Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 15, Cited by 0]

Karnataka High Court

Mrs Veena Shantharam Prabhu vs The Ombudsman on 16 April, 2025

Author: B.M.Shyam Prasad

Bench: B.M.Shyam Prasad

                          1




     IN THE HIGH COURT OF KARNATAKA AT BENGALURU

        DATED THIS THE 16TH DAY OF APRIL 2025

                       BEFORE

      THE HON'BLE MR. JUSTICE B.M. SHYAM PRASAD

       WRIT PETITION NO.5570 OF 2021 (GM-KEB)

BETWEEN
       MRS. VEENA SHANTHARAM PRABHU
       AGED ABOUT 53 YEARS
       W/O. MR. SHANTHARAM RAMDAS PRABHU,
       R/AT NARASIMHA KRUPA,
       B/403, MAURISHKA PARK,
       OPP. SHARADA VIDYALAYA,
       NEAR NAVABHARATA CIRCLE,
       KODIALBAIL, MANGALORE 03.
                                       ...PETITIONER

(BY SRI. VITTAL B R, ADVOCATE)

AND:

1.    THE OMBUDSMAN
      KARNATAKA ELECTRICITY
      REGULATORY COMMISSON,
      NO. 16C-1, KAVERAPPA LAYOUT,
      TANK BED AREA, VASANTH NAGAR,
      BENGALURU 560052.

2.    EXECUTIVE ENGINEER
      MESCOM (O AND M) DIVISION ATTAVAR,
      MANGALORE - 575 001.

3.    ASSISTANT EXECUTIVE ENGINEER
      MANNAGUDDA SUB DIVISION,
      MESCOM, MANGALORE -575 003.

4.    MAURISHKA PARK APARTMENT
      OWNERS ASSOCIATION
                           2




    MAURISHKA PARK APARTMENT
    OPP. SHARADA VIDYALAYA
    NEAR NAVABHARATA CIRCLE
    KODIALBAIL, MANGALORE - 3
    REPRESENTED BY ITS PRESEIDENT
    MR. K. DAYANANDA RAI.

                                    ...RESPONDENTS

(By SRI.H.V. DEVARAJU, ADVOCATE FOR R2 & R3;
   SRI. VIJAYA KRISHNA BHAT M, ADVOCATE FOR R4;
   NOTICE TO R1 SERVED)


     THIS WRIT PETITION IS FILED UNDER ARTICLES
226 AND 227 OF THE        CONSTITUTION OF INDIA
PRAYING TO     QUASH THE ORDER IN CASE NO.
OMB/M/G-394/2020      DATED        31.08.2020   OF
RESPONDENT-1    AS   IN       ANNEXURE-B   WHEREIN
OMBUDSMAN HAS NOT INTERFERED WITH ORDER OF
CGRP STATING THAT THE TRANSFER IS EFFECTED AS
PER KERC; DIRECTION TO RESPONDENT NO. 2 & 3 TO
CANCEL THE EFFECTED NAME TRANSFER IN THE
YEAR 2018 MAURISHKA PARK APARTMENT OWNERS
ASSOCIATION AND RESTORE THE SAME TO THE
ORIGINAL CONSUMER.


     THIS WRIT PETITION HAVING BEEN HEARD AND
RESERVED AND COMING ON FOR PRONOUNCEMENT
OF ORDERS THIS DAY, THE COURT MADE THE
FOLLOWING:


CORAM:   HON'BLE MR JUSTICE B M SHYAM PRASAD
                            3




                         CAV ORDER


     The    petitioner    has        impugned   the        first

respondent's Order dated 31.08.2020 in Case No.

OMB/M/G-394/2020/D-1470               [Annexure-B]        while

seeking directions to the Executive Engineer and the

Assistant Executive Engineer, Mangalore Electricity

Supply Company [MESCOM], who are arrayed as the

second and third respondents, to cancel the transfer

of High Tension [HT] connection in MGHT-47 in

favour of the fourth respondent, an Association of the

owners of the apartments in the complex called

Maurishka Park Condominium, Near Nava Bharata

Circle, Kodiyalbail, Mangalore.


     2.    The   petitioner     is    the   owner    of    the

Apartment No. B-403, and she has purchased this

apartment from the Builder, M/s R K Developers and

Builders, a partnership firm which is represented by

its Managing Partner, Sri. Ramesh Kumar, under the

Sale Deed dated 24.10.2008.            The Developer, on
                                4




16.03.2007, has caused a Deed of Declaration, as

contemplated        under     the     Karnataka      Apartment

Ownership Act, 1972, [referred to as the 'Karnataka

Apartment Ownership Act'] in the name of an

association called Maurishka Park Condominium. In

the year 2014, after the initial sanction of the Low

Tension [LT] connection of 1659 KW, the Developer

has got the sanction of a HT connection [in MGHT-

47] for 400 KVA in the name of its Managing Partner.

