Plot No.20, namely the lands in question to the municipal

 corporation for its use as its Head Office.



 5.      The municipal corporation subsequently discovered that the two

 buildings constructed on Plot No. 19 were not suitable for its office use.


                                     Page 4 of 44
                                 -------------------------




::: Uploaded on - 04/05/2023                             ::: Downloaded on - 05/05/2023 15:02:27 :::
                                             5                 wp [email protected]


 The municipal corporation invited tenders in the year 2005 for the sale of

 two office buildings along with the composite plot. In pursuance of the

 tender/scheme floated by the municipal corporation, various aspirants

 submitted their offers. One M/s. Om Housing Company Pvt. Ltd. (for

 short, "Om Housing") turned out to be the highest tenderer.

 Consequently, the municipal corporation issued to Om Housing a letter

 of acceptance dated 02 July, 2005. Since Om Housing needed finance

 from banks/financial institutions, by its letter dated 10 August, 2015, Om

 Housing requested the municipal corporation to execute "Agreement to

 Lease" in its favour. The municipal corporation consequently executed

 Agreement to Lease dated 18 August, 2005 agreeing to lease these

 composite plots in favour of the Om Housing, on the terms and

 conditions as set out therein.



 6.      The municipal corporation thereafter, by its letter dated 02

 February, 2006 applied to CIDCO for permission to transfer and assign

 its leasehold rights of the composite plot in favour of Om Housing.

 CIDCO by its letter dated 24 February, 2006, requested the municipal



                                      Page 5 of 44
                                  -------------------------




::: Uploaded on - 04/05/2023                              ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          6                 wp [email protected]


 corporation to pay additional lease premium vis-a-vis for the grant of

 additional FSI and amalgamation of the two plots.                       The municipal

 corporation made the payment of Rs.14,78,10,000/- towards the

 additional lease premium for the grant of additional FSI and

 amalgamation of two plots to CIDCO. Upon the payment of such

 additional lease premium, CIDCO by its letters dated 27 October, 2006

 granted permission for the utilisation of the additional FSI as also for the

 amalgamation of the two plots on the terms and conditions as set out

 therein. CIDCO thereafter by its two letters both dated 21 December,

 2006 allowed the municipal corporation to transfer and assign its

 leasehold rights vis-a-vis Plot No.19 and the two buildings standing

 thereon as well as Plot No. 20 in favour of the Om Housing.



 7.      Pursuant to the permission from CIDCO dated 21 December,

 2006, the municipal corporation executed a Deed of Assignment dated 21

 December, 2006 in favour of the Om Housing.



 8.      Thereafter in pursuance of the approval of the CIDCO dated 21



                                   Page 6 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          7                 wp [email protected]


 December, 2006 to transfer and assign its leasehold rights in respect of

 both the said plots, a tripartite agreement dated 28 December, 2006 was

 executed between the CIDCO, the municipal corporation and Om

 Housing. Accordingly, under such agreement the said plots stood vested

 in Om Housing.



 9.      Thereafter, Om Housing submitted a scheme of amalgamation with

 respondent no.3-M/s. Satra Properties (India) Ltd.                    (for short "Satra

 Properties") then known as "Express Leasing Ltd." under Sections 391

 and 394 of the Companies Act, 1956, subject matter of Company Petition

 No. 45 of 2007 filed in this Court. Such petition was allowed by this

 Court by an order dated 16 April, 2007. Om Housing thus stood

 amalgamated with Satra Properties. Consequently all the assets and

 liabilities of Om Housing stood vested with Satra Properties. Further

 CIDCO by its letter dated 27 March, 2008 acknowledged the

 amalgamation of Om Housing with Satra Properties.



 10.     Consequent to the amalgamation, Satra Properties was seized,



                                   Page 7 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          8                 wp [email protected]


 possessed and was sufficiently entitled to Plot No.19 along with two

 existing buildings standing thereon and Plot No.20. CIDCO by its letter

 dated 24 February, 2006, granted consent/ permission for the

 amalgamation of Plot No.19 with Plot No.20 and for the utilization of

 additional FSI pursuant to the payment of costs and charges.                           Satra

 Properties accordingly became entitled to develop the composite plot and

 carry out building operations thereon with development permission to be

 granted by the municipal corporation.



 11.     Upon acquiring the right, title and interest vis-a-vis the composite

 plot, with the permission of the municipal corporation, Satra Properties

 demolished both the office buildings standing on Plot No.19 and applied

 for development permission on the composite plot as per the provisions

 of Section 44 of the Maharashtra Regional and Town Planning Act (for

 short, "MRTP Act") read with Regulation 4 of General Development

 Control Regulations for Navi Mumbai Municipal Corporation, 1994 (for

 short, "the GDCR").




                                   Page 8 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          9                 wp [email protected]


 12.     The municipal corporation by its letter dated 07 March, 2007

 granted development permission to Satra Properties and issued

 Commencement Certificate as also approved plans for the construction of

 a commercial building consisting of two levels of basement for parking

 and storage and ground plus thirteen upper floors. Satra Properties

 accordingly obtained permissions as also had got the revised plan

 sanctioned by the municipal corporation. It also sold various shops and

 offices in the building being constructed by it on the said plots and

 executed Agreements for Sale in favour of several persons who agreed to

 acquire shops/offices in the said project.



 13.     Satra Properties having completed the construction on the

 composite plot, made an application to the municipal corporation for

 issuance of an Occupancy Certificate as per the requirements of the

 regulations. After following the procedure, the municipal corporation

 granted an Occupancy Certificate dated 09 February, 2012 not in

 accordance with Form No.19 as Form No.19 does not contemplate any

 condition attached to it. The Occupancy Certificate dated 09 February,



                                   Page 9 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                                      10                 wp [email protected]


 2012 which reads thus:-

                        "NAVI MUMBAI MUNICIPAL CORPORATION
                   1st Floor, Belapur Bhavan, C.B.D., Navi Mumbai - 400 614.
                                  Tele. Nos. 27577070, 27575700
                                         Fax No. 27573785

          ---------------------------------------------------------------------------------

                             Outward No. TPD/O.C./M. No. B-6704 /714/2012.
                             Date: 09.02.2012.

