Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 0]

Calcutta High Court

Rohitash Kumar Kothari vs Simplex Infrastructure Limited on 20 March, 2025

Author: Shampa Sarkar

Bench: Shampa Sarkar

OCD-10
                              AP-COM/477/2024
                       IN THE HIGH COURT AT CALCUTTA
                     ORDINARY ORIGINAL CIVIL JURISDICTION
                            COMMERCIAL DIVISON


                           ROHITASH KUMAR KOTHARI
                                     VS
                       SIMPLEX INFRASTRUCTURE LIMITED

 BEFORE:
 The Hon'ble JUSTICE SHAMPA SARKAR
 Date : 20th March, 2025.
                                                                                Appearance:
                                                                       Mr. Ratul Das, Adv.
                                                                    Mr. Sunit Biswas, Adv.
                                                            Mr. Rajashree Bhowmick, Adv.
                                                                      . . .for the petitioner.

                                                              Mr. Abhishek Banerjee, Adv.
                                                                Mr. Sitikantha Mitra, Adv.
                                                                    . . .for the respondent.
    The Court:

    1. This is an application under Section 11 of the Arbitration and

         Conciliation Act, 1996, hereinafter referred to as the said Act.                 The

         petitioner carries on business as a proprietor of Chandigarh Trade Link.

         The   petitioner     is    engaged   in   the      business     of   manufacturing,

         distributing, and providing          service    for construction       of chemical

         products.      The petitioner claims to be a wholesale supplier of

         construction, chemicals and tools of Sika, BASF, Fosroc Pidilite, STP,

         Delta and Fischer etc.         The respondent is a well-known construction

         company.       The        respondent is   engaged      in     civil and    structural

         construction    work,       throughout    India.      The     petitioner   and   the
                                   2


respondent entered into an agreement for supply of chemicals and

materials for such construction work of the respondent. Accordingly, a

purchase order was issued by the respondent to the petitioner.               Two

invoices followed the purchase order. The dispute arose in respect of

alleged non-payment of the balance due, amounting to Rs.3,86,057/-.

The total bill raised by the petitioner was approximately Rs.8,86,057/-.

Part payment thereof was made on August 10, 2018, to the tune of five

lakhs. The petitioner invoked arbitration by a notice dated November

15, 2023, as the remaining portion was unpaid.                According to the

petitioner, clause 23 of the purchase order contained an arbitration

clause. The clause provided as follows:

               "In the event of any difference or dispute arising out of or

            in connection with this order, the same should be first

            amicable settled by mutual dialogue.            If the parties fail to

            settle the difference or disputes arising out of or in connection

            with the order (including interpretation of the terms thereof),

            the same shall be referred to Arbitration.           The arbitration

            proceedings   shall       be   conducted   by    a sole    Arbitrator

            appointed by Company secretary of Simplex Infra. Ltd. and

            awards/decision of such Arbitrator shall be final and binding

            upon both the parties.           The Venue of the Arbitration

            proceedings shall be Kolkata. . ."
                                   3


2. The petitioner contends that an application under Section 11 of the said

   Act being AP No.844 of 2022, was also filed before this Court.        The

   pendency of the matter before the Hon'ble Court should be taken into

   consideration.   The period during which the application was pending

   before this Court, should be exempted in computing the period of

   limitation in filing the application, upon granting the benefit under

   Section 14 of the Limitation Act, 1963.

3. Mr. Banerjee, learned advocate for the respondent, relies on the

   affidavit- in-opposition and submits that this Court should not entertain

   the application as the petitioner had given up the claim in respect of the

   purchase order and invoices which are part of the present dispute.

   Reference is made to the order dated January 4, 2024. A learned Court

   recorded that the learned counsel appearing for the petitioner had given

   up the claim in respect of the purchase order relating to the

   construction work at Telengana. Admittedly, this proceeding arises out

   of the purchase order and the invoices in respect of the construction

   work at Telengana.

