Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 0]

Delhi District Court

M/S Bhandari Engineers And Builders Pvt ... vs . M/S D. S. Constructions Ltd. & Anr. on 27 September, 2018

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.




    IN THE COURT OF DR. AJAY GULATI, ADDL. DISTRICT JUDGE,
           SAKET COURTS, SOUTH DISTRICT, NEW DELHI

In the matter of
CS No.207707/2016
Filing No.15718/2008
CNR No. DLST01­000053­2008

M/s Bhandari Engineers and Builders Pvt Ltd.,
a company incorporated under the
Companies Act 1956, having its
Registered Office at Bhandari House,
91, Nehru Place, New Delhi
                                       ................Plaintiff

                                   Versus

1.      M/s D. S. Construction Ltd.
        Having its Registered Office at
        C­66, South Extension­II,
        New Delhi­110 049
2.      N. D. Mehra
        Director
        M/s D. S. Construction Ltd.
        C­66, South Extension­II,
        New Delhi­110 049
                                                              .............Defendants


                 Date of Institution           :                      07.05.2008
                 Date of reserving the judgment:                      27.09.2018
                 Date of pronouncement         :                      27.9.2018
                 Decision                      :                      Dismissed



CS No.207707/2016                                                                Page No. 1 of 36
 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.




        SUIT FOR RECOVERY OF RS.69,00,000/­ ALONGWITH
              INTEREST, PENDENTELITE AND FUTURE

JUDGMENT

1.    The present suit has been filed for seeking recovery of Rs.69,00,000/­ (along with interest @ 18%) from defendant no. 1 as unpaid dues of a work contract which was executed by the plaintiff and due execution of which was acknowledged by defendant no. 1.  However, defendant no.1 has refuted the liability to pay the suit amount on the ground that plaintiff and defendant no.1, vide a tripartite agreement, had foreclosed the execution   of   all   the   pending   works   (vide   a  Foreclosure   and Settlement Agreement dt. 05.03.2005) and  also  finally settled all the claims of the plaintiff qua defendant no.1 for a total sum of Rs. 55 lacs which amount was admittedly received by the plaintiff. However, plaintiff contended that the Foreclosure and Settlement Agreement  dt. 05.03.2005 was in respect of 2 specific   contracts:   package   contracts  S1  and  S2  for construction of 2 flyovers on Delhi - Gurgaon expressway, and not in respect of the work contract for which the suit had been instituted i.e. contract for the construction of storm drains and box culverts  along the  Delhi - Guragon  expressway. A further detailing of certain facts would be necessary to comprehend CS No.207707/2016 Page No. 2 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

the entire scope of the dispute raised in the present suit.

2.   Plaintiff, which is a limited company and engaged in high   end   construction   projects,   was   a   sub­contractor   for carrying out a part of the work of 8 laning of access controlled Delhi - Gurgaon National Highway from 14.30 km to 42.00 km. The   main   contract   was   awarded   by   the  National   Highway Authority   of   India   (NHAI)  to   JPDSC   Ventures   Ltd.   In   turn, JPDSC   Ltd.   had   engaged  Jayprakash   Industries   Limited  (JIL) for the said contract which had further sub contracted a part of the main project i.e. construction of flyovers at Rao Tula Ram marg and at Palam junction to the plaintiff. The sub­contracts were awarded to the plaintiff vide letters dt. 27.1.2003 issued by  Jayprakash   Industries   Limited.   Subsequently,   vide   a multiparty   agreement   which   included   the   plaintiff   and defendant no. 1, defendant no. 1 i.e. DSC Ltd. stepped into the shoes   of  Jayprakash   Industries   Limited  for   all   intents   and purposes.

3.   It   appears   from   the   pleadings   and   documents   on record (especially Ex. Pw1/7) that the sub - contract awarded to the plaintiff did not gather much progress due to procedural CS No.207707/2016 Page No. 3 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

delays, in particular due to the change of design of the flyovers by NHAI. Since the machinery and material procured by the plaintiff at the construction site was lying idle, plaintiff agreed to and consequently, was awarded the work of construction of storm  drains and box culverts  along the same highway (New Delhi   -   Gurgaon   8   laning   expressway)   for   which   the   sub­ contract of construction  of flyovers had been awarded to it. This work was awarded vide a separate letter dt. 10.6.2004 and   was   successfully   completed   by   31.8.2004.   Possession   of the completed work was also taken over by defendant no.1. There   is   no   dispute   regarding   this   aspect.   It   is   also   not   in dispute  that  the  said   work   was  taken  up   by   the  plaintiff  to mitigate the losses accumulating on account of sub­contract of flyovers getting delayed/frustrated. In respect of the work of construction   of  drains   and   culverts,   plaintiff   claims   to   have submitted 2 bills which were cleared by defendant no. 1. The final   bill   however   (and   which   is   a   very   relevant   fact)   was submitted on 9.5.2005 i.e. after the signing of Foreclosure and Settlement   agreement   dt.   05.03.2005   and   almost   8   months after   the   work   of   construction   of  drains   and   culverts  was completed on 31.8.2004 (and handed over to the defendant no. 1).

