Section 99 in West Bengal Municipal (Building) Rules, 2007

99. Deviation during construction.

— If during construction of a building any departure or deviation from the sanctioned plan is intended to be made, sanction of the Authority shall be obtained before the change is made. The revised plan showing the deviation shall be submitted and the procedure laid down for the original plan therefor shall apply to all such amended plans. If on inspection during the construction stage, it is detected that deviation from the sanctioned plans have been made, the applications for the revised plan may not be entertained and the clearance certificate as mentioned in clause (a) of sub-rule (3) of rule 151 will not be issued in respect of the water and sewerage connections till rectification of the deviations.