4. However, this Court finds that the Hon'ble Court had granted liberty to

   the petitioner to invoke arbitration in respect of the remaining purchase

   order. Thus, the contention of Mr. Banerjee that the claims have been

   entirely given up, does not appear to be correct. The Hon'ble Court was

   of the view that the notice invoking arbitration did not cover the

   purchase order of Telengana and a consolidated reference could not be
                                   4


  made.   Accordingly, liberty was given to proceed according to law, in

  respect of the said purchase order. Thus, the petitioner has approached

  this Court by filing an application under Section 11 of the said Act.

5. The question is whether such liberty can be construed as condonation

  of the delay caused by the petitioner in respect of the work order at

  Telengana. In my opinion, when the liberty was given to the petitioner

  to proceed under the law, it meant that the liberty would be subject to

  the rigours of law, which includes the laws of limitation, jurisdiction of

  the referral Court etc. Although, the jurisdiction of the Court is not in

  dispute, in view of the arbitration clause, but this Court finds that the

  invocation of the arbitration clause by the petitioner, in respect of the

  purchase order and invoices arising out of the construction work at

  Telengana was made in November 15, 2023.                Thus, Mr. Das's

  contention that the invocation and filing of the application were in

  exercise of the liberty granted by the Hon'ble Court, is not correct. The

  contention that the notice invoking arbitration and the application for

  reference should be held to be within time, upon excluding the period

  which was consumed in disposing of AP/844/2022, is also not

  accepted. The invocation of the arbitration clause by issuing a notice

  under Section 21 of the said Act was on November 15, 2023. The

  invocation was already time barred. The period of limitation to invoke

  arbitration is within three years from the date when the cause of action

  arose or the right to refer arose. In my opinion, the cause of action to
                                  5


  invoke arbitration arose after part payment was made within the period

  of limitation i.e. on and from August 10, 2018.      The records do not

  reveal that in respect of the construction work at Telengana, any further

  communication or assurance was made by the respondent, thereby

  acknowledging the remaining claim.       Even if the exclusion of time

  during the covid pandemic is allowed, the invocation is time barred.

6. The petitioner invoked the arbitration clause on November 15, 2023, in

  respect of the balance amount payable against the invoices arising out

  of the construction at Telengana. Instead of filing a separate application

  under Section 11 of the said Act, the petitioner had clubbed the claim

  arising out of the construction of work at Telengana, in the application

  filed before this Court, seeking a consolidated reference with regard to

  the disputes arising out of the work orders in respect of construction at

  Srinagar and Telengana. The learned Court was of the view that the

  claims could not be consolidated and the petitioner withdrew the claim

  in respect of the said construction work at Telengana.       The learned

  Court granted liberty to proceed in accordance with law.

7. The invocation with regard to the dispute arising out of the Telengana

  construction, was not made pursuant to the liberty granted by the

  Court. The invocation had already been made. The claim was clubbed

  in my view, in order to circumvent the fact that the invocation was

  already barred by limitation. In any event, as I have already discussed

  hereinabove, liberty granted by a court does not mean that such liberty
                                   6


  could be exercised in ignorance of or in violation to the statutory

  requirement.   It is well settled that the period of limitation to invoke

  arbitration is three years from the date of accrual of the cause of action.

