Supreme Court of India

State Of Madras vs K. N. Shanmugha Mudallar & Ors on 4 March, 1976

Equivalent citations: 1976 AIR 1057, 1976 SCR (3) 536, AIR 1976 SUPREME COURT 1057, 1976 2 SCC 406, 1976 3 SCR 536, 1976 (1) SCJ 429, 1976 UJ (SC) 284

Author: Hans Raj Khanna

Bench: Hans Raj Khanna, P.K. Goswami

           PETITIONER:
STATE OF MADRAS

	Vs.

RESPONDENT:
K. N. SHANMUGHA MUDALLAR & ORS.

DATE OF JUDGMENT04/03/1976

BENCH:
KHANNA, HANS RAJ
BENCH:
KHANNA, HANS RAJ
GOSWAMI, P.K.

CITATION:
 1976 AIR 1057		  1976 SCR  (3) 536
 1976 SCC  (2) 406


ACT:
     Land Acquisition  Act, 1894-Sections  23 and 24 Quantum
of compensation	 -Madras Estates Abolition Act, 1948-Whether
compensation under  Land   Acquisition Act can be claimed if
the estate  is	abolished-Interest  of	compensation  to  be
allowed, from what date.



HEADNOTE:
     The State	of Madras  acquired land  belonging  to	 the
respondent landlords.  The Land Acquisition officer gave his
award determining  the compensation  payable. On a reference
made to	 the Subordinate  judge certain	 compensation	 was
determined. Interest  was awarded  to the respondents on the
compensation amount  from 1st  December, 1949 because in the
opinion of  the Subordinate   Judge,  possession of the land
had been taken on that date.
     On an  appeal, the	 High Court affirmed the decision of
the Subordinate	 Judge	 regarding the rate of compensation.
The High Court also rejected the contention of the appellant
that the  land had vested in the Government under the Madras
States Abolition  Act, 1948, and, therefore, the respondents
were not entitled to compensation under the Land Acquisition
Act. The  High Court  found that  there was  no material  on
record to  show that  the possession  of the  land had	been
taken prior to the date of the award by the Land Acquisition
officer. Interest  was accordingly  directed to run from the
date of the award, i.e. November, 1951.
     In an appeal by certificate, the appellant contended:
	  (1)  The  land   in  question	  vested  under	 the
	       Abolition  Act	in   the   State   and	 the
	       respondents were,  therefore, not entitled to
	       compensation under the Land Acquisition Act.
	  (2)  The quantum  of compensation  awarded by	 the
	       High Court was excessive.
	  (3)  Interest should	have been  allowed from	 1st
	       December, 1949.
^
     HELD: (  1 )  There were . two alternative courses open
to the	State either  to proceed  under the Land Acquisition
Act or	to take	 over the  land	 under	the  Abolition	Act.
Although the  estate was  notified under  the Abolition Act,
the proceedings	 under that  Act were  stayed and the matter
proceed l under the Land Acquisition Act. It was not open to
the appellant  in  the	particular  reference  made  at	 the
instance of  the respondents to the Subordinate Judge to set
up a  claim adverse  to the interest of the respondents. The
High Court  rightly rejected the contention of the appellant
in this behalf. [538D-E, G-H]
     (2 )  Both the  High Court	 as well  as the Subordinate
Judge  awarded	the  compensation  in  accordance  with	 the
previous decisions  which laid	down a	formula.  No  cogent
grounds	 have  been  shown  to	us  to	interfere  with	 the
concurrent findings in this respect. [539B-C]
     (3) There	is no reason to disagree with the High Court
judgment regarding the date on which the interest should run
on the amount of compensation. [539-G]



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1425 of 1968.

From the Judgment and Decree dated the 5-8-74 of the Madras High Court in Appeal No. 448 of 1960.

A. V. Rangam and Miss A. Subhashini for the Appellant. K. Jayaram and R. Chandresekhar for Respondent No. 1 Ex-parte for Respondents 2-8.

537

The Judgment of the Court was delivered by KHANNA, J. This appeal on certificate is by the State of Madras, now Tamil Nadu, against the judgment of Madras High Court affirming on appeal the award of learned Subordinate judge Salem in respect of the amount of compensation payable to the respondents for acquisition of land under the Land Acquisition Act (Act 1 of 1894) (hereinafter referred to as the Act). The High Court, however, directed that the interest on the amount awarded shall run from November 19, 1951, the date of the award by the Land Acquisition officer and not from December 1, 1949 as ordered by the Subordinate Judge.

On July 12, 1949 notification under section 4 of the Act was issued for`the acquisition of 19 acres 45 cents of dry land situated in Alegapuram Mitta for the Salem Fair Lands Co-operative Society Ltd. On December 19, 1950. Alegapuram Mitta was notified under the Madras Estates Abolition Act (Act 26 of 1948) (hereinafter referred to as the Abolition Act). A writ petition was filed in the High Court to challenge that notification. Further proceedings in pursuance of the notification were stayed by the High Court by order dated January. 1, 1951. The Society for which acquisition was being made deposited in the meantime the probable cost of the land on September 13, 1950. On, November 19, 1951 the Land Acquisition officer announced his award.

