Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 22, Cited by 0]

Custom, Excise & Service Tax Tribunal

Moser Baer India Ltd vs Ce & Cgst Noida on 5 April, 2024

CUSTOMS, EXCISE & SERVICE TAX APPELLATE TRIBUNAL
                  ALLAHABAD

                  REGIONAL BENCH - COURT NO.I

                 Excise Appeal No.2679 of 2011

(Arising out of Order-in-Appeal No.215/CE/APPL/Noida/2011/983 dated
28/09/2011 passed by Commissioner (Appeals) Customs, Central Excise &
Service Tax, Noida)

M/s Moser Baer India Ltd.,                          .....Appellant
(A-164, Sector-80, Phase-II, Noida)
                                  VERSUS

Commissioner of Central Excise, Noida                ....Respondent

(C-56/42, Sector-62, Noida) APPEARANCE:

Absent on call, for the Appellant Shri Sandeep Pandey, Authorised Representative for the Respondent CORAM: HON'BLE MR. P.K. CHOUDHARY, MEMBER (JUDICIAL) HON'BLE MR. SANJIV SRIVASTAVA, MEMBER (TECHNICAL) FINAL ORDER NO.70171/2024 DATE OF HEARING : 17 January, 2024 DATE OF PRONOUNCEMENT : 05 April, 2024 SANJIV SRIVASTAVA:
This appeal is directed against the order in appeal No 215/CE/APPL/NOIDA/2011/983 dated 28.09.2011 of the Commissioner (Appeal) Customs, Central Excise and Service Tax, Noida. By the impugned order, following has been held:
"I hereby uphold the confirmation of demand of duty of Rs 35,183/- along with interest of Rs 3833/-, however I set aside the imposition of penalty upon the appellant."

2.0 Deputy registrar (J) has vide his letter dated 16.01.2018, informed as follows:

"Please find enclosed herewith a copy of letter dated 06.01.2018 of Shri Devendra Singh, Resolution 2 Excise Appeal No.2679 of 2011 Professional of Moser Baer India (Ltd. (MBIL) along with the copy of judgment dated 14.11.2017 passed by the Hon‟ble NCLT in C P No IB-378 (PB)/2017.
In the said letter the resolution professional has intimated this Tribunal regarding the commencement of Corporate Insolvency Resolution Process (CIRP) under the provisions of IBC, 2016 in the matter of Moser Baer India Limited.
In view of this all the concerned are hereby requested to place this letter alongwith order of Hon‟ble NCLT before respective Bench of your Tribunal in the appeal cases of Moser Baer India Ltd. pending before your tribunal/ bench for further necessary action."

3.0 In para 8, of the letter dated 06.01.2018, Shri Devendra Singh has stated as follows:

"8. In view of above, I, being Resolution Professional appointed by Hon‟ble NCLT, Principal Bench, New Delhi, advise you not to take/ continue with any recovery action against MBIL, as the same shall be in violation of the provisions of Section 14 of IBC, 2016 and also against the order passed by Hon‟ble NCLT, Principal Bench, New Delhi, dated 14.11.2017. In case you still proceed with any action against MBIL, you make yourself liable for penal action as per section 74 (2) of IBC, 2016."

4.0 In case of Ghanshyam Mishra [(2021) 9 SCC 657], Hon'ble Supreme Court held as follows:

"2. The short but important questions, that arise for consideration in this batch of matters, are as under:-
(i) As to whether any creditor including the Central Government, State Government or any local authority is bound by the Resolution Plan once it is approved by an adjudicating authority under sub-section (1) of Section 31 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as „I&B Code‟)?
                                            3                        Excise Appeal No.2679 of 2011



   (ii)    As to whether the amendment to Section 31                                          by
           Section      7    of     Act        26        of    2019           is clarificatory/
           declaratory or substantive                    in nature?
   (iii)   As to whether after approval of resolution plan                                    by
           the    Adjudicating           Authority            a creditor including the
Central Government, State Government or any local authority is entitled to initiate any proceedings for recovery of any of the dues from the Corporate Debtor, which are not a part of the Resolution Plan approved by the adjudicating authority?

49. The provisions of I&B Code have undergone scrutiny in various judgments of this Court. We would not like to burden the present judgment with the provisions of the statute, which have been duly reproduced and considered in the earlier judgments of this Court.

50. In the case of Innoventive Industries Ltd. vs. ICICI Bank & Anr.[ (2018) 1 SCC 407] after reproducing the „Statement of Objects and Reasons‟ of I&B Code in paragraph 12, this Court observed thus:

"13. One of the important objectives of the Code is to bring the insolvency law in India under a single unified umbrella with the object of speeding up of the insolvency process. As per the data available with the World Bank in 2016, insolvency resolution in India took 4.3 years on an average, which was much higher when compared with the United Kingdom (1 year), USA (1.5 years) and South Africa (2 years). The World Bank's Ease of Doing Business Index, 2015, ranked India as country number 135 out of 190 countries on the ease of resolving insolvency based on various indicia." [emphasis supplied]

51. This Court thereafter in paragraph 16 reproduced the relevant paragraphs contained in the report of the Bankruptcy Law Reforms Committee Report of 2015.