CS No.207707/2016 Page No. 4 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

4.   Subsequently, due to further delays from the side of NHAI and taking into account the losses being suffered by the plaintiff on account of idle machinery and material, liability of which (losses) would have had to be borne by defendant no.1 being   the   main   contractor,   defendant   no.1   entered   into   a tripartite  Foreclosure   and   Settlement   Agreement  which   has already been referred to at the outset. 

5.   It is not in dispute that the plaintiff was required to be paid separately for the work of construction of storm drains and box culverts.  Infact,  the whole purpose for the plaintiff to take  up   this   extra  work  was  to  make   some   money  so  as to mitigate the losses being suffered by it on account of delay in the execution of main sub contract of construction of flyovers. Defendant   itself   has   highlighted   this   aspect   in   its   written statement. The dispute however is in regard to the scope of the Foreclosure and Settlement Agreement. The plaintiff maintains that since the work of construction of  drains and culverts  on the Delhi - Gurgaon highway/expressway was granted vide a separate contract letter (dt. 10.6.2004), it did not form a part of the main sub contracts S1 (for construction of flyover at Rao CS No.207707/2016 Page No. 5 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

Tula Ram Marg) and S2 (for construction of flyover at  Palam Junction)   and   consequently,   the  Foreclosure   and   Settlement Agreement  (F & S A)  did not  encompass within its scope, the final  bill  which  was raised by  the   plaintiff   in  respect  of   the work of drains and culverts. The whole argument raised by the plaintiff is that the F & S A was only in respect of the package contracts   S1   and   S2   whereas   the   contract   for  drains   and culverts  was   an   independent   contract   which   was   neither contemplated nor included in the scope of the final settlement which was entered into between the Plaintiff and Defendant no.1  in  respect  of  contracts S1  and S2.  On  the  other  hand, defendants asserted that the plaintiff agreed to do the work of drains and culverts as an extra work but as a part of the main sub   contract   of   construction   of   flyover   at  Palam  junction. Defendants emphasized that the language of the F & S A was very wide in scope and took into account all possible claims which the plaintiff had and might have had against defendant no.1 in relation to all the work orders given to the plaintiff. Thus,   all   existing   and   future   claims   of   the   plaintiff   against defendant no.1 stood settled by way of final payment for Rs. 55 lacs which was duly received by the plaintiff. Defendants underscored  the   submission   that   the   work   of  drains   and CS No.207707/2016 Page No. 6 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

culverts was an extra work as a part of the main sub contacts of construction of flyovers and hence the  F & S A,  by necessary implication, included all claims which the plaintiff had against defendant   no.   1   in   respect   of   the   work   awarded   to   it   by defendant no.1 including the work of drains and culverts.

6.   There is no denial of the fact that plaintiff had to be paid for the extra work of  drains and culverts. Infact, in the entire   written  statement,   defendants  consistently  maintained that the entire claim of the plaintiff against the defendant no. 1 has already been settled vide the  F & S A.  Thus  the  core issue   which   requires   adjudication   is   the   scope   of  F   &   S   A. However, the respective pleadings necessitated the framing of issues which were framed as follows.

ISSUES

7.   Vide order dated 19.04.2010 the Hon'ble High Court of Delhi had framed the following issues:

1.  Is the suit time­barred? OPD
2.  Does   the   plaintiff   prove   that   the   contract   dated   CS No.207707/2016 Page No. 7 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.
10.05.2004   awarded   by   the   defendants,   for   construction   of   drains   and   culverts   was   duly   performed   and   is,   therefore,   entitled   to   the     amount claimed, i.e. Rs.50,57,658/­, or any  part   thereof ? OPP
3.  Do the defendants prove that the claim is barred,   on   account   of   satisfaction   pertaining   to   works   executed   for   drains   and   culverts,   by   view   of   the   Settlement   Agreement   dated   05.03.2005,   and   other circumstances, as alleged by them? OPD
4.  Do   the   defendants   prove   that   the   plaintiff   waived, abandoned, or surrendered all its  claims   against it under the Work Order for  drains   and   culverts, as  alleged? OPD
5.  Is the plaintiff entitled to interest on any amount   decreed; if so, at what rate and for what period?
6. Relief EVIDENCE ADDUCED On behalf of the plaintiff

8.    Plaintiff company, in order to prove its claim, examined CS No.207707/2016 Page No. 8 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

its   authorized   attorney   Sh.   S.   P.   Soni   as   PW­1   who   led   his evidence  by  way   of   affidavit  Ex.PW1/A.  PW­1  relied  on   the following documents:

1.  Photocopy  of the Special Power of Attorney in favour of PW­1 as Ex.PW1/1;
2.  Photocopy   of   letter   of   intent   No.   JIL/S­ 1/6/2003   dated   27.01.2003   from   Jaiprakash Industries Ltd to the plaintiff as Ex.PW1/2;
3.  Copy   of   letter   of   intent   No.   JIL/S­1/6   dated 26.05.2003 from Jaiprakash Industries to the plaintiff as Ex.PW1/3;
4.  Original Work Order No.1 vide letter No. JIL/S­ 1/6 dated 26.05.2003 from Jaiprakash Industries to the plaintiff as Ex.PW1/4;
5.  Original Work Order No.2 vide letter No. JIL/S­ 1/15/26   dated   14.07.2003   from   Jaiprakash Industries to the plaintiff as Ex.PW1/5;
6.  Copy   of   the   Agreement   dated   03.02.2004   as Ex.PW1/6;
7.   Original   letter   no.   DD/927   dated   28.06.2004 from the plaintiff to defendant no.1 as Ex.PW1/7;
8.  Copies of running bills of packages S­1 to S­2 as CS No.207707/2016 Page No. 9 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.
Ex.PW1/8 (colly.);
9.  Copy of TDS certificate dated 31.03.2004 issued by defendant no.1 as Ex.PW1/9;
10.  Copy of TDS certificate dated 31.05.2004 issued by defendant no.1 as Ex.PW1/10;
11.  Copy of TDS certificate dated 30.04.2005 issued by defendant no.1 as Ex.PW1/11;
12.  Original   letter   No.   DSC/PALAM/GEN/659 dated 29.07.2004 from defendant no.1 to the plaintiff as Ex.PW1/12;
13.  Original   letter   No.   BEBPL/PLM­RTR/2004­ 2005/020   dated   02.09.2004   from   the   plaintiff   to defendant   no.1   and   2004­2005/1116   dated 11.01.2005   from   the   plaintiff   to   defendant   no.1   as Ex.PW1/12A;
14.  Copy of Foreclosure & Settlement Agreement dated 05.03.2005 as Ex.PW1/13;
15.  Copy   of   letter   No.   DCL/Drains/Culverts/45 (2004) dated 10.05.2004 as Ex.PW1/14;
16.  Original   letter   No.   BEBPL/JPDC/01­04/973 dated 02.07.2004 from the plaintiff to the defendants as Ex.PW1/15;
CS No.207707/2016 Page No. 10 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

17.  Original   letter   No.   BEBPL/JPDC/01­04/941 dated 03.07.2004 from the plaintiff to the defendants as Ex.PW1/16;

18.  Original   of   Variation   Order   No.1   issued   vide letter   No.   DSC/549   dated   05.07.2004   from   the defendants to the plaintiff as Ex.PW1/17;

19.  Copies   of   R/A   bills   dated   16.07.2004   and 05.08.2004 of the defendant company as Ex.PW1/18 (colly.);

20.  Copy of Final Bill for C/o Drains & Culverts for Delhi Gurgaon Section of NH­8 (KM 14.495­15.037) from the plaintiff to defendant dated 09.05.2005 as Ex.PW1/19 (colly.);

21.  Original   letter   dated   26.05.2005   from defendants   to   plaintiff   and   original   letter   No. BEBPL/DSC/2005­06/1317   dated   06.06.2005   from the plaintiff to the defendants as Ex. PW1/20 (colly.);

22.  Minutes   of   meeting   dated   20.08.2004   at   DSC camp office, Gurgaon as Ex.PW1/21;

23.  Copy of Bill dated 10.06.2004 from the plaintiff to Jaiprakash Industries Ltd. alongwith covering letter dated 10.06.2004 as Ex. PW1/22;

CS No.207707/2016 Page No. 11 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

24.  Original letter No. BEBPL/DSC/2005­06/1371 dated 05.07.2005 from the plaintiff to the defendants as Ex.PW1/23;

25.  Original letter No. BEBPL/DSC/2005­06/1491 dated 21.09.2005 from the plaintiff to the defendant and   legal   notice   dated   24.12.2005   as   Ex.PW1/24 (colly.);

26.  Copy   of   reply   dated   14.03.2006   to   the   legal notice   dated   24.12.2005   along   with   postal   receipts and A/D as Ex.PW1/25; and

27.  Copy of rejoinder dated 28.03.2006 alongwith postal receipt along with copy of the legal notice dated 23.04.2007 along with postal receipts as Ex.PW1/26 (colly.).

 

(Ex.PW1/1 to Ex.PW1/3, Ex.PW1/6, Ex.PW1/8 to Ex.PW1/11, Ex.PW1/13, Ex.PW1/14, Ex.PW1/18, Ex.PW1/19, Ex.PW1/22, Ex.PW1/25   &   Ex.PW1/26   were   objected   to   by   the   Learned counsel for the defendants on account of admissibility and mode of proof.) CS No.207707/2016 Page No. 12 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

9.    PW­1, in his evidence by way of affidavit, deposed on the   lines   of   the   plaint.   During   his   cross   examination,   PW­1 deposed that the suit was based on the works completed on 31.08.2004   but   denied   that   the   claim   is   time   barred.   He admitted  that the payments were due on the defendants by 30.09.2004 for the work of construction of  storm drains and box culverts which was completed on 31.08.2004 as mentioned in para 16 of his affidavit; that the suit is based on a breach by defendant No.1 of the contract entered into with the plaintiff; and that there were no other contracts except S1 & S2 dated 27.01.2003, and award of work under letter dated 10.05.2004. He further submitted that there was no independent contract by defendant No. 2 to discharge the liability of defendant No.