                                    OCCUPANCY CERTIFICATE

          Read:            1) Revised Certificate for Commencement of Construction
                           bearing       No.       N.M.M.C./T.P.D./B.P./M.       No. A-
                           8151/3450/2009, dated 04.09.2009, issued by Navi
                           Mumbai Municipal Corporation.
                           2) Circular dated 31.07.2008 about charging of Premium
                            issued by Navi Mumbai Municipal Corporation.
                           3) Certificate regarding Completion of Construction, dated
                           30.03.2011 produced by the Architect- M/s. Hiten Sethi.
                              --------------------------------------------------

                  The owner by name M/s. Satra Properties (India) Limited of the
          land bearing Plots of land No. 19 and 20, situated in Sector No. 19-D,
          Vashi, Navi Mumbai in Navi Mumbai has completed the construction on
          the said plot of land on the date 23.02.2011. The Certificate in respect
          thereof has been submitted by the concerned Architect M/s. Hiten Sethi. As
          the terms and conditions, as mentioned in the Revised Certificate for
          Commencement of Construction dated 04.09.2009 issued by the Navi
          Mumbai Municipal Corporation, have been complied with and also the
          action about recovery of various fees pursuant to the Circular dated
          31.07.2008 about charging Premium, issued by the Municipal Corporation
          has been carried out, permission is granted to make use of the said plot of
          land as follows:
          1) Area of the plot of land             :       19238.51 Sq. Mtrs.

          2) Permissible Floor Space Index                :         1.50

          3) Built-up Area under Commercial use :                   28751.840 Sq. Mtrs.

             (Shops - 59, Offices - 329, Banquet
             Halls - 02 under commercial use)
          4) Built-up Area under Balcony         :                  4799.44 Sq. Mtrs.


                                               Page 10 of 44
                                            -------------------------




::: Uploaded on - 04/05/2023                                        ::: Downloaded on - 05/05/2023 15:02:27 :::
                                                      11                 wp [email protected]



                                                                (Sd/-)
                                                        [Sanjay S. Banait],
                                                Assistant Director, Town Planning,
                                                Navi Mumbai Municipal Corporation."



 14.      On the same day, a covering letter dated 09 February, 2012 was

 addressed to Satra Properties inter-alia setting out conditions in respect of

 the Occupancy Certificate and, more particularly condition no.4 stating

 that it would be binding to produce 'No Objection Certificate' issued by

 the CIDCO within one year, otherwise occupancy would be cancelled.

 The said letter is addressed by the Assistant Director of Town Planning,

 Navi Mumbai Municipal Corporation to Satra Properties which reads

 thus:-

                          "NAVI MUMBAI MUNICIPAL CORPORATION
                      1st Floor, Belapur Bhavan, C.B.D., Navi Mumbai 400614
                            Tel.No. 27577070, 27575700, Fax 27573785
          ------------------------------------------------------------------------------------------
                             Outward No. T.P.D./O.C./M.No. B-6704/714/2012
                             Date : 09.02.2012
          To,
          M/s. Satra Properties (India) Ltd.
          Plot No. 19 and 20, Sector 19 D,
          Vashi, Navi Mumbai.

                   File No. N.M.M.C./S.M.No.........Matter No. B-6704

                   Subject :- Regarding issuing Occupancy Certificate in respect of
                              the property bearing Plot No. 19 and 20, Sector 19 D,
                              Vashi, Navi Mumbai.



                                               Page 11 of 44
                                            -------------------------




::: Uploaded on - 04/05/2023                                        ::: Downloaded on - 05/05/2023 15:02:27 :::
                                                 12                 wp [email protected]


                  Reference :- Applications dated 30.03.2011 and 11.09.2011 of your
                               Architect.
          Respected Sir,

                  In pursuance of the applications referred to hereinabove, the
          Occupancy Certificate for commercial use of the property bearing Plot No.
          19 and 20, Sector 19 D, Vashi, Navi Mumbai, is enclosed herewith.
                  As internal changes have been made without permission, the
          amount of Security Deposit has been forfeited, as per the condition
          mentioned in the Construction Commencement Certificate, which may
          please be noted.
                  As per the Government Circular No. BCA 2007/M.No.
          788/Labour 7-A, dated 26th October, 2009 issued by the Industry, Energy
          and Labour Department, Labour Cess has been paid in this matter and the
          Labour Welfare Cess Unique Code No. 20110200403 B-6704 01 has been
          given thereto.

          Conditions:- 1) Appropriate precaution should be taken from time to
          time to permanently maintain the markings showing the entire Parking
          Arrangement within the boundary of the said building, as shown in the
          sanctioned plan.
          2)       Precaution should be taken categorically to see that common
          passages, Lobby, AHU in the said building and the area, free of Floor Space
          Index, calculated by charging premium as well as other items (area) taken
          free of Floor Space Index, is not misused or is not used unauthorizedly.
          3)       As the Palm Beach Road is passing adjacent to the said Plot, the
          access for the vehicles to the said plot should not be given from Palm Beach
          Road. Similarly, precaution should be taken to see that no hindrance is
          caused to the traffic on Palm Beach road.
          4)       It shall be binding to submit No-Objection Certificate issued by the
          Office of CIDCO, within one year or else, this Occupancy Certificate shall
          be cancelled.

          Copy for information -                                  Yours faithfully,
          1) Hiten Sethi, Architect,
          'Meher', ground floor, Plot No.260, Sector 28,             Sd/-
          Vashi, Navi Mumbai.                                     (Sanjay S. Banait)
          2) Deputy Commissioner (Cess),             Assistant Director, Town Planning,
          Koparkhairane.
          3) Deputy Commissioner, Zone 1/2, N.M.M.C..
          4) Assessor and Collector, N.M.M.C., Turbhe.
          5) Chief Architect and Planner, CIDCO Ltd..
          6) Ward Officer, N.M.M.C., Turbhe."
                                                                     (emphasis supplied)



                                          Page 12 of 44
                                       -------------------------




::: Uploaded on - 04/05/2023                                   ::: Downloaded on - 05/05/2023 15:02:27 :::
                                             13                 wp [email protected]


 On 8 December 2012 Satra Properties sought a 'No Dues Certificate'

 from CIDCO.             In such letter addressed by Satra Properties, it was

 recorded that CIDCO had not replied to the earlier letters of Satra

 Properties dated 22 November 2010, 30 December 2010 and 9 March

 2011, requesting for a 'No Due Certificate'. On 3 January 2013, for the

 first time, CIDCO responded to the said letters addressed by Satra

 Properties inter alia stating that Satra Properties would have to bear for

 some time for a "No Dues Certificate", as CIDCO was to interalia obtain

 compliance from the municipal corporation in regard to the lease of the

 said plots, incidental to the grant of change of usage of the land and

 enhanced FSI.



 15.     The petitioner has contended that the Municipal Corporation was

 insisting on "No Dues Certificate" to be obtained by Satra Properties and

 failing which Satra Properties was threatened to invoke the occupation

 certificate. This necessitated Satra Properties to address letters to CIDCO

 to approach the Municipal Corporation and settle the issues.



