Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

State Consumer Disputes Redressal Commission

Kseb,Rep.By Secretary vs M/S.Omega Elevators on 28 March, 2017

  	 Cause Title/Judgement-Entry 	    	       STATE CONSUMER DISPUTES REDRESSAL COMMISSION  THIRUVANANTHAPURAM             Complaint Case No. CC/07/6             1. KSEB,Rep.by Secretary	  Vydyuthi Bhavanam,Pattom,Tvpm  2. The Chief Engineer (Civil Construction) South  KSEB, Vydyuthi Bhavanam, Pattom, Tvpm  Kerala ...........Complainant(s)   Versus      1. M/s.Omega Elevators  4,Kurien Tower,3rd Floor,Banerjee Road,Kochi  2. Kumar.M.Desai  Omega Elevators, H.O.Omega, New Sharda Mandir Road, Paldi, Ahemadabad ............Opp.Party(s)       	    BEFORE:      HON'ABLE MR. JUSTICE SRI P.Q.BARKATH ALI PRESIDENT     SRI. V. V. JOSE MEMBER          For the Complainant:  For the Opp. Party:    Dated : 28 Mar 2017    	     Final Order / Judgement    

'\THE KERALA STATE  CONSUMER DISPUTES REDRESSAL  COMMISSION

 

VAZHUTHACAUD,  THIRUVANANTHAPURAM.

 

 COMPLAINT .  NO- 06/2007

 

 JUDGMENT  DATED. 28-03-2017

 

 

 

PRESENT:- 

 

          JUSTICE.  SRI. P.Q. BARKATH ALI         : PRESIDENT

 

          SRI. V.V.JOSE                                              : MEMBER

 

 

 

 COMPLAINANTS:

 
	 The Kerala State Electricity Board


 

Represented by its Secretary,

 

Vydyuthi Bhavanam, Pattom,

 
	  


 
	 The Chief Engineer ( Civil - Construction) South,


 

KSE Board, Vydyuthi Bhavanam, Pattom, Thiruvananthapuram.

 

(By Adv. B. Sakthidharan Nair)

 

 

 

     V/S

 

 OPPOSITE PARTIES:

 
	 M/s. Omega Elevators, 4, Kurien Tower,
	  
	 Mr. Kumar. M. Desai, Omega Elevators, " H.O. Omega" , New Sharda Mandir Road, Paldi,


 

Ahemedabad- 380007.

 

(By Adv. Poovappally Rama chandran Nair , C.S.Rajmohan and others)

 

 

 

(2)

 

 JUDGMENT 

JUSTICE. SRI. P.Q.BARKATH ALI: PRESIDENT             This is a complaint filed by the complainant  M/s. KSEB claiming  compensation for the defective lift supplied by the opposite parties. First complainant is KSEB represented by its  secretary and second complainant is its Chief Engineer ( Civil Construction) Vydhyuthi Bhavan, Pattom. 

          The case of the complainants as detailed in the complaint in brief is this.

          The Head office of the  Board is  functioning  at Vydyuthi Bhavan, Pattom, Thiruvananthapuram in  building  having  10 floors and lift  1 to 5.    Five ' Beacon'  make  passenger  lifts were  installed  during July 1985.  Due to frequent  complainant  in 1999 board by its order dated December 30, 2003  decided  to replace  lifts  4 & 5 and by order dated January 13, 2005 decided to replace the lift No. 1,2 and 3. 

                                                          (3)

For replacement  for lift 4 &5 Tender  was invited on June 12, 2003 and for replacement for lift   1 ,2 and 3 tender was invited on October 7, 2004.  For the  replacement  of lift  4 & 5  the rate was Rs. 25lakhs for  supply and  erection  and Rs. 10,50,000/- for  annual comprehensive   maintenance  contract for 5 years.  The guarantee  period  was for  one year.   For the replacement of lift  1 ,2, and 3 rate was Rs. 38, 16,000/- for supply and erection   and Rs.  8,25,000/- for the annual  maintenance  for 5 years.   On  May  29, 2004 after completion  of supply  and  erection of   lifts 4 & 5    Rs.  25 lakhs was paid to the first opposite party and on completion of supply and erection  of lifts  1 ,2 and 3 on October  31, 2005 Rs. 38, 16,000/- was paid to the first opposite party.   Clause  17 of the agreement  provides a  guarantee period   12  months  from the date of commissioning .  The guarantee period of lifts 4 & 5  is  May 28,  2005 and that of lifts 1,2   is  3 October 30, 2006.  After installation the lifts were not properly functioning.  The technicians  of the opposite parties  failed to rectify the defect.  The lift                                                                    (4) have  manufacturing defect even during the warranty period  which amounts to deficiency  in service.  The lift have to be repaired  141 times till May 14, 2007.  Therefore complainant filed the complaint  claiming  refund of Rs. 63,16,000/-  being the cost of the lifts  or in the alternative to repair the same.  Complainant  has also claimed a compensation of  Rs. 25 lakhs. 