4 Excise Appeal No.2679 of 2011

Thereafter, this Court reproduced all the relevant provisions of I&B Code in paragraphs 18 to 26. 52. This Court in the case of Innoventive Industries Ltd. (supra) thereafter elaborately discussed the scheme of the various provisions of the I&B Code in paragraphs 27 to 32, which read thus:

"27. The scheme of the Code is to ensure that when a default takes place, in the sense that a debt becomes due and is not paid, the insolvency resolution process begins. Default is defined in Section 3(12) in very wide terms as meaning non-payment of a debt once it becomes due and payable, which includes non-payment of even part thereof or an instalment amount. For the meaning of "debt", we have to go to Section 3(11), which in turn tells us that a debt means a liability of obligation in respect of a "claim" and for the meaning of "claim", we have to go back to Section 3(6) which defines "claim" to mean a right to payment even if it is disputed. The Code gets triggered the moment default is of rupees one lakh or more (Section 4). The corporate insolvency resolution process may be triggered by the corporate debtor itself or a financial creditor or operational creditor. A distinction is made by the Code between debts owed to financial creditors and operational creditors. A financial creditor has been defined under Section 5(7) as a person to whom a financial debt is owed and a financial debt is defined in Section 5(8) to mean a debt which is disbursed against consideration for the time value of money. As opposed to this, an operational creditor means a person to whom an operational debt is owed and an operational debt under Section 5(21) means a claim in respect of provision of goods or services.
28. When it comes to a financial creditor triggering the process, Section 7 becomes relevant. Under the Explanation to Section 7(1), a default is in respect of a financial debt owed to any financial creditor of the corporate debtor -- it 5 Excise Appeal No.2679 of 2011 need not be a debt owed to the applicant financial creditor. Under Section 7(2), an application is to be made under sub-section (1) in such form and manner as is prescribed, which takes us to the Insolvency and Bankruptcy (Application to Adjudicating Authority) Rules, 2016. Under Rule 4, the application is made by a fi- nancial creditor in Form 1 accompanied by documents and records required therein. Form 1 is a detailed form in 5 parts, which requires particulars of the applicant in Part I, particulars of the corporate debtor in Part II, particulars of the proposed interim resolution professional in Part III, particulars of the financial debt in Part IV and documents, records and evidence of default in Part V. Under Rule 4(3), the applicant is to dispatch a copy of the application filed with the adjudicating authority by registered post or speed post to the registered office of the corporate debtor. The speed, within which the adjudicating authority is to ascertain the existence of a default from the records of the information utility or on the basis of evidence furnished by the financial creditor, is important. This it must do within 14 days of the receipt of the application. It is at the stage of Section 7(5), where the adjudicating authority is to be satisfied that a default has occurred, that the corporate debtor is entitled to point out that a default has not occurred in the sense that the "debt", which may also include a disputed claim, is not due. A debt may not be due if it is not payable in law or in fact. The moment the adjudicating authority is satisfied that a default has occurred, the application must be admitted unless it is incomplete, in which case it may give notice to the applicant to rectify the defect within 7 days of receipt of a notice from the adjudicating authority. Under sub-section (7), the adjudicating authority shall then communicate the order passed to the financial creditor and corporate debtor within 7 days of admission or rejection of such application, as the case may be.
6 Excise Appeal No.2679 of 2011
29. The scheme of Section 7 stands in contrast with the scheme under Section 8 where an operational creditor is, on the occurrence of a default, to first deliver a demand notice of the unpaid debt to the operational debtor in the manner provided in Section 8(1) of the Code. Under Section 8(2), the corporate debtor can, within a period of 10 days of receipt of the demand notice or copy of the invoice mentioned in sub-section (1), bring to the notice of the operational creditor the existence of a dispute or the record of the pendency of a suit or arbitration proceedings, which is pre-existing--i.e. before such notice or invoice was received by the corporate debtor. The moment there is existence of such a dispute, the operational creditor gets out of the clutches of the Code.
30. On the other hand, as we have seen, in the case of a corporate debtor who commits a default of a financial debt, the adjudicating authority has merely to see the records of the information utility or other evidence produced by the financial creditor to satisfy itself that a default has occurred. It is of no matter that the debt is disputed so long as the debt is "due" i.e. payable unless interdicted by some law or has not yet become due in the sense that it is payable at some future date. It is only when this is proved to the satisfaction of the adjudicating authority that the adjudicating authority may reject an application and not otherwise.
31. The rest of the insolvency resolution process is also very important. The entire process is to be completed within a period of 180 days from the date of admission of the application under Section 12 and can only be extended beyond 180 days for a further period of not exceeding 90 days if the committee of creditors by a voting of 75% of voting shares so decides. It can be seen that time is of essence in seeing whether the corporate body can be put back on its feet, so as to stave off liquidation.
7 Excise Appeal No.2679 of 2011
32. As soon as the application is admitted, a moratorium in terms of Section 14 of the Code is to be declared by the adjudicating authority and a public announcement is made stating, inter alia, the last date for submission of claims and the details of the interim resolution professional who shall be vested with the management of the corporate debtor and be responsible for receiving claims. Under Section 17, the erstwhile management of the corporate debtor is vested in an interim resolution professional who is a trained person registered under Chapter IV of the Code. This interim resolution professional is now to manage the operations of the corporate debtor as a going concern under the directions of a committee of creditors appointed under Section 21 of the Act. Decisions by this committee are to be taken by a vote of not less than 75% of the voting share of the financial creditors. Under Section 28, a resolution professional, who is none other than an interim resolution professional who is appointed to carry out the resolution process, is then given wide powers to raise finances, create security interests, etc. subject to prior approval of the committee of creditors."

