Section 194(4) in Rajasthan Municipalities Act, 2009
(4)(a)Municipality may, by bye-laws, provide that the documents required to be submitted under sub-Section (2) may be submitted in electronic form;(b)The Municipality shall decide the application and convey its written orders within a period of two months from the date of receipt of application. The Municipality or any authority or any committee empowered to grant the permission, shall also be competent to grant or to reject or modify the map or to impose other conditions or restrictions, as may be deemed necessary. In cases where the Municipality fails to convey its decision within two months, the applicant may undertake the construction, after giving one month's clear notice to that effect to the Municipality, considering it as a case of deemed permission. However, it shall be the responsibility of the applicant and the architect or engineer to ensure that in all cases of deemed permission, the provisions of the Act, rules and bye- laws are not violated.