          Opposite parties are M/s Omega Elevators , Kochi represented by one  Mr. Reghu and second opposite party is  Kumar M. Desai who  is having  a valid license  for  installing the lift  of first opposite party.  They in their version contended thus:  It is  true  that an agreement was entered  into  between the complainant  and opposite parties  to replace the old lifts  ( 1,2,3,4 &5) using the old damaged   guide rails at  Vydyuthi Bhavan  with a guarantee period of one year.  The guarantee  period of lift  No. 1,2,3 was over  on  October  13, 2006.  Warranty period of  lifts  No. 4 & 5 was over on May 28, 2005.  Thereafter  annual maintainance                                                                       (5) comprehensive contract was being done.  As per the agreement the installation work of  replacing  the old lifts using the old guide rails  with a new  one was over  within the stipulate time.  It was inspected thoroughly  by the  electrical inspectorate  and clearance  certificate  was obtained.  After taking possession   of the lifts complainant approached the opposite parties several times for several  modifications.  After executing  the  work the electrical inspector  inspected the lift of the  complainant   before handing  over possession of the lifts.  If there are any minor  defects  opposite parties are prepared to rectify the same.  The lift technicians  have instructed the complainant to replace  the old guide rails and faulty  ELCB used in lifts.  There is no lift operator in all there   lifts.  The components of the lifts are all very sophisticated electronic component which could be damaged by the  misuse of these lifts by the officials, employees  and  public who are unaware   of using the lifts in Vyduthi Bhavan.  Therefore there is no deficiency of service                                                                    (6) on the part of the opposite parties.  Complainant is also barred by limitation as agreement  was executed  in  2003 and the complainant has taken  possession of lifts in 2004.  Therefore complaint has to be dismissed.

          On the side of the complainants PW1 Sri. Rajeev Kumar.K the  Executive Engineer Civil Construction (   Construction south) KSEB, Vydyuthi Bhavan, Thiruvananthapuram was examined  and Exbt.A1 to A36 were marked.  On the side of the opposite parties Dw1  Sri. Reghu Raghavan  the Branch Manager of the first opposite party was examined and Exbt.B1 to B7 were marked.

          The following points arise for considerations Whether the complaint is maintainable?

Whether  there is any deficiency of service on the part of the opposite parties?

What are the reliefs the complainants are entitled to?

(7)

Point No.1           Opposite parties filed IA.683/2009 to amend  the  version  raising    the question   of  maintainability  of the complaint on the ground that complainant    is a commercial establishment.  The said IA was  allowed by order dated  29/07/2009. Thereafter   the question  of maintainability was heard as  a preliminary point.  By order dated October 29, 2009,   this commission found the  complaint  is maintainable which was confirmed in appeal by  National Commission  in first  appeal No. 5/2010 by Judgment dated January 22, 2010.  Thus the said order has become  final  and therefore  we hold that complaint  is maintainable.