 16.     On 15 January 2014 Municipal Corporation issued a show cause

                                      Page 13 of 44
                                   -------------------------




::: Uploaded on - 04/05/2023                               ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         14                 wp [email protected]


 notice to Satra Properties as to why the Occupation Certificate granted by

 the municipal corporation should not be revoked and called upon Satra

 Properties for a hearing on 22 January 2014. The petitioner also

 addressed a letter on 22 January 2014 to the Municipal Commissioner

 requesting the NMMC that the petitioner be also heard in the matter, as

 the issue pertains to the cancellation of the occupancy certificate of the

 premises of the petitioner society.



 17.     A hearing on the show - cause notice issued by the Municipal

 Commissioner was scheduled on 22 January 2014, however no notice was

 issued to the petitioner. On 17 December 2016 which was almost after 2

 years of the earlier show - cause notice, a fresh show - cause notice came to

 be issued to Satra Properties, however, no notice was issued to the

 petitioner, on 20 December 2016 to participate at the hearing. Petitioner

 addressed an E-mail to the Municipal Corporation requesting the

 petitioner's presence at the hearing, to take place on a future date. A copy

 of such letter was also forwarded to the Additional Commissioner of the

 Municipal Corporation.



                                  Page 14 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                              15                 wp [email protected]


 18.     On 23 December 2016 a hearing on the show cause notice took

 place before the Municipal Commissioner, however, no notice of such

 hearing was issued to the petitioner although an opportunity of the same

 was sought by the petitioner by its letters as noted above. Consequent to

 such hearing on 27 December 2016, the Municipal Commissioner passed

 the impugned order cancelling the Occupancy Certificate as also the

 revised      Commencement          Certificate.         The      said     order      was      also

 communicated to the members of the petitioner/society. The impugned

 order cancelling the Occupation Certificate is annexed at Exhibit-N (Page

 270 to the Writ Petition). The operative part of the impugned order is

 required to be noted which reads thus:-

                   (Official Translation of the Original Marathi Version)

          "                     ORDER

          A)      As the Condition No.4 mentioned in the Occupancy
          Certificate issued to the building standing on the Plot under subject,
          by the Navi Mumbai Municipal Corporation, under letter dated
          09.02.2012, is not complied with, the Occupancy Certificate
          togetherwith the revised Building Permission, is hereby cancelled.

          B)     As the Building Permission granted in the matter under
          subject is cancelled, the said structure becomes illegal/unauthorized
          one and therefore, the Deputy Commissioner and Controller
          (Unauthorized Works) as well as the Ward Officer Concerned shall
          take further legal action.



                                       Page 15 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                              16                 wp [email protected]


          C)     In the matter under subject, as the Developer and also the
          Architect concerned are responsible, the copy of this Order is sent to
          the Council of Architects, New Delhi for taking action against him
          accordingly.

          Copy of this order is served upon the Developer M/s. Satra Properties
          (India) Ltd. and the Architect Shri Hiten Sethi."



 19.     In the above circumstances, the present petition has been filed

 praying for the following reliefs:-

          "a)     That this Hon'ble Court may be pleased to declare:

          (i)    That condition no.4 appended to the O. C. dated the 9 th
          February, 2012 requiring the 3rd Respondents to furnish the NOC of
          the 5th Respondents was/is ultra-vires the provisions of the MRTP
          Act, MPMC Act and the GDRC (particularly Reg. 9.8 of the GDRC)
          and hence liable to be quashed and set aside; and

          (ii)   That the 1st / 2nd Respondents have no jurisdiction in law to
          cancel/revoke the O.C. dated 9th February, 2012 (Exh. "H"); and

          (iii) That the 1st / 2nd Respondents have no jurisdiction to issue
          notices at Exhs - "O" to "O-104" and the identical notices to the
          other members of the Petitioners under S. 53(1) of the MRTP Act as
          they have done; and

          (iv) That the O.C. dated 9th February, 2012 (Exh - "H") is
          irrevocable; and

          (v)     That the order dated 27th December, 2016 (Exh - "N") is bad
          in law, untenable and liable to be quashed and set aside; and

          (vi) That the notices at Exhs - "O" to "O-104" and other identical
          notices to the other members of the Petitioners issued without having
          jurisdiction to do so are also bad in law and liable to be quashed and
          set aside.

          (b)     That this Hon'ble Court may be pleased to issue writ of

                                       Page 16 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                               17                 wp [email protected]


          certiorari or a writ in the nature of certiorari or any other writ, order
          or direction of this Hon'ble Court calling for the records of the
          proceedings conducted by the 1st / 2nd Respondents u/s. 51(1) of the
          MRTP Act in which the impugned order dated 27 th December, 2016
          was passed and after scrutinising, quash and set aside the same.

          (c)    That this Hon'ble Court may be pleased to issue writ of
          mandamus or writ in the nature of mandamus or any other writ,
          order and direction directing the 1 st / 2nd Respondents to withdraw
          the notices at Exhs - "O" to "O-104" and all other identical notices
          issued to the other members of the Petitioners or in the alternative
          this Hon'ble Court may be pleased to quash/set aside the same.

          (d)    That pending the hearing and final disposal of this Writ
          Petition, this Hon'ble Court may be pleased to restrain the 1 st / 2nd
          Respondents, their officers, servants and agents from:

                  (i)    implementing, operating and executing the impugned
          order dated 27th December, 2016 (Exh - "N") and/or in any manner
          interfering with and/or disturbing the peaceful possession and use
          and enjoyment of the building known as 'Satra Plaza' standing on
          Plot No. 19/20, Sector - 19-D, Vashi, Navi Mumbai by the
          Petitioners and/or their members.

                 (ii)   implementing, operating and executing the notices at
          Exhs - "O" to "O-104" and all other identical notices issued to the
          other members of the Petitioners and/or in any manner interfering
          with and/or disturbing the peaceful possession and use and
          enjoyment of the building known as 'Satra Plaza' and the tenements
          therein standing on Plot No. 19/20, Sector - 19-D, Vashi, Navi
          Mumbai by the Petitioners and/or their members.

          (e)    That this Hon'ble Court may be pleased to grant interim/ad-
          interim reliefs in terms of Prayer Clauses (d-i) and (d-ii) supra."