1. He denied that work of construction of storm drain and box culverts  was being done as an 'extra item' to the contract for Palam  Junction   flyover.  Significantly,   witness   also   deposed that the plaintiff had requested that the work of  storm drain and   box   culverts  be   treated   as   extra   item   to   the   original contract;   however,   defendant   No.1   refused   and   prepared separate bills for the work done;  that  there was  no  separate letter by which defendant No. 1 refused to treat the work of construction of storm drain and box culverts as extra items; and CS No.207707/2016 Page No. 13 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

that preparation of separate bills by defendant No. 1 indicated that it treated the request of the plaintiff as refused.

 

10.  PW­1 denied the suggestions that defendant No.1 would never   have   awarded   the   contract   for   construction   of  storm drain and box culverts if it had not already been awarded the original   contracts   under   Packages   S1   and   S2;   and   that   the construction   of   the   drains   and   culverts   was   integral   to   the main contract and hence, only an extension.

11.  PW­1  further  denied  that   the   phrases   'other   works' mentioned   in   the   'No   Claims   Certificate'   at   page   175   of Ex.PW1/13 referred only to the works done for construction of drains and culverts; that all the claims of the plaintiff have been settled   vide   settlement   agreement   Ex.PW1/13   and   no   claim certificate,   both   dated   05.03.2005;   that   bills   for   drains   and culverts were raised alongwith bills for construction of flyover under S­1 and S­2; that raising bills for drains and culverts in May,   2005   i.e.   8   months   after   completion   of   work,   was   an afterthought to extract more money from the defendant;  and that   plaintiff   was   not   entitled   to   recover   any   amount   from defendant No.1. 

CS No.207707/2016 Page No. 14 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

12.  In response to a specific question as to what prevented the   plaintiff   from   stating   in   the   'settlement   agreement' Ex.PW1/3 that its claim pertaining to  drains and culverts  was not included as a part of the settlement, PW­1 answered that the  settlement  agreement dated 05.03.2005  Ex.PW1/13  was with regard to package S­1 and S­2 only and not for contract of  drains   and   culverts.  He   further   submitted   that   bills   for construction   of  drains   and   culverts  were   raised   as   the   work done for extra items along with the bill of contract package S 1 & S 2, as there was no work order on that day for drain and culverts. 

  No   other   witness   was   examined   on   behalf   of   the plaintiff.

On behalf of the defendants

13.  On the other hand, defendants in order to controvert the claim of the plaintiff, examined Sh. M. S. Narula as DW­1 who led his evidence by way of affidavit Ex.DW1/A. DW­1 relied on the following documents:

1.  The   Board   Resolution   dated   07.03.2016   as Ex.D1/1;
CS No.207707/2016 Page No. 15 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

2.  Covering   letter   dated   10.06.2004   from   the plaintiff to Jaiprakash Industries along with RA Bill no. 6, as Ex.D1;

3.  The RA Bill No.6 as Ex.D2;

4.  Copy   of   Foreclosure   &   Settlement   Agreement dated 05.03.2005, already exhibited as Ex.PW1/13;

5.  Copy   of   letter   No.   DCL/Drains/Culverts/45 (2004)   dated   10.05.2004,   already   exhibited   as Ex.PW1/14;

6.  Original   letter   No.   BEBPL/JPDC/01­04/973 dated 02.07.2004 from the plaintiff to the defendants, already exhibited as Ex.PW1/15;

7.  Original   letter   No.   BEBPL/JPDC/01­04/941 dated 03.07.2004 from the plaintiff to the defendants, already exhibited as Ex.PW1/16;

8.  Original   of   Variation   Order   No.1   issued   vide letter   No.   DSC/549   dated   05.07.2004   from   the defendants   to   the   plaintiff,   already   exhibited   as Ex.PW1/17; and

9.  Original   letter   dated   26.05.2005   from defendants   to   plaintiff   and   original   letter   No. BEBPL/DSC/2005­06/1317   dated   06.06.2005   from CS No.207707/2016 Page No. 16 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

the   plaintiff   to   the   defendants,   already   exhibited   as Ex.PW1/20 (colly.).