Point No.2:-

          It is admitted that the lift Numbers 1,2,3, 4 and 5 installed in the Head office at  Vydyuthi Bhavan, Pattom were replaced by the first opposite party  in pursume to the tender , work orders and agreement  executed by the complainants and the first opposite party.  Exbt.A1 is the agreement  dated  January 12,2004 in respect of  lift No. 4 &5. 
                                                                   (8)
Exbt.A2 is the agreement dated March 1, 2005 in respect of lift No. 1,2 and 3.  As per the schedule of Exbt.A1 the agreed rate of lift  Numbers 4 & 5 was  25 lakhs for supplying and  erection of lifts and  Rs. 5,50,000/- for annual maintenance contract.  As per the schedule  of Exbt.A2  agreement the rate was  Rs. 32,16,000/- for supply and erection of lift 1,2 and 3 Rs. 8,25,000/- for annual  maintenance  contract for 5 years.  Exbt.A3 &A4 are the bills for Rs. 25 lakhs and Rs. 38 , 16,000/- issued by the opposite parties.  Exbt.A5 is the possession of elevators certificate dated May 29, 2004 showing that the 4 lifts were  commissioned  on May 29,  2004 and warranty period was  from May 29,  2004 to May 28,2005.  Exbt.A6 is the possession of  elevators certificate dated October 31, 2005 of lift No.5.
          The case of the complainants as testified as Pw1 is that several times the lifts broke down  and it was  got repaired  by the technicians of the opposite party.  He alleged that the said lifts  suffers from manufacturing defect and that therefore either opposite party is  bound to                                                                    (9) replace the same  or refund its  price.  Complainants mainly relied on Exbt.A7 to A20  and A32 and Exbt.X1 and Exbt. X2 .  Exbt.A7 are the true copies of the abstract of complainant  log books .  Exbt.A8 series are the lift complaint  reports issued by the opposite parties.  Exbt.X1 is the report  of the expert commissioner showing the defects of the ' Lift'.  Exbt.X2 is the additional report of the Commissioner.  In Exbt.X1 the report  the expert commissioner  suggested replacement of lifts two and five and replacement of parts of lift one,   three and four.  In Exbt.X2 report commissioner have reported about the probable expenditure required for repairing lifts 1,3 and 4.   The above documents prove  beyond   doubt  that the  lifts    became   defective  during the warranty period itself   and though  the  employees of the opposite parties attended the aforesaid defect they could not  rectify the same.  Exbt.A9  to A.29 are the letters           sent by the complainants requesting the opposite parties to rectify the defects in the lifts which they did not do.                                                    
                                                          (10)
In IA. 689/2009 on  October 4, 2007 this commission directed the opposite parties to rectify  the defect in 15 days which opposite parties  did not do.  Therefore on October31,  2007  this commission permitted the complainants  to carry out the repairs at  the risk of the opposite parties. In pursuance of the said order  complainants  spent about  Rs.11,16,000/- for repairing lifts.  Complainants have also replaced the lift 2 & 5 spending Rs. 47,91,960/-.   Complainants produced statements showing the details of the amount spent.   It is clear from the above that the lift  suffer from manufacturing defects.    Thus there is clear deficiency of service on the part of the opposite parties.  It follows that complainants are entitled to refund of the price  of the lift and compensation.  They  also entitled to get the amounts  spend  for replacing the lifts. 
          In the result complaint is allowed.  Opposite parties are directed to refund to the complainants Rs. 63,16,000/- being   price of the lifts installed  by the opposite parties.  They are also entitled to recover from                                                           (11) the opposite parties Rs. 47,91,960/- spent  for installing  the new lifts 2 and 5 and Rs. 11,16,000/-  being the cost incurred for repairing the lifts 1,3 &4.    Instead of awarding compensation  we feel that interest at the rate of 12% per  annum  from the date  of complaint till realization would be reasonable.  The complainants are entitled to a cost of Rs. 10,000/- in this complaint. 

 

 

 

                                      JUSTICE. P.Q.BARKATH ALI: PRESIDENT

 

 

 

                                      V.V.JOSE                                      : MEMBER

 

 

 

 APPENDIX

 

 Witness for the complainant:

 

Pw1:  Sri. Rajeev Kumar.K.

 

                                                              (12)

 

Exbt.X1- Report of expert Commissioner dated on 01-02-2011.

 

Exbt. X2- Additional report  of expert Commissioner dated. 01/02/2011 

 

 Witness  for the opposite parties:

 

Dw1: Sri . Reghu Raghavan

 

 Exhbits for the complainants:

 

 Exbt. A1The copy of the agreement 2/ CECC/2004 dated. 12.01.2004 .

 

Exbt.A2- Copy  of the agreement 3/CECC/2005 dated. 01.03.2005.

 

Exbt.A3-   Copy of the Bill No. 27  dated. 28/02/2004.

 

Exbt.A4-Copy of the Bill No. 13 dated . 31/10/2005.

 

Exbt.A5- Copy of the possession of elevator certificate  certificate dated.           29/05/2004.