 20.     On behalf of the municipal corporation, a reply affidavit of Mr.

 Hemant Ramdas Thakur, Assistant Director of Town Planning, Navi

 Mumbai Municipal Corporation, has been filed stating that a detailed


                                        Page 17 of 44
                                     -------------------------




::: Uploaded on - 04/05/2023                                 ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         18                 wp [email protected]


 reply affidavit filed in the companion petition by Satra Properties be

 considered as an affidavit in the present proceedings. In the municipal

 corporation's reply affidavit filed in the companion petition, it is

 contended that the municipal corporation has acted in pursuance of the

 Government order dated 16 December, 1994 issued under Section 154 of

 the MRTP Act conferring powers on the municipal corporation as

 planning authority in respect of the developed nodes. It is stated that the

 State Government in the said order incorporated that it was mandatory

 for the municipal corporation to insist upon Satra Properties to obtain

 'No Objection Certificate' (in short "NOC") from CIDCO before issuing

 a development permission; and that the municipal corporation should

 insist on obtaining NOC from CIDCO at the time of issuing an

 Occupancy Certificate. It is hence stated that the provision for obtaining

 NOC both at the time of grant of development permission, as well as, at

 the time of issuance of an occupancy certificate was mandatory by virtue

 of the said order of the State Government, as CIDCO continued to own

 most of the lands in the Navi Mumbai Project Area, and was entitled to

 recover different kinds of charges from the allottees of lands. It is for such



                                  Page 18 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                             19                 wp [email protected]


 reason the grant of development permission under Section 44 of the

 MRTP Act was made subject to CIDCO issuing NOC, both at the time of

 issuance of the Commencement Certificate as well as for grant of an

 Occupancy Certificate. This is also stated to be the requirement under

 Regulation 6.3.17 of the DCR of the municipal corporation, necessary for

 utilisation of additional FSI, change of user, mixed user, amalgamation,

 redevelopment etc. The affidavit also refers to some file notings which

 inter-alia included Satra Properties, undertaking that it would be fully

 responsible for any financial and legal aspects if they arise in the future,

 and that the municipal corporation would not be held responsible

 whatsoever. Considering such an undertaking, it was decided to issue

 Occupancy Certificate on the condition to submit CIDCO's NOC within

 three months. In this regard, the relevant extract of the reply affidavit is

 required to be noted which reads thus:-

          "...... The said file noting was approved at various levels such as
          Draughtsman, Dy. Accountant, Dy. Engineer, Town Planner and
          Asst. Director of Town Planning. After such approval, the concerned
          file was placed for approval of the Municipal Commissioner who
          remarked that Occupancy Certificate should be granted as the plot
          was auctioned by NMMC to the Petitioners as a peculiar case.
          Accordingly, the then Asst. Director of Town Planning issued the
          occupancy certificate dated 09/02/2012 in respect of both Plot Nos.
          19 and 20 by putting condition therein that NOC of CIDCO must
          be submitted within 1 year, failing which the Occupancy Certificate

                                      Page 19 of 44
                                   -------------------------




::: Uploaded on - 04/05/2023                               ::: Downloaded on - 05/05/2023 15:02:27 :::
                                              20                 wp [email protected]


          shall stand cancelled. Thus as against the period of 3 months
          proposed in the file nothing approved till the level of Commissioner,
          it is not clear as to why period of 1 year was stipulated in the
          Occupancy Certificate dated 09/02/2012. Furthermore there is no
          provision for processing proposal for Occupancy Certificate merely
          on the basis of an undertaking of the developer. Similarly there is no
          provision for issuance of conditional Occupancy Certificate."



 21.     The said affidavit further states that the objective behind making a

 provision for mandatorily obtaining NOC from the CIDCO for grant of

 Occupancy Certificate, is to ensure that CIDCO recovers various charges

 from the allottees. It is stated that in the present case, on account of non-

 completion of construction by the petitioner within the time limit, Satra

 Properties became liable to pay charges to CIDCO for condonation of

 delay, and Satra Properties wanted to avoid the liability to pay such

 charges to the CIDCO. It is further stated that Satra Properties ought to

 have complied with its undertaking to make payment of the CIDCO

 charges. The affidavit also refers to a correspondence in the peculiar facts

 of the case, in as much as, the plots in question placed at the disposal of

 the municipal corporation. In these circumstances, municipal corporation

 addressed a letter dated 04 November, 2016 to the Chairman and

 Managing Director of the CIDCO requesting for the decision on the no



                                       Page 20 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         21                 wp [email protected]


 dues certificate. In such letter, it was pointed out by the Municipal

 Commissioner that CIDCO had sought time vide letter dated 03 January,

 2013 for issuance of no dues certificate, but no further decision from the

 CIDCO was received thereof.           It is stated that the Manager (Town

 Services), CIDCO responded to the said letter of the Municipal

 Commissioner by his letter dated 25 November, 2016 stating that the

 matter was placed before the Board of the CIDCO on 28 August, 2013

 and the Board sought clarification of various issues pertaining to the

 legality of sale of plot to NMMC, grant of permission to transfer, change

 of user etc. and it is for such reason, it was communicated that 'No Dues

 Certificate' cannot be granted to Satra Properties in respect of Plot No. 19

 and 20. It is stated that on such backdrop, the Assistant Director of Town

 Planning had issued a show cause notice dated 17 December, 2016 to

 Satra Properties and to its Architect with a copy thereof to CIDCO and

 invited them for the hearing scheduled on 23 December, 2016. Further

 that during such hearing, Satra Properties had requested for further

 extension of time for submission of CIDCO's NOC. It is stated that after

 hearing the parties, the Municipal Commissioner passed the impugned



                                  Page 21 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                              22                 wp [email protected]


 order dated 27 December, 2016 revoking the revised development

 permission as well as Occupancy Certificate.                        It is stated that the

 Municipal Commissioner was accordingly entitled to revoke the

 permission as per the provisions of Section 258 of the Maharashtra

 Municipal Corporations Act as well as DCPR Regulation 8.6.                                  It is

 accordingly prayed that the petition be dismissed.



 22.     This petition was first heard on 02 February, 2017 when a co-

 ordinate bench of this Court while issuing notice to the respondents had

 directed that no coercive steps be taken against the members of the

 petitioner in pursuance of the impugned order.                         The said order has

 continued to operate till date. It may also be stated that a co-ordinate

 bench of this Court on 05 September, 2022, had passed the following

 order:-

          "1.    Heard the learned Counsel for CIDCO. Learned Counsel for
          CIDCO tendered Minutes of Meeting dated 6.4.2021 and submitted
          that pursuant to order dated 30.3.2021, passed by this Court, a
          meeting was held on 6.4.2021. He further submitted that, in the said
          meeting, the Navi Mumbai Municipal Corporation and CIDCO
          concluded that in view of the Completion Certificate of the Architect,
          Occupancy Certificate was issued by the Navi Mumbai Municipal
          Corporation on 9.2.2012 and the present status that the occupants
          are using the constructed premises, that all these facts will be
          brought to the notice of the Board and the issue of validity of the

                                       Page 22 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                               23                 wp [email protected]


          Occupancy Certificate issued by Navi Mumbai Municipal
          Corporation on 9.2.2012, will be submitted for suitable consideration
          of the Board. The decision of the Board will be communicated to the
          Hon'ble High Court. Learned Counsel for CIDCO further submitted
          that the next meeting of the Board is likely to be held shortly.