[emphasis supplied]

53. After discussing the relevant provisions of I&B Code, this Court observed thus:

"33. Under Section 30, any person who is interested in putting the corporate body back on its feet may submit a resolution plan to the resolution professional, which is prepared on the basis of an information memorandum. This plan must provide for payment of insolvency resolution process costs, management of the affairs of the corporate debtor after approval of the plan, and implementation and supervi- sion of the plan. It is only when such plan is approved by a vote of not less than 75% of the voting share of the financial creditors and the adjudicating authority is satisfied that the plan, as 8 Excise Appeal No.2679 of 2011 approved, meets the statutory requirements mentioned in Section 30, that it ultimately approves such plan, which is then binding on the corporate debtor as well as its employees, members, creditors, guarantors and other stakeholders. Importantly, and this is a major departure from previous legislation on the subject, the moment the adjudicating authority approves the resolution plan, the moratorium order passed by the authority under Section 14 shall cease to have effect. The scheme of the Code, therefore, is to make an attempt, by divesting the erstwhile management of its powers and vesting it in a professional agency, to continue the business of the corporate body as a going concern until a resolution plan is drawn up, in which event the management is handed over under the plan so that the corporate body is able to pay back its debts and get back on its feet. All this is to be done within a period of 6 months with a maximum extension of another 90 days or else the chopper comes down and the liquidation process begins." [emphasis supplied]

54. It could thus be seen, that one of the dominant objects of I&B Code is to see to it, that an attempt has to be made to revive the Corporate Debtor and make it a running concern. For that, a resolution applicant has to prepare a resolution plan on the basis of the Information Memorandum. The Information Memorandum, which is required to be prepared in accordance with Section 29 of I&B Code along with Regulation 36 of the Regulations, is required to contain various details, which have been gathered by RP after receipt of various claims in response to the statutorily mandated public notice. The resolution plan is required to provide for the payment of insolvency resolution process costs, management of the affairs of the Corporate Debtor after approval of the resolution plan; the implementation and supervision of the resolution plan. It is only after the Adjudicating Authority satisfies itself, that the plan as approved by CoC with the requisite voting share of 9 Excise Appeal No.2679 of 2011 financial creditors meets the requirement as referred to in sub-section (2) of Section 30, grants its approval to it. It is only thereafter, that the said plan is binding on the Corporate Debtor as well as its employees, members, creditors, guarantors and other stakeholders involved in the resolution Plan. The moratorium order passed by the Adjudicating Authority under Section 14 shall cease to operate, once the Adjudicating Authority approves the resolution plan. The scheme of I&B Code therefore is, to make an attempt, by divesting the erstwhile management of its powers and vesting it in a professional agency, to continue the business of the Corporate Debtor as a going concern until a resolution plan is drawn up. Once the resolution plan is approved, the management is handed over under the plan to the successful applicant so that the Corporate Debtor is able to pay back its debts and get back on its feet.

55. This Court recently in the case of Kalpraj Dharamshi and another vs. Kotak Investment Advisors Ltd. and another (supra) has, in detail, considered the provisions of Sections 30 and 31 of I&B Code, the Bankruptcy Law Reforms Committee (BLRC) Report of 2015 and the judgments of this Court in the case K. Sashidhar (supra), Committee of Creditors of Essar Steel India Limited through Authorised Signatory vs. Satish Kumar Gupta & Ors. (supra) and Maharashtra Seamless Limited vs. Padmanabhan Venkatesh and others (supra) and observed thus:

"139. It is thus clear, that the Committee was of the view, that for deciding key economic question in the bankruptcy process, the only one correct forum for evaluating such possibilities, and making a decision was, a creditors committee, wherein all financial creditors have votes in proportion to the magnitude of debt that they hold. The BLRC has observed, that laws in India in the past have brought arms of the Government (legislature, executive or judiciary) into the question 10 Excise Appeal No.2679 of 2011 of bankruptcy process. This has been strictly avoided by the Committee and it has been provided, that the decision with regard to appropriate disposition of a defaulting firm, which is a business decision, should only be made by the creditors. It has been observed, that the evaluation of proposals to keep the entity as a going concern, including decisions about the sale of business or units, restructuring of debt, etc., are required to be taken by the Committee of the Financial Creditors. It has been provided, that the choice of the solution to keep the entity as a going concern will be voted upon by CoC and there are no constraints on the proposals that the resolution professional can present to CoC. The requirements, that the resolution professional needs to confirm to the Adjudicator, are:
(i) that the solution must explicitly require the repayment of any interim finance and costs of the insolvency resolution process will be paid in priority to other payments;
(ii) that the plan must explicitly include payment to all creditors not on the creditors committee, within a reasonable period after the solution is implemented; and lastly
(iii) the plan should comply with existing laws governing the actions of the entity while implementing the solutions.

140. The Committee also expressed the opinion, that there should be freedom permitted to the overall market, to propose solutions on keeping the entity as a going concern. The Committee opined, that the details as to how the insolvency is to be resolved or as to how the entity is to be revived, or the debt is to be restructured will not be provided in the I&B Code but such a decision will come 11 Excise Appeal No.2679 of 2011 from the deliberations of CoC in response to the solutions proposed by the market.

141. This Court in the case of K. Sashidhar (supra) observed thus:

"32. Having heard the learned counsel for the parties, the moot question is about the sequel of the approval of the resolution plan by CoC of the respective corporate debtor, namely, KS&PIPL and IIL, by a vote of less than seventy-five per cent of voting share of the financial creditors; and about the correctness of the view taken by NCLAT that the percentage of voting share of the financial creditors specified in Section 30(4) of the I&B Code is mandatory. Further, is it open to the adjudicating authority/appellate authority to reckon any other factor other than specified in Sections 30(2) or 61(3) of the I&B Code as the case may be which, according to the resolution applicant and the stakeholders supporting the resolution plan, may be relevant?"

