85. Preparatory works before commissioning of pipelines.

- The owner, agent and manager of a mine shall, before the commencement of the commissioning activities of pipelines, ensure that-
(a)commissioning procedure is in place;
(b)pressure testing is completed for entire pipeline and associated station piping;
(c)pressure leak check of the above ground piping and flanged joints is completed;
(d)pipeline has been cleaned and debris has been removed;
(e)mainline sectionalising valves are installed as per requirement;
(f)all Golden joints are inspected and accepted;
(g)geometric survey of pipeline section is carried out, if applicable; and
(h)trained and experienced officials in adequate numbers are appointed for supervision of commissioning work of pipelines.