In June 2018, the Developer, as the Consumer of

MESCOM has issued No-objection Certificate [NOC],

for transfer of the subject HT connection to the fourth

respondent.


     3.    The       fourth         respondent,      after     the

resolution in the general body, has applied with

MESCOM        for   transfer    of     this   HT     Connection

enclosing NOC signed by Sri Ramesh Kumar [the

Managing      Partner   of     the     Developer],    a      Fresh

Agreement and an Indemnity bond. The Assistant

Executive Engineer, MESCOM [the third respondent],
                                      5




upon         verification     of     these         documents,     has

recommended transfer, and the Executive Engineer

[the second respondent] has issued Work Order dated

28.07.2018 for transfer of the HT Connection to the

fourth       Respondent.      The         petitioner   has   filed    a

complaint with the second respondent complaining

about illegal disconnection of electricity to her

apartment, and          the        second respondent by the

Communication dated 16.10.2018 has informed the

petitioner       that   the        fourth     respondent     is      the

Registered Consumer and that it is not responsible for

any disconnection.


        4.      The petitioner, with this Communication

dated    16.10.2018,          has        applied    with   Consumer

Grievance         Redressal         Forum,         Mangalore      [the

Grievance Redressal Forum] against the MESCOM

authorities under the provisions of the Karnataka

Electricity Regulation Commission [the Consumer

Grievance        Redressal         Forum       and     Ombudsman]

Regulations, 2004 [the KERC Regulations, 2004]. The
                               6




petitioner has complained about the transfer of the

HT Connection in favour of the fourth respondent.


     5.      The Grievance Redressal Forum, by its

order dated 07.02.2020, has rejected the petitioner's

complaint inter alia because the Consumer [the

Developer]     and   the    Transferee     [the     Apartments'

Owners' Association - the Fourth Respondent] are not

parties. The petitioner has filed her appeal against

this Order dated 07.02.2020 with the first respondent

under Regulation 21.2 of the KERC Regulations

2004. The petitioner in the appeal with the first

respondent     has    contended     that      the    Consumer

Grievance Forum has failed to consider that:

     [i] the     fourth     respondent        is     not   a

          Cooperative society registered with the

          Registrar of Cooperative Societies as is

          required under the provisions of the

          Karnataka Apartment Ownership Act,

     [ii] the transfer of the HT connection in

          MGHT-47      in     favour     of   the     fourth
                              7




          respondent violates Regulation 9.10 of

          the   Conditions   of   Electricity   Supply

          Regulations1 as documents in terms of

          Regulation 36 thereof are not collected,

      [iii] even otherwise, the fourth respondent,

          to be a properly constituted Society or an

          Association, should be registered under

          the Registration Act, 1908 and the stamp

          duty paid under the Karnataka Stamp

          Act,1957, and

      [iv] the petitioner, as the owner of the subject

          apartment, will be a consumer with the

          MESCOM under the Conditions of Supply

          Regulations.



The petitioner has also alleged that there was some

violation of due procedure in the proceedings with the

Consumer Grievance Forum as copies were not

served.


1   These Regulations are called "Conditions of Supply of
    Electricity of Distribution Licenses in the State of
    Karnataka 2006".
                                  8




       6.     The first respondent, in the light of the

contentions as aforesaid, has considered whether it

must     interfere     with     the       Consumer        Grievance

Redressal Forum's order dated 07.02.2020 on the

ground that such order is illegal or perverse. The first

respondent has opined that the Consumer Grievance

Redressal Forum's order does not suffer from any

such infirmity. The first respondent' conclusion in

these regards is based on its opinion that:


       [a] the officers of MESCOM cannot go into

             the     question        of   legality   of     the

             constitution of the fourth respondent

             and if the petitioner has any grievance

             with the constitution of the fourth

             respondent, such grievance must be

             addressed by the competent civil court;

       [b]   the first respondent has also concluded

             that    HT   connection        transferred      in

             favour of the fourth respondent is

             based on the consent of the consumer
                              9




             [the Developer] and upon execution of

             Indemnity Bond and Fresh Agreement.


        7.    As regards the petitioner's reliance upon

Regulation 9.10[b][ii] of Conditions of Electricity

Supply Regulations, the first respondent has opined

that it is clear from the plain reading of this

Regulation that if a Developer does not wish to have

any stake in the complex after completion of the

project, MESCOM can permit transfer of the service

in the name of an Association, or a Society, that is

formed to attend to the maintenance of the apartment

complex with sub-meters but on the condition there

shall be no profit or loss accruing to the society. The

first    respondent    has   also   opined   that    the

disconnection of the electricity cannot be attributed

to the MESCOM and its officers as the HT connection

is transferred in favour of the fourth respondent.