(emphasis supplied)

142. After considering the judgment of this Court in the case of Arcelormittal India Private Limited v. Satish Kumar Gupta46 and the relevant provisions of the I&B Code, this court further observed in K. Sashidhar (supra) thus:

"52. As aforesaid, upon receipt of a "rejected" resolution plan the adjudicating authority (NCLT) is not expected to do anything more; but is obligated to initiate liquidation process under Section 33(1) of the I&B Code. The legislature has not endowed the adjudicating authority (NCLT) with the jurisdiction or authority to analyse or evaluate the commercial decision of CoC much less to enquire into the justness of the rejection of the resolution plan by the dissenting financial creditors. From the legislative history and the background in which the I&B Code has been enacted, it is noticed that a completely new approach has been adopted for 12 Excise Appeal No.2679 of 2011 speeding up the recovery of the debt due from the defaulting companies. In the new approach, there is a calm period followed by a swift resolution process to be completed within 270 days (outer limit) failing which, initiation of liquidation process has been made inevitable and mandatory. In the earlier regime, the corporate debtor could indefinitely continue to enjoy the protection given under Section 22 of the Sick Industrial Companies Act, 1985 or under other such enactments which has now been forsaken. Besides, the commercial wisdom of CoC has been given paramount status without any judicial intervention, for ensuring completion of the stated processes within the timelines prescribed by the I&B Code. There is an intrinsic assumption that financial creditors are fully informed about the viability of the corporate debtor and feasibility of the proposed resolution plan. They act on the basis of thorough examination of the proposed resolution plan and assessment made by their team of experts. The opinion on the subjectmatter expressed by them after due deliberations in CoC meetings through voting, as per voting shares, is a collective business decision. The legislature, consciously, has not provided any ground to challenge the "commercial wisdom" of the individual financial creditors or their collective decision before the adjudicating authority. That is made non­justiciable." (emphasis supplied)

143. This Court has held, that it is not open to the Adjudicating Authority or Appellate Authority to reckon any other factor other than specified in Sections 30(2) or 61(3) of the I&B Code. It has further been held, that the commercial wisdom of CoC has been given paramount status without any judicial intervention for ensuring completion of the stated processes within the timelines prescribed by the I&B Code. This Court thus, in unequivocal 13 Excise Appeal No.2679 of 2011 terms, held, that there is an intrinsic assumption, that financial creditors are fully informed about the viability of the corporate debtor and feasibility of the proposed resolution plan. They act on the basis of thorough examination of the proposed resolution plan and assessment made by their team of experts. It has been held, that the opinion expressed by CoC after due deliberations in the meetings through voting, as per voting shares, is a collective business decision. It has been held, that the legislature has consciously not provided any ground to challenge the "commercial wisdom" of the individual financial creditors or their collective decision before the Adjudicating Authority and that the decision of CoC's „commercial wisdom‟ is made nonjusticiable.

144. This Court in Committee of Creditors of Essar Steel India Limited through Authorised Signatory (supra) after referring to the judgment of this Court in the case of K. Sashidhar (supra) observed thus:

"64. Thus, what is left to the majority decision of the Committee of Creditors is the "feasibility and viability"

of a resolution plan, which obviously takes into account all aspects of the plan, including the manner of distribution of funds among the various classes of creditors. As an example, take the case of a resolution plan which does not provide for payment of electricity dues. It is certainly open to the Committee of Creditors to suggest a modification to the prospective resolution applicant to the effect that such dues ought to be paid in full, so that the carrying on of the business of the corporate debtor does not become impossible for want of a most basic and essential element for the carrying on of such business, namely, electricity. This may, in turn, be accepted by the resolution applicant with a consequent modification as to distribution of funds, payment being provided to a certain type of operational creditor, 14 Excise Appeal No.2679 of 2011 namely, the electricity distribution company, out of upfront payment offered by the proposed resolution applicant which may also result in a consequent reduction of amounts payable to other financial and operational creditors. What is important is that it is the commercial wisdom of this majority of creditors which is to determine, through negotiation with the prospective resolution applicant, as to how and in what manner the corporate resolution process is to take place." (emphasis supplied)

145. This Court held, that what is left to the majority decision of CoC is the "feasibility and viability" of a resolution plan, which is required to take into account all aspects of the plan, including the manner of distribution of funds among the various classes of creditors. It has further been held, that CoC is entitled to suggest a modification to the prospective resolution applicant, so that carrying on the business of the Corporate Debtor does not become impossible, which suggestion may, in turn, be accepted by the resolution applicant with a consequent modification as to distribution of funds, etc. It has been held, that what is important is, the commercial wisdom of the majority of creditors, which is to determine, through negotiation with the prospective resolution applicant, as to how and in what manner the corporate resolution process is to take place. 146. The view taken in the case of K. Sashidhar (supra) and Committee of Creditors of Essar Steel India Limited through Authorised Signatory (supra) has been reiterated by another three Judges Bench of this Court in the case of Maharashtra Seamless Limited (supra).