          2.     Learned Counsel seeks time to inform this Court about the
          next date of the meeting, on which appropriate decision will be taken
          on the issue of validity of the Occupancy Certificate issued by Navi
          Mumbai Municipal Corporation on 9.2.2012.

          3.    Place the matter under the caption                      'directions' on
          supplementary board on 14.9.2022.

          4.      It is made clear that no further adjournment will be granted."



 23.     Lastly, this Court on 21April, 2023, noting the peculiar facts of the

 case, passed the following order calling upon the NMMC to take an

 appropriate decision:-

          "1.    We have heard Mr. Rajadhyaksha, learned Senior Counsel for
          the Petitioner and Mr. Dande, learned counsel for the NMMC and
          Mr. Kulkarni, learned Counsel for CIDCO for some time.

          2.      We have discussed the issues as falling for consideration of the
          Court. Mr. Dande, Learned counsel for the NMMC considering the
          complexion of case fairly states that he would take instructions from
          his clients as to whether the issues could be resolved. The controversy
          in the present proceedings is quite peculiar. In our opinion, this is a
          fit case where an appropriate decision to reconsider the impugned
          order passed by the Municipal Commissioner of NMMC needs to be
          taken. Prima facie we are of the opinion that serious prejudice has
          been caused to the petitioner by the impugned order which is of a
          nature that by a stroke of the pen the occupation certificate as well as
          C.C. have been cancelled, seriously affecting legal and constitutional
          rights of the Petitioners, who are the occupants of the premises. It was
          condition relevant to the developer in regard to any recovery at the
          hands of CIDCO, which could not affect the occupants of the

                                        Page 23 of 44
                                     -------------------------




::: Uploaded on - 04/05/2023                                 ::: Downloaded on - 05/05/2023 15:02:27 :::
                                                24                 wp [email protected]


          completed building, in respect of which occupation certificate as also
          completion certificate was granted. Such order passed by the
          Municipal Corporation had a direct bearing on the rights of the
          occupants guaranteed under Article 300 (A) of the Constitution,
          apart from the rights which an occupancy certificate would confer
          under the provisions of the MRTP Act. We are also disturbed by the
          fact that the impugned order has been passed in breach of the basic
          requirement of law not being followed, namely that the Petitioners
          not being heard in compliance of the principles of natural justice,
          when the Municipal Commissioner who has passed the impugned
          order was aware that the building was occupied by third parties and
          any such order passed by him would adversely affect the third parties
          like the petitioners. This is the complexion of the proceedings.

          3.      We leave it to the Municipal Commissioner to take
          appropriate decision and inform the said decision to the court failing
          which we would be constrained to adjudicate the petition on merits
          after hearing all the parties.

          4.     Accordingly Stand over to 24th April, 2023 at 3 p.m. part
          heard.

          5.      If at all appropriate decision is taken, we keep open all
          contentions of the CIDCO to take appropriate action in accordance
          with law in regard to recovery of its dues in respect of plot of land in
          question. We are also informed that there are number of other similar
          plots in which this issue is being discussed between CIDCO and the
          NMMC, by the committee as appointed by the State Government by
          Government Resolution dated 27th October, 2022 and the extension
          to which, is granted by the subsequent Government Resolution dated
          8th February, 2023, a copy of which is placed on record.

          6.      Parties to act on the authenticated copy of this order."



                  Submissions on behalf of the Petitioner

 24.     Mr. Rajadhyaksha, learned senior counsel for the petitioner, has

 made the following submissions: -


                                         Page 24 of 44
                                      -------------------------




::: Uploaded on - 04/05/2023                                  ::: Downloaded on - 05/05/2023 15:02:27 :::
                                            25                 wp [email protected]


         (i)      The impugned order cancelling the Occupancy Certificate

         and the revised Commencement Certificate is patently illegal and a

         nullity as it is passed without an opportunity of hearing being

         granted to the petitioner in adherence to the principles of natural

         justice.



         (ii)     It is stated that the impugned order is clearly an order which

         has civil consequences as it has adversely affected the rights of the

         third parties who are purchasers of the premises and are members

         of the petitioner-society. It is submitted that there is a serious

         prejudice which is caused to the members of the petitioner by the

         impugned order as it could never be contemplated that in respect

         of a legally constructed building, in which premises are purchased

         by such third party purchasers, being revoked of its Occupancy

         Certificate, creating a situation that it would not be possible for the

         members of the petitioner to deal with their premises.                            It is

         submitted that this is directly in violation of the rights of the

         members of the petitioner guaranteed under Article 19(1)(g) of the



                                     Page 25 of 44
                                  -------------------------




::: Uploaded on - 04/05/2023                              ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          26                 wp [email protected]


         Constitution of India affecting their business and the right to

         property guaranteed under Article 300A of the Constitution of

         India apart from being patently arbitrary, unreasonable and in

         violation of Article 13 of the Constitution.



         (iii)    It is submitted that such cancellation of Occupancy

         Certificate for the reasons as set out in the impugned orders falls

         foul of the provisions of Section 51 of the MRTP Act. In such

         context, it is submitted that Section 51 provides for inbuilt

         safeguards. In the present case, there was no reason whatsoever to

         invoke a power conferred under Section 51 of the MRTP Act, in as

         much as power under Section 51 of the MRTP Act can be exercised

         only when the planning authority is of the opinion that the

         permission may be revoked or modified having regard to the

         development plan. It is submitted that there is no such reason

         whatsoever which would justify invocation of Section 51 of the

         MRTP Act.




                                   Page 26 of 44
                                -------------------------




::: Uploaded on - 04/05/2023                            ::: Downloaded on - 05/05/2023 15:02:27 :::
                                             27                 wp [email protected]


         (iv)     It is submitted that even Section 51 is subject to the

         observance of the principles of natural justice, which is a condition

         precedent which has been breached as no hearing was granted to

         the petitioner before passing the impugned order.

         (v)      It is submitted that it is well settled that power under Section

         51 of the MRTP Act can be used only for the purposes set out in

         the provision and not for any extraneous purposes and by applying

         the principles of law that the power is required to be exercised only

         in the manner as prescribed by the statute or not at all, the

         impugned order deserves to be set aside.