14.  DW­1   in   his   examination­in­chief   by   way   of   affidavit, deposed on the lines of the written statement.   

15.  During   his   cross   examination,   DW­1   submitted   that running bill No. 6 was duly checked by the defendants and all the bills were taken into consideration while making the final 'settlement agreement' and therefore, he had stated that bill No. 6 had been paid;  that  defendant No.1 had prepared and certified   2   running   bills   Ex.PW1/18   but   the   same   were objected to by the plaintiff vide its letters which was finally settled   in   the   settlement   agreement;  that  the   defendant company had issued TDS  certificate  to the  plaintiff  showing payment of TDS in accordance with law; that it was incorrect that   the   number   of   contract   award   dated   10.05.2004 Ex.PW1/4,   referred   to   as   No.   DSCL/Drains/Culverts/45 (2004)   dated   10.05.2004,   was   to   be   quoted   in   future correspondence between the parties  since the letter of award was   not   accepted   by   the   plaintiff;  that  2   letters   dated 02.07.2004 & 03.07.2004 of the plaintiff confirmed that the CS No.207707/2016 Page No. 17 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

work of drain and box culverts were extra items and the same would be included in the contract of  Palam  Junction flyover, namely S2; and that he was not sure about the contents of the bills. Witness also  denied  that defendants were liable to pay any   bills   or   claims   etc.   after   the   settlement   agreement   of 05.03.2005 & simultaneous issuance of NOC from the plaintiff on   payment   of   settlement   amount   after   signing   of   the settlement agreement. In regard to the question about mention of   contract   No.   DSCL/Drains/Culverts/45   (2004)   dated 10.05.2004   in   the   settlement   agreement   and   no   claim certificate, he replied that he had already said that contract No.   DSCL/Drains/Culverts/45(2004)   dated   10.05.2004   was not accepted by the plaintiff and instead they wrote letters on 2nd  July 2004 and 3rd  July 2004 wherein they had confirmed that   the  drain   and   culvert   works  would   be   treated   as   extra work and included in their contract of Palam Junction flyover namely S­2. 

  No other witness was examined on behalf of the defendants.

CS No.207707/2016 Page No. 18 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

FINAL SUBMISSIONS

16.  I   have   heard   the   arguments   advanced   by   the   Learned counsel for  the  parties and have  carefully gone  through  the record and the evidence adduced by the parties. 

FINDINGS

17.   The issue­wise findings are as under:

ISSUE NO.3 & 4
 3.  Do   the   defendants   prove   that   the   claim   is barred, on  account   of   satisfaction   pertaining   to works executed for drains and culverts, by view of the   Settlement   Agreement   dated   05.03.2005,   and other circumstances, as alleged by them? OPD
4.  Do   the   defendants   prove   that   the   plaintiff waived,   abandoned,   or   surrendered   all   its   claims against   it   under   the   Work   Order   for   drains   and culverts, as alleged? OPD CS No.207707/2016 Page No. 19 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

18.   Since   the   claim   of   the   plaintiff   hinges   entirely   on   the interpretation   of   the  F   &   S   A  and   the   respective  no objections/claim   certificates  issued   by   both   the   parties   after signing of the F & S A, the oral evidence led by the parties is not of much relevance. Infact, even during the course of final submissions, ld. Counsel for the parties argued purely on the interpretation of the F & S A on the basis of the documents on record.   Only   sparing   reference   was   made   to   the   oral testimonies of the witnesses.

19.  In   order   to   understand   the   scope   of  Foreclosure   and Settlement Agreement (F & S A), it needs to be understood that there are 2 parts of the said agreement i.e. (1) foreclosure of the   un­executed   pending   contracts,   and   (2)   settlement agreement. In so far as the foreclosure part of the agreement is concerned, there is no dispute regarding its scope since, vide the  foreclosure  clause,   the   contracts   which   were   yet   to   be performed by  the  plaintiff were  foreclosed  and plaintiff  was discharged from the performance of all works under  all work orders and LOA's issued to it. However, the second part of the agreement which refers to the monetary settlement between CS No.207707/2016 Page No. 20 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

the plaintiff and the defendant, is very broadly worded which takes within its fold, all possible claims of the plaintiff against the defendants.

 

20.  The  crucial   issue  which   requires   detailed   discussion   is whether the work of drains and culverts was an 'extra work' but as a part of the main sub contracts, or whether the said 'extra work' was a completely independent contract and thus beyond the scope of  F & S A? The plaintiff contends that the 'extra work' was an  independent  contract  having no  co­relation  to the contracts S 1 and S 2 whereas the defendants have argued the reversed. It is important to answer this question first since this   has   a   bearing   on   determining   the  intent  of   the   parties while entering into F & S A. In order to answer this question and before discussing the terms of the 'settlement agreement', it   is   imperative   to   briefly   reproduce   certain   principles   of interpretation of contract. 

21.  The   most   basic   principle   is   the   '4   corner   test'   which means that the court will simply look at the contract and if the meaning is clear, will proceed to enforce it without going into the question of whether the bargain was a wise or imprudent CS No.207707/2016 Page No. 21 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

one from the perspective of the complaining party.    The second principle is that the contract should be read and interpreted as a whole. This means the court will consider all the provisions of the contract and not just any one specific provision to resolve an ambiguity.

  Third   principle   is   to   construe   the   contract   in   a reasonable manner. If the court finds an ambiguity, the law states the court should reject an interpretation that would lead to an absurd or harsh result. 

Another important principle of contract interpretation is that   specific   terms   in   a   contract   will   override   general inconsistent language. 