147. In all the aforesaid three judgments of this Court, the scope of jurisdiction of the Adjudicating Authority (NCLT) and the Appellate Authority (NCLAT) has also been elaborately considered. It will be relevant to 15 Excise Appeal No.2679 of 2011 refer to paragraph 55 of the judgment in the case of K. Sashidhar (supra), which reads thus:

"55. Whereas, the discretion of the adjudicating authority (NCLT) is circumscribed by Section 31 limited to scrutiny of the resolution plan "as approved" by the requisite per cent of voting share of financial creditors. Even in that enquiry, the grounds on which the adjudicating authority can reject the resolution plan is in reference to matters specified in Section 30(2), when the resolution plan does not conform to the stated requirements. Reverting to Section 30(2), the enquiry to be done is in respect of whether the resolution plan provides : (i) the payment of insolvency resolution process costs in a specified manner in priority to the repayment of other debts of the corporate debtor, (ii) the repayment of the debts of operational creditors in prescribed manner, (iii) the management of the affairs of the corporate debtor, (iv) the implementation and supervision of the resolution plan, (v) does not contravene any of the provisions of the law for the time being in force, (vi) conforms to such other requirements as may be specified by the Board. The Board referred to is established under Section 188 of the I&B Code. The powers and functions of the Board have been delineated in Section 196 of the I&B Code. None of the specified functions of the Board, directly or indirectly, pertain to regulating the manner in which the financial creditors ought to or ought not to exercise their commercial wisdom during the voting on the resolution plan under Section 30(4) of the I&B Code. The subjective satisfaction of the financial creditors at the time of voting is bound to be a mixed baggage of variety of factors. To wit, the feasibility and viability of the proposed resolution plan and including their perceptions about the general capability of the resolution applicant to translate the projected plan 16 Excise Appeal No.2679 of 2011 into a reality. The resolution applicant may have given projections backed by normative data but still in the opinion of the dissenting financial creditors, it would not be free from being speculative. These aspects are completely within the domain of the financial creditors who are called upon to vote on the resolution plan under Section 30(4) of the I&B Code."

148. It has been held, that in an enquiry under Section 31, the limited enquiry that the Adjudicating Authority is permitted is, as to whether the resolution plan provides:

(i) the payment of insolvency resolution process costs in a specified manner in priority to the repayment of other debts of the corporate debtor,
(ii) the repayment of the debts of operational creditors in prescribed manner,
(iii) the management of the affairs of the corporate debtor,
(iv) the implementation and supervision of the resolution plan,
(v) the plan does not contravene any of the provisions of the law for the time being in force,
(vi) conforms to such other requirements as may be specified by the Board.

149. It will be further relevant to refer to the following observations of this Court in K. Sashidhar (supra):

57. ...Indubitably, the remedy of appeal including the width of jurisdiction of the appellate authority and the grounds of appeal, is a creature of statute.

The provisions investing jurisdiction and authority in NCLT or NCLAT as noticed earlier, have not made the commercial decision exercised by CoC of not approving the resolution plan or rejecting the same, justiciable. This position is reinforced from the limited 17 Excise Appeal No.2679 of 2011 grounds specified for instituting an appeal that too against an order "approving a resolution plan" under Section 31. First, that the approved resolution plan is in contravention of the provisions of any law for the time being in force. Second, there has been material irregularity in exercise of powers "by the resolution professional"

during the corporate insolvency resolution period. Third, the debts owed to operational creditors have not been provided for in the resolution plan in the prescribed manner. Fourth, the insolvency resolution plan costs have not been provided for repayment in priority to all other debts. Fifth, the resolution plan does not comply with any other criteria specified by the Board. Significantly, the matters or grounds-- be it under Section 30(2) or under Section 61(3) of the I&B Code --are regarding testing the validity of the "approved" resolution plan by CoC; and not for approving the resolution plan which has been disapproved or deemed to have been rejected by CoC in exercise of its business decision." [emphasis supplied]

150. It will therefore be clear, that this Court, in unequivocal terms, held, that the appeal is a creature of statute and that the statute has not invested jurisdiction and authority either with NCLT or NCLAT, to review the commercial decision exercised by CoC of approving the resolution plan or rejecting the same.

151. The position is clarified by the following observations in paragraph 59 of the judgment in the case of K. Sashidhar (supra), which reads thus:

"59. In our view, neither the adjudicating authority (NCLT) nor the appellate authority (NCLAT) has been endowed with the jurisdiction to reverse the commercial wisdom of the dissenting financial creditors and that too on the specious ground that it is only an opinion of the minority financial creditors....."
18 Excise Appeal No.2679 of 2011

152. This Court in Committee of Creditors of Essar Steel India Limited through Authorised Signatory (supra) after reproducing certain paragraphs in K. Sashidhar (supra) observed thus:

"Thus, it is clear that the limited judicial review available, which can in no circumstance trespass upon a business decision of the majority of the Committee of Creditors, has to be within the four corners of Section 30(2) of the Code, insofar as the Adjudicating Authority is concerned, and Section 32 read with Section 61(3) of the Code, insofar as the Appellate Tribunal is concerned, the parameters of such review having been clearly laid down in K. Sashidhar"

153. It can thus be seen, that this Court has clarified, that the limited judicial review, which is available, can in no circumstance trespass upon a business decision arrived at by the majority of CoC.

154. In the case of Maharashtra Seamless Limited (supra), NCLT had approved the plan of appellant therein with regard to CIRP of United Seamless Tubulaar (P) Ltd. In appeal, NCLAT directed, that the appellant therein should increase upfront payment to Rs. 597.54 crore to the "financial creditors", "operational creditors" and other creditors by paying an additional amount of Rs. 120.54 crore. NCLAT further directed, that in the event the "resolution applicant" failed to undertake the payment of additional amount of Rs. 120.54 crore in addition to Rs. 477 crore and deposit the said amount in escrow account within 30 days, the order of approval of the „resolution plan‟ was to be treated to be set aside. While allowing the appeal and setting aside the directions of NCLAT, this Court observed thus:

"30. The appellate authority has, in our opinion, proceeded on equitable perception rather than commercial wisdom. On the face of it, release of assets at 19 Excise Appeal No.2679 of 2011 a value 20% below its liquidation value arrived at by the valuers seems inequitable. Here, we feel the Court ought to cede ground to the commercial wisdom of the creditors rather than assess the resolution plan on the basis of quantitative analysis. Such is the scheme of the Code. Section 31(1) of the Code lays down in clear terms that for final approval of a resolution plan, the adjudicating authority has to be satisfied that the requirement of sub-section (2) of Section 30 of the Code has been complied with. The proviso to Section 31(1) of the Code stipulates the other point on which an adjudicating authority has to be satisfied. That factor is that the resolution plan has provisions for its implementation. The scope of interference by the adjudicating authority in limited judicial review has been laid down in Essar Steel [Essar Steel India Ltd. Committee of Creditors v. Satish Kumar Gupta, (2020) 8 SCC 531], the relevant passage (para 54) of which we have reproduced in earlier part of this judgment. The case of MSL in their appeal is that they want to run the company and infuse more funds. In such circumstances, we do not think the appellate authority ought to have interfered with the order of the adjudicating authority in directing the successful resolution applicant to enhance their fund inflow upfront."

155. This Court observed, that the Court ought to cede ground to the commercial wisdom of the creditors rather than assess the resolution plan on the basis of quantitative analysis. This Court clearly held, that the appellate authority ought not to have interfered with the order of the adjudicating authority by directing the successful resolution applicant to enhance their fund inflow upfront.

156. It would thus be clear, that the legislative scheme, as interpreted by various decisions of this Court, is 20 Excise Appeal No.2679 of 2011 unambiguous. The commercial wisdom of CoC is not to be interfered with, excepting the limited scope as provided under Sections 30 and 31 of the I&B Code."

56. Another three Judges Bench of this Court in the case of Karad Urban Cooperative Bank Ltd. vs. Swwapnil Bhingardevay & Ors. (supra), taking a similar view, has observed thus:

"14. The principles laid down in the aforesaid decisions, make one thing very clear. If all the factors that need to be taken into account for determining whether or not the corporate debtor can be kept running as a going concern have been placed before the Committee of Creditors and CoC has taken a conscious decision to approve the resolution plan, then the adjudicating authority will have to switch over to the hands off mode. It is not the case of the corporate debtor or its promoter/Director or anyone else that some of the factors which are crucial for taking a decision regarding the viability and feasibility, were not placed before CoC or the resolution professional...."

57. It could thus be seen, that the legislature has given paramount importance to the commercial wisdom of CoC and the scope of judicial review by Adjudicating Authority is limited to the extent provided under Section 31 of I&B Code and of the Appellate Authority is limited to the extent provided under sub-section (3) of Section 61 of the I&B Code, is no more res integra.

58. Bare reading of Section 31 of the I&B Code would also make it abundantly clear, that once the resolution plan is approved by the Adjudicating Authority, after it is satisfied, that the resolution plan as approved by CoC meets the requirements as referred to in sub-section (2) of Section 30, it shall be binding on the Corporate Debtor and its employees, members, creditors, guarantors and other stakeholders. Such a provision is necessitated since one of the dominant purposes of 21 Excise Appeal No.2679 of 2011 the I&B Code is, revival of the Corporate Debtor and to make it a running concern.

59. The resolution plan submitted by successful resolution applicant is required to contain various provisions, viz., provision for payment of insolvency resolution process costs, provision for payment of debts of operational creditors, which shall not be less than the amount to be paid to such creditors in the event of liquidation of the Corporate Debtor under section 53; or the amount that would have been paid to such creditors, if the amount to be distributed under the resolution plan had been distributed in accordance with the order of priority in sub-section (1) of section 53, whichever is higher. The resolution plan is also required to provide for the payment of debts of financial creditors, who do not vote in favour of the resolution plan, which also shall not be less than the amount to be paid to such creditors in accordance with subsection (1) of section 53 in the event of a liquidation of the Corporate Debtor. Explanation 1 to clause (b) of subsection (2) of Section 30 of the I&B Code clarifies for the removal of doubts, that a distribution in accordance with the provisions of the said clause shall be fair and equitable to such creditors. The resolution plan is also required to provide for the management of the affairs of the Corporate Debtor after approval of the resolution plan and also the implementation and supervision of the resolution plan. Clause (e) of sub-section (2) of Section 30 of I&B Code also casts a duty on RP to examine, that the resolution plan does not contravene any of the provisions of the law for the time being in force.

60. Perusal of Section 29 of the I&B Code read with Regulation 36 of the Regulations would reveal, that it requires RP to prepare an information memorandum containing various details of the Corporate Debtor so that the resolution applicant submitting a plan is aware of the assets and liabilities of the Corporate Debtor, including the details about the creditors and the amounts claimed by them. It is also required to contain the 22 Excise Appeal No.2679 of 2011 details of guarantees that have been given in relation to the debts of the corporate debtor by other persons. The details with regard to all material litigation and an ongoing investigation or proceeding initiated by Government and statutory authorities are also required to be contained in the information memorandum. So also the details regarding the number of workers and employees and liabilities of the Corporate Debtor towards them are required to be contained in the information memorandum.

61. All these details are required to be contained in the information memorandum so that the resolution applicant is aware, as to what are the liabilities, that he may have to face and provide for a plan, which apart from satisfying a part of such liabilities would also ensure, that the Corporate Debtor is revived and made a running establishment. The legislative intent of making the resolution plan binding on all the stake-holders after it gets the seal of approval from the Adjudicating Authority upon its satisfaction, that the resolution plan approved by CoC meets the requirement as referred to in sub-section (2) of Section 30 is, that after the approval of the resolution plan, no surprise claims should be flung on the successful resolution applicant. The dominant purpose is, that he should start with fresh slate on the basis of the resolution plan approved.