The respondents, it may be stated, were the Melevaramdars (land holders) of the land in question. Kudiwaramdars (cultivators) were also, besides the respondents, parties to the proceedings before the Land Acquisition officer. The Land Acquisition officer by his award dated November 19, 1951 awarded compensation to the cultivators at the rate of Rs. 1,500 per acre for part of the land near the road and at the rate of Rs. 1,300 per acre for the rest of the land. Rs. 520, 11 As, 1 P the capitalised value of the net rental income was held to be the amount payable to the respondents. The Kudiwaramdars were content with the compensation awarded to them, but the respondents who were, as already mentioned above, Melavaramdars asked for a reference to court under section 18 of the Act for claiming enhanced compensation. According to the respondents, they were entitled to one-third of the value of the totality of the interest in the land. According further to the respondents, compensation for the total land should be awarded at the rate of Rs. 3,000 per acre Learned Subordinate Judge held that the respondents were entitled to 50 percent of the compensation awarded in respect of the Melawaram interest in the land. The Subordinate Judge in this context relied r upon an earlier decision of the Madras High Court wherein it had been held that the rights of Melavaramdars were not confined only to rent from land and that they had other recognised rights and were entitled to compensation for those rights. The respondents were thus held entitled to compensation for their Melavaramdar interest at the rate of Rs. 750 per acre in respect of land near the road and Rs. 650 per acre in respect of the remaining land. Interest was awarded to the respondents on the compensation amount from December 1, 1949 2-608SCI/76 538 because, in the opinion of the Subordinate Judge, possession of the land had been taken from that date.

On appeal the High Court affirmed the decision of the Subordinate Judge regarding the rate of compensation. The contention advanced on behalf of the appellant that as the land had vested in the Government under the Abolition Act, the respondents were not entitled to compensation under the Land Acquisition Act, was rejected. It was observed that in the land acquisition proceedings the Government was estopped from denying the absence of any interest in the claimants whom the Government had made parties to the proceedings. Regarding the date from which interest on the amount or compensation should accrue, the High Court found that there was no material on the record to show that possession of the land had been taken prior to the date of the award by the Land Acquisition officer. Interest was accordingly directed to run from the date of the award.

In appeal before us Mr. Rangam on behalf of the appellant-state has urged that as the land in question has vested under the Abolition Act in the State the respondents are not entitled to compensation under the Land Acquisition Act. We find it difficult to accede to this submission, for we are of the opinion that in case the State wanted to take over the land under the Abolition Act it should not have proceeded to acquire the interest of the respondents in the land in dispute under the Land Acquisition Act. There were two alternative courses open to the State, either to proceed under the Land Acquisition Act or to take over the land under the Abolition Act. Although the estate was notified under the Abolition Act, the proceedings under that Act were stayed and the matter proceeded under the Land Acquisition Act. As the proceedings which were continued were under the Land Acquisition Act the compensation payable had also to be paid in accordance with the provisions of that Act. The reference which was made by the Land Acquisition officer to the Subordinate Judge under section 18 of the Land Acquisition Act was with respect to the quantum of compensation payable to the respondents because the respondents had felt dissatisfied with the amount awarded to them as compensation by the said officer. The underlying assumption of those proceedings was that the respondents had an interest in the land. If it was the case of the appellant that the respondents had been divested of their interest in the land and the same had vested in the appellant State, the appellant should have taken appropriate steps to make such a claim in accordance with law. No such claim seems to have been made. The High Court expressly left open the question of the claim of the State Government to the amount of compensation deposited on the score that Melwaramdar respondents were not entitled to it by reason of having lost all their interest in the land at the relevant point of time. We agree with the High Court that it was not open to the appellant-State in the particular reference made at the instance of the respondents to the Subordinate Judge to set up a claim adverse to the interest of the respondents. There is also we find nothing in the award of the learned Subordinate Judge to show that any question was raised before him that the amount of compensation was not payable to the 539 respondents in accordance with the provisions of the Land Acquisition Act. This question appears to have been agitated for the first time only in the appeal before the High Court. The High Court rejected the contention in this behalf. We find no cogent ground to take a different view.

As regards the quantum of compensation, the High Court has referred to the previous decisions which show that the formula gene- rally adopted is to pay one-third of the total compensation to Melavaramdars and two-thirds of the compensation to Kudiwaramdars. In accordance with that formula, the respondents would be entitled to one-half of the compensation payable to Kudiwaramdars. Both the Subordinate Judge and the High Court awarded compensation in accordance with this formula. No cogent ground has been shown to us as to why we should interfere with the concurrent finding in this respect. We also find no reason to disagree with the High Court regarding the date from which interest should run on the amount of compensation.

The appeal fails and is dismissed with costs. P.H.P. Appeal dismissed.