22.  Reverting to the terms of the  F & S A,  the reason for entering into the said agreement was to 'foreclose' all pending work   contacts   which   had   been   awarded   to   the   plaintiff   but which could not be executed due to delays, and to settle the monetary   claims   of   the   plaintiff   with   regard   to   the   work awarded to it. Since the 'settlement' part of the F & S A does not refer to any specific contract but to all  present  and  future claims of the plaintiff against the defendants in respect of all work   awarded   to   the   plaintiff   under   LOA's   and   work CS No.207707/2016 Page No. 22 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

contracts,   a   plain   reading   of   the   said   'Agreement'   makes   it clear   that   the   scope   of   the   settlement   included   'any'   claim which could have been raised against defendant no. 1. As a corollary, it would also include any pending dues in respect of the work of drains and culverts. A detailed discussion in this regard would be necessary to conclusively prove the  intent of the parties at the time of entering into the F & S A.   

23.  A   perusal   of   the   letter   of   contract   dt.   10.6.2004   vide which   the   work   of  drains   and   culverts  was   allotted   to   the defendant   conveys   the   impression   that   the   defendant   no.   1 intended to treat it as a separate contract. However, it was the plaintiff which in clear terms wrote back to defendant no. 1 vide letter dt. 2.7.2004 and 3.7.2004 conveying it to defendant no. 1 that the extra work of  drain and culverts  was an extra item of the main contract of construction of flyover at  Palam junction. Infact, in the letter dt. 3.7.2004, plaintiff repeatedly refers to the terms of contract pertaining to Palam flyover and asserted   that   the   terms   of   the   original   contact   will   be applicable to the work of  construction of  drains and culverts. The relevant references in the letter dt. 3.7.2004 (Ex.PW1/16) are reproduced below:

CS No.207707/2016 Page No. 23 of 36
M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.
"2.  Your Point No.2 We   categorically   and   vehemently   deny   the  contents   of point No. 2 of your letter under reference. At no point of time have ever we accepted the rates as mentioned by you.
We have executed the works of storm drain & culverts as extra item in addition to the works of flyovers, which are being executed by us. Please note that the terms and conditions of our contract with you for Palam Junction Flyover will be applicable for executing the extra items of storm drain and box culverts.
(a)   Works   Contract   Tax   (VAT)   and   other taxes/levies/royalties etc., will be applicable as per our contract with you for Palam flyover.
(c) The   terms   and   conditions   laid   in   the   contract provisions of Palam Junction Flyover contract would be applicable and the same rates would be applicable for fixing of barricades etc. if required.
(g)  The   terms   and   conditions   of   our   contract   for Palam flyover for excavation would be applicable for this work.   However   rate   of   excavation   would   have   to   be derived from our contract, as the cost of mass excavation is cheaper than the cost of trench excavation.
CS No.207707/2016 Page No. 24 of 36

M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

4. Your Point No.4 Specification laid down in our contract of Palam flyover will be followed.

7.  Your Point No.7­ Performance Security:

No   such   security   shall   be   retained   from   our   bills   for carrying out extra items and hence no applicable. The condition of Palam flyover contract will be applicable.

8.  Your Point No.8 With regard to Point No.8 of your letter under reference, terms and conditions of our contract of Palam Flyover would be applicable for this work also.

11.  Your Point No.11 Retention money will be as per our contract of Palam flyover agreement.

12.  Your Point No.12 As the work of drain & box culverts are an extra item the   same   would   be   included   as   an   extra   item   in   our contract of Palam Junction flyover work.

13.  Your Point No.13 CS No.207707/2016 Page No. 25 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

Step in Right of NHAI­ The terms and conditions as per contract of Palam flyover with you would be applicable.

14.  Your Point No.14 As we have a contract for Palam Junction Flyover and we are executing the storm drain and box culverts as an extra item, hence your Point No.14 is not applicable."

Perusal of reply given by plaintiff in response to item no. 12 makes it patent that plaintiff was clear that the work of drains and culverts was to be treated as an extra work but as a part of the work of construction of flyover at Palam junction.

24.  Not   only   this,   in   the   letter   dated   2.7.2004,   plaintiff categorically   admits   (rather   asserts)   that   the   extra   work   of construction   of  drains   and   culverts  was   a   part   of   the   main contract.   The   relevant   part   of   the   letter   dt.   2.7.2004   is reproduced below:

"To avoid some of our manpower from remaining idle   you   had   requested   us   to   execute   the   item   of storm   drain   and   box   culverts  as   part   of   our contract, till the work of the flyover resumes.
CS No.207707/2016 Page No. 26 of 36
M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.
......
We would also like to inform and confirm to you that   as   these   are   extra   items   the   terms   and conditions of our original contract with you would be applicable and no new terms and conditions are applicable or acceptable."