62. This aspect has been aptly explained by this Court in the case of Committee of Creditors of Essar Steel India Limited through Authorised Signatory (supra).

"107. For the same reason, the impugned NCLAT judgment [Standard Chartered Bank v. Satish Kumar Gupta, 2019 SCC OnLine NCLAT 388] in holding that claims that may exist apart from those decided on merits by the resolution professional and by the Adjudicating Authority/Appellate Tribunal can now be decided by an appropriate forum in terms of Section 60(6) of the Code, also militates against the rationale of Section 31 of the Code. A successful resolution 23 Excise Appeal No.2679 of 2011 applicant cannot suddenly be faced with "undecided"

claims after the resolution plan submitted by him has been accepted as this would amount to a hydra head popping up which would throw into uncertainty amounts payable by a prospective resolution applicant who would successfully take over the business of the corporate debtor. All claims must be submitted to and decided by the resolution professional so that a prospective resolution applicant knows exactly what has to be paid in order that it may then take over and run the business of the corporate debtor. This the successful resolution applicant does on a fresh slate, as has been pointed out by us hereinabove. For these reasons, NCLAT judgment must also be set aside on this count." 63. In view of this legal position, we could have very well stopped here and held, that, the observation made by NCLAT in the appeal filed by EARC to the effect, that EARC was entitled to take recourse to such remedies as are available to it in law, is impermissible in law.

64. As held by this Court in the case of Pr.

Commissioner of Income Tax vs. Monnet Ispat and Energy Ltd.[ SLP(C) No.6483/2018 (order dated 10.8.2018)] , in view of provisions of Section 238 of I&B Code, the provisions thereof will have an overriding effect, if there is any inconsistency with any of the provisions of the law for the time being in force or any instrument having effect by virtue of any such law. As such, the observations made by NCLAT to the aforesaid effect, if permitted to remain, would frustrate the very purpose for which the I&B Code is enacted.

86. As discussed hereinabove, one of the principal objects of I&B Code is, providing for revival of the Corporate Debtor and to make it a going concern. I&B Code is a complete Code in itself. Upon admission of petition under Section 7, there are various important duties and functions entrusted to RP and CoC. RP is required to issue a publication inviting claims from all the stakeholders. He is required to collate the said 24 Excise Appeal No.2679 of 2011 information and submit necessary details in the information memorandum. The resolution applicants submit their plans on the basis of the details provided in the information memorandum. The resolution plans undergo deep scrutiny by RP as well as CoC. In the negotiations that may be held between CoC and the resolution applicant, various modifications may be made so as to ensure, that while paying part of the dues of financial creditors as well as operational creditors and other stakeholders, the Corporate Debtor is revived and is made an on-going concern. After CoC approves the plan, the Adjudicating Authority is required to arrive at a subjective satisfaction, that the plan conforms to the requirements as are provided in sub-section (2) of Section 30 of the I&B Code. Only thereafter, the Adjudicating Authority can grant its approval to the plan. It is at this stage, that the plan becomes binding on Corporate Debtor, its employees, members, creditors, guarantors and other stakeholders involved in the resolution Plan. The legislative intent behind this is, to freeze all the claims so that the resolution applicant starts on a clean slate and is not flung with any surprise claims. If that is permitted, the very calculations on the basis of which the resolution applicant submits its plans, would go haywire and the plan would be unworkable.

87. We have no hesitation to say, that the word "other stakeholders" would squarely cover the Central Government, any State Government or any local authorities. The legislature, noticing that on account of obvious omission, certain tax authorities were not abiding by the mandate of I&B Code and continuing with the proceedings, has brought out the 2019 amendment so as to cure the said mischief. We therefore hold, that the 2019 amendment is declaratory and clarificatory in nature and therefore retrospective in operation.

25 Excise Appeal No.2679 of 2011

88. There is another reason, which persuades us to take the said view. Sub-section (10) of Section 3 of the I&B Code defines "creditor" thus:

"(10) "creditor" means any person to whom a debt is owed and includes a financial creditor, an operational creditor, a secured creditor, an unsecured creditor and a decree­holder;"

89. Sub-sections (20) and (21) of Section 5 of the I&B Code define "operational creditor" and "operational debt"

respectively as such:
(20) "operational creditor" means a person to whom an operational debt is owed and includes any person to whom such debt has been legally assigned or transferred;
(21) "operational debt" means a claim in respect of the provision of goods or services including employment or a debt in respect of the payment of dues arising under any law for the time being in force and payable to the Central Government, any State Government or any local authority;

90. "Creditor" therefore has been defined to mean „any person to whom a debt is owed and includes a financial creditor, an operational creditor, a secured creditor, an unsecured creditor and a decree­holder‟. "Operational creditor" has been defined to mean a person to whom an operational debt is owed and includes any person to whom such debt has been legally assigned or transferred. "Operational debt" has been defined to mean a claim in respect of the provision of goods or services including employment or a debt in respect of the payment of dues arising under any law for the time being in force and payable to the Central Government, any State Government or any local authority.

91. It is a cardinal principle of law, that a statute has to be read as a whole. Harmonious construction of subsection (10) of Section 3 of the I&B Code read with subsections (20) and (21) of Section 5 thereof would reveal, that even a claim in respect of 26 Excise Appeal No.2679 of 2011 dues arising under any law for the time being in force and payable to the Central Government, any State Government or any local authority would come within the ambit of „operational debt‟. The Central Government, any State Government or any local authority to whom an operational debt is owed would come within the ambit of „operational creditor‟ as defined under sub-section (20) of Section 5 of the I&B Code. Consequently, a person to whom a debt is owed would be covered by the definition of „creditor‟ as defined under sub-section (10) of Section 3 of the I&B Code. As such, even without the 2019 amendment, the Central Government, any State Government or any local authority to whom a debt is owed, including the statutory dues, would be covered by the term „creditor‟ and in any case, by the term „other stakeholders‟ as provided in subsection (1) of Section 31 of the I&B Code.