 

Exbt.A6- Copy of the possession of elevator  certificate certificate   dated.                            31/10/2005.

 

Exbt.A7- Abstract of log of complaints  recorded (11 sheets) .

 

Exbt.A8- Copy of lift  complaint Reports ( 69 Nos).

 

 

 

                                                                   (13)

 

Exbt.A9- Copy of letter  send  to the  opposite party by  the complainant                             dated. 08/02/2006.

 

Exbt.A10-Copy  of letter  send to the  opposite party by  the complainant                  dated. 04/04/2006.

 

Exbt.A11-Copy of letter  send to the  opposite party by  the complainant                             dated. 04/05/2006.                                                        

 

Exbt.A12- Copy of letter   send to the  opposite party by  the                                               complainant dated. 08/05/2006

 

Exbt.A13- Copy of letter     send to the  opposite party by  the                                    complainant dated. 12/05/2006.

 

Exbt.A14-Copy of letter   send to the  opposite party by  the complainant                  dated. 16/05/2006.

 

Exbt.A15- Copy of letter   send to the  opposite party by  the                                               complainant dated. 22/05/2006.

 

Exbt.A16-Copy of letter    send to the  opposite party by  the                                               complainant dated. 23.05.2006

 

Exbt.A17- Copy of letter    send to the  opposite party by  the                                              complainant dated 26.06.2006

 

Exbt.A18-  Copy of letter    send to the  opposite party by  the                                    complainant dated. 30.06.2006

 

 

 

                                                          (14)

 

Exbt.A19- Copy of letter     send to the  opposite party by  the                                    complainant  dated. 30.06.2006

 

Exbt.A20- Copy of letter    send to the  opposite party by  the                                              complainant dated. 06/07/2006.

 

Exbt.A21-  Copy of letter      send to the  opposite party by  the                                  complainant dated. 07/07/2006

 

Exbt.A22- copy of letter    send to the  opposite party by  the                                               complainant dated. 15/07/2006

 

Exbt.A23- Copy of letter     send to the  opposite party by  the                                    complainant dated. 17/07/2006.

 

Exbt.A24- Copy of letter    send to the  opposite party by  the                                              complainant  dated. 18/09/2006.

 

Exbt.A25- copy of letter       send to the  opposite party by  the                                   complainant     dated. 30/09/2006

 

Exbt.A26- Copy of letter    send to the  opposite party by  the                                              complainant dated. 02-02-2007

 

Exbt.A27- Copy of letter   send to the  opposite party by  the                                               complainant dated. 28/03/2007.

 

Exbt.A28-  Copy of letter send to the  opposite party by  the complainant dated.                           18/05/2007

 

 

 

                                                          (15)

 

Exbt.A29-Copy of letter  sent to the opposite party  by the complainant dated. 25-                       04-2007.

 

Exbt.A30- Copy of letter dated. 15-03-2007 and  Copy of postal receipt                               ExhibitA.30 series.

 

Exbt.A31- Copy of the Attendance report .

 

Exbt.A32- copy of the lift break down log.

 

Exbt.A33- copy of the agreement dated. 30/10/2008                                          

 

Exbt.A34- Copy of  Agreement dated. 06/12/2007.

 

Exbt.A35-Supplementary agreement dated. 14/01/2009.

 

 Exhbits for the opposite parties:

 

Exbt.B1- Special Power of Attorney

 

Exbt.B2- Routine maintainance card

 

Exbt.B3-   Proceeding of the electrical Inspector,Thiruvananthapuram .

 

Exbt.B4- Letter  given to the complainant  by opposite party dated.                     21-03-2007.

 

Exbt.B5- The certificate  issued to the opposite party by the                                 complainant .

 

 

 

                                                          (16)

 

Exbt.B6- Letter given to the complainant by the opposite party                                      dated. 05-09-2007.

 

Exbt.B7- Letter given to complainant by opposite party dated.                                       06/04/2007.

 

 

 

JUSTICE. P.Q.BARKATH ALI: PRESIDENT

 

 

 

                                       V.V.JOSE                                      : MEMBER

 

 

 

 

 

 

 

Sh/-

 

 

 

 

 

 

 

                                                                            

 

              [HON'ABLE MR. JUSTICE SRI P.Q.BARKATH ALI]  PRESIDENT 
     [ SRI. V. V. JOSE]  MEMBER