25.  It is thus clear that plaintiff itself treated the extra work of  drains   and   culverts  to   be   a   part   of   the   main   contract   of construction of flyover at Palam junction. That being so, it can be safely assumed that the while entering into F & S A, there was clear intent on both the sides, and more so from the side of   the   plaintiff   that   the   settlement   is   being   entered   into   in respect of all its claims including the work of construction of drains and culverts. Any doubt in this regard is set to rest by looking at the no claim/ satisfaction certificate issued by the plaintiff which was executed on the same day as the F & S A was signed. The opening para of this certificate makes it amply clear that plaintiff had clear intent of settling all the matters with defendant no. 1 and settlement was not just restricted to contract packages S 1 and S 2. The relevant part of the said certificate is reproduced below :    

CS No.207707/2016 Page No. 27 of 36
M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.
"This is  to  certify    that  we the undersigned have amicably   settled   all   our   disputes,   differences   and claims   of   any   nature   whatsoever,   in   present   or future, whether or not claimed as yet, against (i) M/s D. S. Constructions Ltd (DSC for brevity), (ii) M/s   Jaypee   DSC   Ventures   Limited   (JPDSC   for brevity) and (iii) M/s Jaiprakash Industries ltd (JIL for   brevity)   arising   out   of   and   in   respect   of   the Work   for   Package   No.S1   &   S2,   various   Work Orders   issued   in   our   favour   and  other   works done, relating to the conversion of Delhi­Gurgaon Section   of   NH­8   (from   KM   14.30   to   KM   42.00) into   Access   Controlled   8/6   Lane   Highway.   The mutually agreed terms thereof have been reduced in writing under the Settlement Agreement dated 05 th March 2005."

26.  Use of expansive language in the 'settlement' part of the F&SA could only have been a result of the clear contemplation in the mind of plaintiff and defendant no.1 that after settling the matter, plaintiff should not be able to/ permitted to come up with any residuary claim in respect of the contacts S1 & S 2 CS No.207707/2016 Page No. 28 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

or any other claim in respect of any other work awarded to it.  To put it in textbook manner, the parties were  ad idem  in respect of settling all their pending claims including the work of construction of drains and culverts.

27.  Merely because a separate contract number was awarded to the work of drains and culverts which was to be referred to in all future communications between the parties, is no ground to hold that it was an independent contract especially keeping in mind the plaintiff's own conduct in asserting and admitting that the work of drains and culverts was a part of the main contract   of   construction   of   Palam   flyover.   There   is   no document to show that after the plaintiff wrote the letters dt. 2.7.2004   and   3.7.2004   to   defendant   no.   1,   there   was   any revert from defendant no. 1 which could prove that the work of  drains   and   culverts  was   to   be   treated   as   an   independent contract.

28.                      Ld.   Counsel   for   the   plaintiff   appears   to   have misconstrued   the   true   intent   and   scope   of   the   'Settlement Agreement'.   Ld.   Counsel   highlighted   the   initial   paras   of   the said 'Agreement' wherein reference has been made to contract CS No.207707/2016 Page No. 29 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

S1 and S2. A careful perusal of the 'Agreement' would show that the above­said reference to contract S1 and S2 was merely to   give   a   factual   background   to   the   'Agreement'   which   was being entered into so that the relationship status amongst the parties was clear.  Subsequent  paragraphs of the  'Agreement' make   it   clear   that   the   scope   of   the   'Agreement'   stretched beyond  the  contracts S1 & S2 and covered all  works which were awarded to the plaintiff.  

29.                       A supplementary argument was raised on behalf of   the   plaintiff   contending   that   since   defendant   no.1   had issued separate TDS certificates in respect of the bills raised for the work of construction of drains and culverts, the said work was   treated   as   a   separate   contract   by   defendant   no.1.   The Court   is  unable   to   be   persuaded   with   this  contention.   First, there is no dispute that plaintiff had to be paid additionally for this extra work. Consequently, for bills raised in respect of this extra work, defendant no.1 issued separate TDS certificates in accordance with the bills raised. Second, in the RA bill no. 6, plaintiff did not raise any separate Bill for the work of drains and culverts and submitted it as a part of the bill for the work of flyovers which shows that previous raising of separate bills CS No.207707/2016 Page No. 30 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

was  nothing  significant,   with   the   plaintiff  itself   merging  the bills   for   the   work   of   construction   of   flyovers   and   work   of construction of drains and culverts in a single Bill.   

30.  On behalf of defendants, another relevant fact has been highlighted.   Plaintiff   had   included   the   claim   of   this   'extra work' along with the claim of contracts S1 and S2 for certain bills. The said bills were exhibited as Ex.D 2 (colly.). These running bills also show that plaintiff treated this extra work as a part of the work of construction of flyover at Palam which is clear from the heading on each page of the running Bill. While including   the   claim   for   this   'extra   work',  plaintiff   has   not referred to the separate contract number which was allotted vide   Award   letter   dt.   10.6.2004   and   which   the   plaintiff claimed   was   to   be   quoted   in   all   future   correspondences between the parties. It is reasonable to assume that a separate number  was  given  to  the  contract for  construction  of  storm drains   and   box   culverts  which   appears   to   be   only   for   the purpose of identification that a specific work was allotted to the plaintiff. Nothing more can be read into this, especially in view  of  the  detailed  discussion   above.  As  a  corollary  to  the above discussion, it is held that Plaintiff had no cause of action CS No.207707/2016 Page No. 31 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

to submit the bill dt. 9.5.2005 after the signing of F & S A with defendant no. 1. Consequently, both these issues are decided in favour of the defendants and against the plaintiff.