         (vi)     It is next submitted that Occupancy Certificate can never be

         conditional as it has serious consequences, as also such can also

         never be the interpretation of the development control regulations

         which are sought to be relied on behalf of the CIDCO. In any

         event, the CIDCO under New Bombay Disposal Of Land

         Regulations, 1975 can recover lease premium or any other charges

         from Satra Properties as provided under Regulation 3.                              Even

         otherwise it has a contractual right to recover the same from Satra

                                      Page 27 of 44
                                   -------------------------




::: Uploaded on - 04/05/2023                               ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         28                 wp [email protected]


         Properties, which is also clear from the affidavit filed by the

         CIDCO referring to the clauses in the Deed of Assignment. A

         development permission being conditionally issued, would not be a

         correct position in law, even on the cumulative reading of the said

         regulations. In support of such contention, reliance is placed on

         the decisions of (I) Digambar Sakharam Tambolkar and another v.

         Pune Municipal Corporation and others1, (ii) Shree Ambica

         Developers v. State of Maharashtra and others 2, (iii) Mahavir

         Enterprises and others v. State of Maharashtra and others 3, (iv)

         Smt. Subhadrabai D. Gaykar v. Asst. Director of Town Planning

         Kalyan Municipal Corporation and Ors.4, (v) Hansa D. Moodaliar

         v. Pune Municipal Corporation and Ors.5, (vi) Brajrendra Singh

         Yambem v. UOI and anr.6, (vii) Kedar Nath Yadav v. State of W.B. 7

         and (viii) Tahsildar, Taluk Office, Thanjore and Ors. v. V. G.

         Thambidurai and anr.8.


 1   1987 Mh.L.J. 419
 2   2012(3) Mh. L.J. 640
 3   1990 Mah. L.J. 1015
 4   2004(2) Mh.L.J. 1087
 5   1998(3) Mh.L.J. 10
 6   (2016) 9 SCC 20
 7   (2017) 11 SCC 601
 8   (2017) 12 SCC 642

                                  Page 28 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         29                 wp [email protected]




         Submissions on behalf of the Respondents


 25.     On the other hand, Mr. Dande, learned counsel for the municipal

 corporation would not dispute that the petitioners were not heard before

 passing of the impugned order by which the Occupancy Certificate

 granted to the petitioner's premises was cancelled as also the revised

 Commencement Certificate. It is submitted that however such action was

 required to be taken by the municipal corporation in pursuance of the

 directions of the State Government and the insistence of the CIDCO for

 recovery of amount due and payable by Satra Properties to the CIDCO in

 regard to the plots in question. It is submitted that it was an obligation on

 Satra Properties to make payment of the said amount to the CIDCO. It is

 submitted that CIDCO, under its regulations and the NOC granted by it

 to undertake development of the plots in question, was entitled to recover

 the said amount from Satra Properties. It is next submitted that not only

 in respect of the plots held by the petitioner, but also in respect of the

 other plots, issue of amounts due and payable to the CIDCO was also

 subject matter of consideration before the State Government. In such


                                  Page 29 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         30                 wp [email protected]


 regard, discussions have taken place between the CIDCO and the

 NMMC. It is submitted that under the terms and conditions of the

 agreement entered between Satra Properties and the NMMC, it was

 incumbent on Satra Properties to make payment of such amount and for

 such reason, there cannot be a dispute that amounts are recoverable by

 CIDCO from Satra Properties. In so far as the applicability of Section 51

 of the MRTP Act is concerned, Mr. Dande has made submissions on the

 purport of Section 51 of the MRTP Act.



 26.     Mr. Ashutosh Kulkarni, learned counsel for the CIDCO would

 submit that issuance of Occupancy Certificate and its cancellation are

 matters purely concerning the municipal corporation. It is submitted that

 however, CIDCO has its claim to recover the amounts on the said plots

 and which need to be kept open and the CIDCO ought not to be

 prejudiced in any manner so that the recovery of the said amounts is in

 any manner affected. Mr. Kulkarni has drawn our attention to powers of

 CIDCO as conferred under New Bombay Disposal Of Land Regulations,

 1975 and also taking into consideration the provisions of the MRTP Act,

 whereunder the CIDCO was appointed by the State Government as a

                                  Page 30 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          31                 wp [email protected]


 new town development authority, for the Navi Mumbai Project. It is

 hence, his submission that whatever amounts, which is legitimately due

 and payable to the CIDCO, CIDCO would be entitled to recover the

 same as permissible in law. Mr. Kulkarni, therefore, submits that the

 rights and interest of the CIDCO, to such extent needs to be protected.




 27.     On the above conspectus, we have heard learned counsel for the

 parties, as also we have perused the record.



         Analysis and Conclusion

 28.     At the outset, it needs to be stated that on facts, there is no dispute

 that Satra Properties was allotted the plots in question and that Satra

 Properties had undertaken the construction in question.                                  The

 construction was undertaken as per the plans which were approved. The

 construction was never categorized to be an illegal construction and was

 in fact, granted an Occupancy Certificate on 09 February, 2012. The

 consequence of a building receiving Occupancy Certificate needs no

 elaboration, suffice it to observe that the building in question was

                                   Page 31 of 44
                                -------------------------




::: Uploaded on - 04/05/2023                            ::: Downloaded on - 05/05/2023 15:02:27 :::
                                              32                 wp [email protected]


 permitted to be legally occupied as also tenements in the building could

 be purchased and sold by the members of the petitioner to third parties.

 Thus, the consequence of Occupancy Certificate being granted not only is

 a consequence relevant to the co-operative society like the petitioner, in

 which such tenements are situated, but also relevant in so far as the

 members of the petitioner who have purchased the tenements and who

 are entitled in law to occupy the same on the assumption, that their

 occupation by virtue of the Occupancy Certificate granted by the

 municipal corporation is legal and valid.



 29.     The power of revocation of an Occupancy Certificate is governed

 by Section 51 of the MRTP Act. As the impugned order passed by the

 Municipal Commissioner is in exercise of such powers, such provision is

 required to be noted which reads thus:-

          "51. Power of revocation and modification of permission to
          development:-
          (1)    If it appears to a Planning Authority that it is expedient,
          having regard to the Development plan prepared or under
          preparation that any permission to develop land granted 1 [or
          deemed to be granted] under this Act or any other law, should be
          revoked or modified, the Planning Authority may, after giving the
          person concerned an opportunity of being heard against such
          revocation or modification, by order, revoke or modify the permission
          to such extent as appears to it to be necessary:


                                       Page 32 of 44
                                    -------------------------




::: Uploaded on - 04/05/2023                                ::: Downloaded on - 05/05/2023 15:02:27 :::
                                               33                 wp [email protected]


          Provided that- (a) where the development relates to the carrying out
          of any building or other operation, no such order shall affect such of
          the operations as have been previously carried out; or shall be passed
          after these operations have substantially progressed or have been
          completed;
          (b) where the development relates to a change of use of land, no such
          order shall be passed at any time after change has taken place.