95. In the result, we answer the questions framed by us as under:

(i) That once a resolution plan is duly approved by the Adjudicating Authority under subsection (1) of Section 31, the claims as provided in the resolution plan shall stand frozen and will be binding on the Corporate Debtor and its employees, members, creditors, including the Central Government, any State Government or any local authority, guarantors and other stakeholders. On the date of approval of resolution plan by the Adjudicating Authority, all such claims, which are not a part of resolution plan, shall stand extinguished and no person will be entitled to initiate or continue any proceedings in respect to a claim, which is not part of the resolution plan;
(ii) 2019 amendment to Section 31 of the I&B Code is clarificatory and declaratory in nature and therefore 27 Excise Appeal No.2679 of 2011 will be effective from the date on which I&B Code has come into effect;
      (iii)   Consequently        all        the    dues          including        the
              statutory      dues        owed          to         the        Central
Government, any State Government or any local authority, if not part of the resolution plan, shall stand extinguished and no proceedings in respect of such dues for the period prior to the date on which the Adjudicating Authority grants its approval under Section 31 could be continued."

4.0 Thus in terms of the above correspondences and above decision of the Hon'ble Supreme Court the CESTAT could not have proceeded with the case of the appellant. By its order dated 20th September 2018 in IB-378 (PB)/2017, National Company Law Tribunal (NCLT) has ordered for liquidation of the Appellant, stating as follows:

"17. In the factual scenario, the members of the COC have decided to liquidate the Corporate Debtor, due to non receipt of any resolution plan, by majority of 100% vote sharing.
20. It is submitted that the COC has resolved by 100% majority to liquidate the Corporate Debtor as there is no resolution plan. The Committee of Creditors was of the opinion that no resolution plan could be possible, and it is in best interest of all the stake holders that the Corporate Debtor be liquidated and the decision of COC be intimated to the adjudicating authority in terms of the provisions of the code.
21. In the factual background and in absence of any resolution plan and for want of time beyond statutory CIRP period; there is no other alternative but to order, in conformity with the unanimous decision of the COC, for liquidation of the Corporate Debtor under Section 33 of the Code.
22. In the result application is allowed by ordering the liquidation of the corporate debtor namely Moser Baer India Ltd., in the manner laid down in Chapter III of Part II of the 28 Excise Appeal No.2679 of 2011 Insolvency and Bankruptcy Code 2016 along with following directions:
a. Mr. Anil Kohli resolution professional holding registration no IBBI/IPA-001/IP-P00112/2017- 18/10219, is appointed as liquidator in terms of Section 34 (1) of the Code.

b. Mr. Anil ZKohli is directed to issue Public Announcement stating that the corporate debtor is in liquidation, in terms of Regulation 12 of the Insolvency and bankruptcy Board of India (Liquidation Process) Regulations, 2016;

c. The registry is directed to communicate this Order to the registrar of Companies, NCT of Delhi & Haryana and to the Insolvency and Bankruptcy Board of India; d. The Order of Moratorium passed under Section 14 of the Insolvency and Bankruptcy Code, 2016 shall cease to have its effect and that a fresh Moratorium under Section 33 (%) of Insolvency and Bankruptcy Code shall commence;

e. The Liquidator is directed to proceed with the process of liquidation in the manner laid down in Chapter III of Part II of the Insolvency and Bankruptcy Code 2016and in accordance with the relevant regulations. f. The liquidator shall submit a Preliminary Report to the adjudicating Authority within seventy five days from the liquidation commencement date as per regulation 13 of the Insolvency and Bankruptcy (Liquidation Process) Regulation 2016.

g. Copy of this order be sent to the financial creditors, corporate debtor and the liquidator for taking necessary steps.

h. CA. 756 (PB)/ 2018 filed in Company Petition IB-378 (PB)/2017 is disposed of in the above said terms."

5.0 Rule 22 of Custom Excise Service Tax Appellate Tribunal Procedure Rules, 1982 read as follows:

29 Excise Appeal No.2679 of 2011
"RULE 22. Continuance of proceedings after death or adjudication as an insolvent of a party to the appeal or application. -- Where in any proceedings the appellant or applicant or a respondent dies or is adjudicated as an insolvent or in the case of a company, is being wound up, the appeal or application shall abate, unless an application is made for continuance of such proceedings by or against the successor-in-interest, the executor, administrator, receiver, liquidator or other legal representative of the appellant or applicant or respondent, as the case may be :
Provided that every such application shall be made within a period of sixty days of the occurrence of the event : Provided further that the Tribunal may, if it is satisfied that the applicant was prevented by sufficient cause from presenting the application within the period so specified, allow it to be presented within such further period as it may deem fit."

6.0 Undisputedly in terms of the order dated 20.09.2018, National Company Law Tribunal has directed for winding up of the appellant company and have appointed official liquidator in the matter. No application as per Rule 22, has been made by the official liquidator appointed by the NCLT in the matter for continuance of this appeal before tribunal even after expiry of more than five years from the date of NCLT order. Thus the appeals should abate in terms of the above referred rule. 7.0 Appeal abates in terms of Rules 22 of Custom, Excise & Service Tax Appellate Tribunal Procedure Rules, 1982.

(Pronounced in open court on- 05 April, 2024) Sd/-

(P.K. CHOUDHARY) MEMBER (JUDICIAL) Sd/-