ISSUE NO.2 Does   the   plaintiff   prove   that   the   contract   dated 10.05.2004 awarded by the defendants, for construction of   drains   and   culverts   was   duly   performed   and   is, therefore,   entitled   to   the   amount   claimed,   i.e. Rs.50,57,658/­, or any part thereof? OPP

31.  There   is   no   dispute   regarding   the   completion   of   the work of drains and culverts by the plaintiff. The only dispute is whether plaintiff is entitled to recover the suit amount which it claims   to   be   pending   in   respect   of   the   contract   letter   dt. 10.5.2004. In view of the findings returned under issue no 3 and 4, it is held that plaintiff is not entitled to recover the suit amount from the defendants.  

ISSUE NO.1 CS No.207707/2016 Page No. 32 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

Is the suit time­barred? OPD

32.  In view of the finding returned on issues no. 2 to 4, this issue does not really require a finding since it has been held that plaintiff had no cause of action to file the present suit. However,   even   assuming   that   plaintiff   did   have   a   cause   of action,   the   suit   claim   was   barred   by   limitation,   for   the following   reasons.   It   is   not   in   dispute   that   the   work   of constructions of storm drains & box culverts was completed and handed over to the NHAI by 30.8.2004. Prior to this, plaintiff had raised 2 running bills which were purportedly cleared by the defendants. The 3rd and final bill however, was submitted on   09.05.2005.   Perusal   of   the   cross   examination   of   PW   1 (which has been highlighted above while discussing evidence of the plaintiff) reveals a clear admission by the witness to the effect   that   the   amount   payable   for   the   work   of  drains   and culverts  which was completed on 30.8.2004, became due on 30.9.2004.  The   period  of  limitation  to  seek recovery  on  the basis of a contractual obligation for a work done is 3 years from the date on which the work is done i.e. as per article 18 of   the  Schedule  of   the   Limitation   Act.   Since   the   work   was handed over  to  defendant no.  1 by  30.8.2004,  the  cause   of action   for   the   plaintiff   to   seek   its   dues   naturally   arose   on CS No.207707/2016 Page No. 33 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

30.8.2004   itself.   Even   going   by   the   testimony   of   PW1,   the amount   recoverable   from   defendant   no.1   for   the   work   of constructing  drain   and   culverts  became   due   on   30.9.2004. Thus, at best, the period of limitation to enforce the monetary liability   against   defendant   no.   1   started   to   run   from   the following   day   i.e.   1.10.2004.   There   is   no   explanation forthcoming from the side of the plaintiff with regard to the delay   in   submitting   the   final   bill   after   a   gap   of   almost   8 months from the date of handing over the possession of the completed work to defendant no. 1. Plaintiff has computed the date of accrual of cause of action from the date that the final bill   was   submitted  but  which   computation   is   incorrect.   The plaintiff   could   not   have   possibly   extended   the   period   for limitation by late submission of the bill in question. Period of limitation,   which  once  begins   to  run,  does   not   stop  for   any reason except in case of legal disability. That is the most basic principle   of   the   law   of   limitation.   There   is   thus   nothing   to show that the terms of the allotted work gave the liberty to the plaintiff   to   seek   recovery   of   its   dues   after   expiry   of   an uncertain period irrespective of the commencement of period of   limitation   i.e.  as worked   out  from   the   date   of   accrual  of cause of action, as per statutory law. It is thus clear that even CS No.207707/2016 Page No. 34 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

going by the testimony of PW 1, the cause of action for the plaintiff to seek recovery of its dues arose on 30.9.2004 and consequently, the period of limitation to enforce the monetary liability against the defendants started to run from 1.10.2004. Period of 3 years expired on 30.9.2007 whereas the present suit was filed on 23.5.2008, making the institution of the suit clearly barred due to expiry of limitation period. This issue is thus decided against the plaintiff.  

ISSUE NO.5 Is the plaintiff entitled to interest on any amount decreed; if so, at what rate and for what period?

33.  Since the plaintiff has been held to be 'not entitled'  to recover the suit amount, there is no question of computing the rate   of   interest.   This   issue   thus   does   not   require   to   be adjudicated.

RELIEF

34.  In view of the findings returned under issue no. 1 to 4, CS No.207707/2016 Page No. 35 of 36 M/s Bhandari Engineers and Builders Pvt Ltd. vs. M/s D. S. Constructions Ltd. & Anr.

the suit of the  plaintiff is dismissed. Parties are  left to bear their   own   costs.   Decree   sheet   be   prepared   accordingly. Thereafter, file be consigned to the record room.

ANNOUNCED IN THE OPEN                (AJAY GULATI)
COURT ON 27.10.2018                ADDL. DISTRICT JUDGE­02
                               SOUTH, SAKET COURTS, NEW DELHI




CS No.207707/2016                                                              Page No. 36 of 36