8. In the decision of Arif Azeem Co. Ltd. vs Aptech Ltd. reported in

  (2004) 5 SCC 313, the Hon'ble Apex Court held as follows:-


     72. In Bharat Sanchar Nigam Limited (supra), this Court while
     observing that although the arbitration petition was not barred by
     limitation, yet the cause of action for the underlying claims having
     arisen much earlier, the claims were clearly barred by limitation on
     the day notice for arbitration was invoked. Relevant paragraphs are
     extracted herein below:
           "48. Applying the law to the facts of the present case, it is clear
           that this is a case where the claims are ex facie time-barred by
           over 5½ years, since Nortel did not take any action whatsoever
           after the rejection of its claim by BSNL on 4-8-2014. The notice
           of arbitration was invoked on 29-4-2020. There is not even an
           averment either in the notice of arbitration, or the petition filed
           under Section 11, or before this Court, of any intervening facts
           which may have occurred, which would extend the period of
           limitation falling within Sections 5 to 20 of the Limitation Act.
           Unless, there is a pleaded case specifically adverting to the
           applicable section, and how it extends the limitation from the
           date on which the cause of action originally arose, there can be
           no basis to save the time of limitation.
           49. The present case is a case of deadwood/no subsisting
           dispute since the cause of action arose on 4-8-2014, when the
           claims made by Nortel were rejected by BSNL. The respondent
           has not stated any event which would extend the period of
           limitation, which commenced as per Article 55 of the Schedule
           of the Limitation Act (which provides the limitation for cases
           pertaining to breach of contract) immediately after the rejection
           of the final bill by making deductions.
           50. In the notice invoking arbitration dated 29-4-2020, it has
           been averred that:
           "Various communications have been exchanged between the
           petitioner and the respondents ever since and a dispute has
           arisen between the petitioner and the respondents, regarding
           non-payment of the amounts due under the tender document."
                              7


       51. The period of limitation for issuing notice of arbitration
       would not get extended by mere exchange of letters, [S.S.
       Rathore v. State of M.P., (1989) 4 SCC 582 : 1990 SCC (L&S)
       50; Union of India v. Har Dayal, (2010) 1 SCC 394; CLP (India)
       (P) Ltd. v. Gujarat Urja Vikas Nigam Ltd., (2020) 5 SCC 185] or
       mere settlement discussions, where a final bill is rejected by
       making deductions or otherwise. Sections 5 to 20 of the
       Limitation Act do not exclude the time taken on account of
       settlement discussions.
       Section 9 of the Limitation Act makes it clear that:"where once
       the time has begun to run, no subsequent disability or
       inability to institute a suit or make an application stops it."
       There must be a clear notice invoking arbitration setting out
       the "particular dispute" [ Section 21 of the Arbitration and
       Conciliation Act, 1996.] (including claims/amounts) which
       must be received by the other party within a period of 3 years
       from the rejection of a final bill, failing which, the time bar
       would prevail.

       52. In the present case, the notice invoking arbitration was
       issued 5½ years after rejection of the claims on 4-8-2014.
       Consequently, the notice invoking arbitration is ex facie time-
       barred, and the disputes between the parties cannot be
       referred to arbitration in the facts of this case." (emphasis
       supplied)

****

87. Similarly, in Bharat Sanchar Nigam Limited (supra), it was held by this Court thus:

"51. The period of limitation for issuing notice of arbitration would not get extended by mere exchange of letters, [S.S. Rathore v. State of M.P., (1989) 4 SCC 582 : 1990 SCC (L&S) 50; Union of India v. Har Dayal, (2010) 1 SCC 394; CLP (India) (P) Ltd. v. Gujarat Urja Vikas Nigam Ltd., (2020) 5 SCC 185] or mere settlement discussions, where a final bill is rejected by making deductions or otherwise. Sections 5 to 20 of the Limitation Act do not exclude the time taken on account of settlement discussions. Section 9 of the Limitation Act makes it clear that: "where once the time has begun to run, no subsequent disability or inability to institute a suit or make an application stops it." There must be a clear notice invoking arbitration setting out the "particular dispute" [ Section 21 of the Arbitration and Conciliation Act, 1996.] (including claims/amounts) which must be received by the other party 8 within a period of 3 years from the rejection of a final bill, failing which, the time bar would prevail." (emphasis supplied)
9. Thus, this application fails.
10. AP-COM 477 of 2024 is, accordingly, disposed of.

(SHAMPA SARKAR, J.) sp/