          (2)    Where permission is revoked or modified by an order made
          under sub-section (1) and any owner claims within the time and in
          the manner prescribed, compensation for the expenditure incurred in
          carrying out the development in accordance with such permission
          which has been rendered abortive by the revocation or modification,
          the Planning Authority shall, after giving the owner reasonable
          opportunity of being heard by the Town Planning Officer, and after
          considering his report, assess and offer, subject to the provisions of
          section 19, such compensation to the owner as it thinks fit.

          (3)     If the owner does not accept the compensation and gives
          notice, within such time as may be prescribed, of his refusal to accept,
          the Planning Authority shall refer the matter for the adjudication of
          the Court, and the decision of the Court shall be final and be binding
          on the owner and Planning Authority."


 30.     A bare reading of Section 51 of the MRTP Act makes it explicit

 that the planning authority is required to be satisfied on the following

 requirements to invoke the powers under Section 51 to revoke the

 Occupancy Certificate:-

 i.      If it appears to the Planning Authority that it is expedient, having

 regard to the "Development Plan" prepared or under preparation that any

 permission to develop land granted [or deemed to be granted] under the

 MRTP Act is required to be revoked or modified,

                                        Page 33 of 44
                                     -------------------------




::: Uploaded on - 04/05/2023                                 ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         34                 wp [email protected]


 ii.     Necessarily such a decision of the Planning Authority is required to

 be taken in the context of an existing development plan prepared or

 under preparation, that such a permission to develop is likely to affect

 such development plans.

 iii.    A Planning Authority in taking such action is under an obligation

 to grant an opportunity of being heard to the person concerned against

 such revocation or modification, before an order is passed to revoke or

 modify the permission.



 31.     The proviso below sub-section (1) also has a bearing in as much as

 where the development relates to the carrying out of any building or other

 operation, no such order shall affect such of the operations as have been

 previously carried out; or shall be passed after these operations have

 substantially progressed or have been completed.                   Further where the

 development relates to a change of use of land, no such order shall be

 passed at any time after a change has taken place.



 32.     The question is whether the requirements of Section 51 are

 satisfied in the present case, so as to empower the municipal corporation

                                  Page 34 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                          35                 wp [email protected]


 to invoke the provisions of Section 51. On a plain reading of the

 impugned order, it is clear that the Occupancy Certificate has been

 revoked for breach of condition no.4 of the letter dated 09 February, 2012

 issued by the municipal corporation namely that Satra Properties did not

 produce NOC from CIDCO within one year of the issuance of the

 Occupancy Certificate. It is clear that the breach of condition no.4 of the

 Occupancy Certificate, is no ground as Section 51(1) of the MRTP Act

 would contemplate, so as to authorise or empower the municipal

 corporation to cancel the Occupancy Certificate. Such reason as assigned

 by the Municipal Commissioner is nothing to do with development plan

 or any proposed development plan and hence, on the clear implication of

 the provisions of Section 51(1), the impugned order cancelling

 Occupancy Certificate is rendered illegal.



 33.     This apart, there is a direct breach of provision of sub-section (1) of

 Section 51 in the Municipal Commissioner passing the impugned order in

 as much as the petitioner certainly was concerned and in fact seriously

 prejudiced by any action to be taken by the Municipal Commissioner to

 revoke the Occupancy Certificate in exercise of the powers under Section

                                   Page 35 of 44
                                -------------------------




::: Uploaded on - 04/05/2023                            ::: Downloaded on - 05/05/2023 15:02:27 :::
                                                36                 wp [email protected]


 51(1) of the MRTP Act. The Municipal Commissioner proceeded

 completely on an erroneous premise that it would be Satra Properties

 alone who was the concerned person who would be required to be given a

 personal hearing.             This was an arbitrary approach of the Municipal

 Commissioner. He could not have taken a superficial view of the matter,

 deviating from the requirements of law.



 34.     As stated by us in the foregoing paragraphs, the grant of the

 Occupancy Certificate brings about several other legal consequences,

 concerning third parties who would be adversely affected, if the

 Occupancy Certificate is to be revoked. The petitioner, who would be

 directly affected by such decision, was admittedly not heard. Hence the

 impugned order passed without hearing the petitioner not only falls foul

 of sub-section (1) of Section 51, but would be required to be held to be

 non-est and illegal being in breach of the principles of natural justice qua

 the petitioner when it brings about civil consequences.



 35.     The above discussion would lead us to unhesitatingly observe that

 the Municipal Commissioner in passing the impugned order has

                                         Page 36 of 44
                                      -------------------------




::: Uploaded on - 04/05/2023                                  ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         37                 wp [email protected]


 proceeded on a total misinterpretation of the requirement of sub-section

 (1) of Section 51 on all counts, namely that the issue did not involve

 anything to do with the development plan or any proposed development

 plan and that the reason of non-compliance of condition no.4 of the

 Occupancy Certificate could never be of any consideration to revoke the

 Occupancy Certificate as granted to the premises of the petitioner.



 36.     As noted above, the Municipal Commissioner totally overlooked

 that the reasons as set out in the impugned order of an alleged non-

 compliance of condition no.4 i.e. non obtaining of NOC from the

 CIDCO was totally alien and/or extraneous to the applicability of Section

 51 in the facts of the present case. In such context, Mr. Rajadhyaksha

 would be justified in placing reliance on the decisions in Digambar

 Sakharam Tambolkar and another vs. Pune Municipal Corporation and

 others (supra) and Mahavir Entraprises and others vs. State of

 Maharashtra and others9 when he contends that the impugned order has

 been passed on misapplication of the powers vested with the Municipal

 Commissioner under Section 51of the MRTP Act.

 9   1990 Mh.L.J. 1015

                                  Page 37 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                            38                 wp [email protected]




 37.     In Digambar Sakharam Tambolkar and another vs. Pune

 Municipal Corporation and others (supra), the Division Bench after

 noting the said provision, has held that Section 51 which falls under

 Chapter IV of the MRTP Act, which deals with "Control of Development

 and Use of Land included in Development Plans". It was observed that

 there were several inbuilt safeguards in the said provision. It was observed

 that permission already granted can be revoked under S. 51 only if it

 appears to the Planning Authority that it is expedient to do so having

 regard to the Development plan prepared or under preparation. The

 Court observed that there were sufficient guidelines indicated in the

 section itself to invoke the said provision. It was also observed that there

 is a provision for giving opportunity of being heard to the affected party

 before the permission already granted could be revoked or modified and it

 is not as if in all cases falling under Section 51 (1) but not falling under

 the proviso thereto, the permission granted must be revoked and

 accordingly, upheld the constitutional validity of Section 51. The relevant

 observations are required to be noted which read thus:-

          "This section comes under Chapter IV which deals with "Control of

                                     Page 38 of 44
                                  -------------------------




::: Uploaded on - 04/05/2023                              ::: Downloaded on - 05/05/2023 15:02:27 :::
                                               39                 wp [email protected]


          Development and Use of Land included in Development Plans".
          There are several inbuilt safeguards in the section as is evident from
          its plain reading. Permission already granted can be revoked under
          Section 51 only if it appears to the Planning Authority that it is
          expedient to do so having regard to the Development plan prepared
          or under preparation. It is therefore, difficult to accept that no guide-
          lines are indicated in the section. There is provision for giving
          opportunity of being heard to the affected party before the permission
          already granted can be revoked or modified. There again it is not as if
          in all cases falling under Section 51 (1) but not falling under the
          proviso thereto, the permission granted must be revoked. It can be
          modified in appropriate cases. Thus, the Planning Authority is vested
          with the discretion. It can revoke or modify the permission
          depending upon the circumstances of each case. Sub-section (2) on
          the other hand provides for compensation in cases where the affected
          party has to suffer loss for no fault of it. In case the affected party is
          not satisfied with the amount of compensation granted, there is
          provision for reference of the disputes for the adjudication of the
          Court."


 38.     In Mahavir Entraprises and others vs. State of Maharashtra and

 others (supra), the Court was concerned with the action of the respondent

 of passing the order impugned in the said proceedings without hearing

 the petitioners. The Court observed that such action was in breach of the

 principles of natural justice, which were explicitly recognized by the

 provisions of sub-section (1) of Section 51. Applying the well - settled

 principles of law that if the statute provides that the power vested in the

 authority should be exercised in a particular manner, it cannot be

 exercised in any other manner (as held in Hukum Chand Shyam Lal vs.



                                        Page 39 of 44
                                     -------------------------




::: Uploaded on - 04/05/2023                                 ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         40                 wp [email protected]


 Union of India and others, AIR 1976 SC 789) the Court held that the

 exercise of power by the Planning Authority under section 51 of the Act

 was subject to the observance of the principles of natural justice being a

 condition precedent for the exercise of such power and an order which

 was passed without due observance of the principles of natural justice was

 an order without jurisdiction and accordingly, the order impugned therein

 was quashed and set aside.



 39.     In Shree Ambica Developers v. State of Maharashtra and others

 (supra) a Division Bench of this Court has held that the power conferred

 by Section 51, can be exercised if the planning authority is of the opinion

 that the permission must be revoked or modified having regard to a

 development plan and when no such ground was stated in the order

 impugned before the Court, an order under Section 51 revoking

 occupation certificate would be rendered illegal.



 40.     In Kohinoor CTNL Infrastructure Company Pvt. Ltd. and another

 vs. Municipal Corporation of Greater Mumbai 10, a Division Bench of this

 10 2013(1) Mh.L.J. 88

                                  Page 40 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                         41                 wp [email protected]


 Court considering Section 51(1) of the MRTP Act, observed that this is a

 provision made in the interest of preserving the sanctity of a development

 plan and the intent of the provision is to ensure that a development which

 would impede or be detrimental to the realisation of the purposes of a

 development plan that is already prepared, or even one that is under

 preparation should be regulated and this is how sub-section (1)

 empowered the planning authority to modify or revoke planning

 permission already granted to develop land. It was observed that the

 legislature was cognizant of the fact even before a permission is revoked or

 modified, planning permissions may have been acted upon and works

 may have commenced and to deal with such cases, the legislature has

 drawn a balance through the proviso.



 41.     In our opinion, the position in law empowering the planning

 authority to invoke Section 51 is absolutely clear as seen from the

 provisions of sub-section (1) of Section 51. It is only when the objected

 development is in some manner affecting the development plan invoked

 or being prepared, which is likely to frustrate the object of the

 development plan, it is only on such circumstances, the authority and

                                  Page 41 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::
                                           42                 wp [email protected]


 power under sub-section (1) of Section 51 can be invoked to take steps to

 revoke the occupation certificate. It is only in these circumstances, the

 planning authority would assume jurisdiction to initiate such action by

 following the procedure in law to revoke the occupation certificate and

 not for any other reason which is alien and not recognised under Section

 51 of the MRTP Act. The facts of the present case clearly demonstrate

 that none of the requirements as sub-section (1) of Section 51 were

 attracted so as to invoke such powers to cancel the Occupancy Certificate

 granted to the petitioner's premises.                  In these circumstances, the

 impugned order is patently illegal.



 42.     There is yet another question as to whether it was permissible for

 the municipal corporation to issue a Conditional Occupancy Certificate in

 respect of the petitioner's premises.             In our opinion, the municipal

 corporation was not in a position to justify anything either under the

 MRTP Act or under the DCR framed by CIDCO that it was permissible

 for the CIDCO to issue a conditional Occupancy Certificate of the nature

 as issued in the present case. Thus, issuance of a conditional occupancy

 certificate itself was unjustified.

                                    Page 42 of 44
                                 -------------------------




::: Uploaded on - 04/05/2023                             ::: Downloaded on - 05/05/2023 15:02:27 :::
                                            43                 wp [email protected]


 43.     In the light of the above discussion, the petition needs to succeed.

 It is accordingly allowed in terms of the following order:-

                                       ORDER

i. The impugned order dated 27 December, 2016 passed by the Municipal Commissioner of the respondent - Navi Mumbai Municipal Corporation cancelling the Occupancy Certificate and the revised Commencement Certificate is quashed and set aside. ii. It is declared that condition no.4 as incorporated in the Occupancy Certificate dated 09 February, 2012 issued in respect of the petitioner's premises is illegal and was incorporated without any authority in law. iii. As a consequence of the above orders, the Municipal Corporation is prohibited from initiating any coercive action under the impugned order dated 27 December, 2016 under notices issued under Section 53(1) of the MRTP Act.

iii. Rule is made absolute in the above terms.

iv. No costs.

Order in Writ Petition No. 1184 of 2017

44. In view of the above judgment and order passed by us on Writ Page 43 of 44

-------------------------

::: Uploaded on - 04/05/2023 ::: Downloaded on - 05/05/2023 15:02:27 :::

44 wp [email protected] Petition No. 1374 of 2017, this petition also needs to succeed. It is allowed in terms of judgment and order passed on the said petition. No costs.

 [KAMAL KHATA, J.]                                             [G. S. KULKARNI, J.]




                                  Page 44 of 44
                               -------------------------




::: Uploaded on - 04/05/2023                           ::: Downloaded on - 05/05/2023 15:02:27 :::