        8.    The petitioner, during these proceedings,

has filed civil suits, and she is joined by her

husband. The orders of the respective courts in these
                                10




civil proceedings have been carried in challenge

before this Court in Revision Petitions, and this Court

has disposed of these petitions answering questions

canvassed for consideration. The details of these

proceedings as also another pending suit must be

mentioned before the rival submissions in support of

and against the first respondent's impugned order

dated 31.08.2020. The details are as follows.


A Small Causes suit in SC No. 26/20192 on the
file of the II Additional Senior Civil Judge and
CJM, Mangalore

         8.1        The     petitioner,     joined    by    her

husband - a co-owner of the subject apartment with

her - has filed this suit for a mandatory injunction

against the fourth respondent's Office bearers to

restore electricity connection for their apartment. The

petitioner and her husband have asserted that the

fourth respondent is formed illegally by a few owners


2   The suit is initially filed in SC No. 4/2018 with another
    Court and with this plaint being rejected with liberty to the
    petitioner and her husband to re-present, the plaint in SC
    No. 4/2018 is re-presented and is assigned the present
    number.
                             11




of the apartments in the complex without complying

with the conditions in the Deed of Declaration

registered under the provisions of the Karnataka

Apartment     Ownership     Act.   However,   the   first

respondent has applied for rejection of the plaint

under Order VII Rule 11[a] and [d] of the Code of Civil

Procedure, 1908 [CPC].


       8.2        The civil Court has allowed the

fourth respondent's application rejecting the plaint,

and the civil Court's order is called in question in the

revision petition in CRP 64/2021. The civil Court's

another order rejecting the petitioner's application

[for restoration of the disconnected electricity to the

petitioner's apartment - IA No. 2] is called in question

in CRP No. 96/2021.        This Court has disposed of

both the civil revision petitions by the Common order

dated 08.09.2021 affirming that the civil Court has

rightly rejected the petitioner's suit.


       8.3        This Court in CRP No.64/2021 and

CRP No.96/2021 has considered the petitioner's
                               12




contention that the submission of the apartments to

the   provisions     of     the     Karnataka    Apartments

Ownership Act is only to ensure marketable and

editable title to the concerned apartments and the

responsibility of maintenance and other aspects are

covered      by    the     Karnataka      Ownership     Flats

[Regulation of the Promotion of Construction, Sale,

Management and Transfer] Act, 1972 [Karnataka

Ownership     of   Flats    Act],   and   that   the   fourth

respondent is not duly constituted because it is not

registered under this latter enactment. This Court

has examined whether the Karnataka Apartment

Ownership Act        and the Karnataka Ownership of

Flats Act are mutually exclusive or supplementary

and when an apartment is submitted to the former

Act would the latter apply.


The suit in OS No. 221/2022 on the file of the III
Additional Civil Judge and CJM, Mangaluru.

       8.4         The petitioner, and again joined by

her husband, has filed this suit for declaration that

certain clauses in the Deed of Declaration dated
                               13




16.03.2007 are void, that this Deed of Declaration is

not in accordance with the Karnataka Apartment

Ownership Act and are void ab initio and that the

fourth respondent cannot disconnect electricity to her

apartment. This suit is pending consideration.


        8.5       However, the petitioner has filed Ex.

Case No.228/2023 on the file of the III Additional

Civil Judge and JMFC, Mangaluru for breaking open

of the lock of the Electrical Room and Restoration of

electricity   supply   with    the   intervention   of   the

jurisdictional police relying on the civil Court's

interim order on IA No. III directing the fourth

respondent to restore electricity to the apartment.

The Executing Court, on 05.10.2023, has issued

directions for restoration of electricity with the

assistance of an electrician.


        8.6       This   Court,      on   22.09.2023,    has

heard the learned counsels for the parties, and when

the petition is listed for final submissions on

29.09.2023, Sri. Vittal B R, the learned counsel for
                                14




the petitioner, is permitted to file a Memo, to ensure

that there is no precipitation because of certain

orders in the execution proceedings. The learned

counsel and Sri Vijaykrishna M Bhat, the learned

counsel for the fourth respondent, have stated the

following.


     [a]     The   fourth     respondent   can     file   an
             application for the release of the amount
             deposited by the petitioner with the
             concerned Court in O.S. No.221/2022
             under protest, but on the condition that
             there shall be restoration of electricity to
             the subject unit forthwith, and the fourth
             respondent shall receive such amount
             subject to the outcome of the suit and
             without prejudice to the petitioner's rights
             to claim set off for such amount towards
             "future liability towards maintenance".

     [b] With the restoration of electricity, the
             petitioner will continue to pay future
             demands     by     the   fourth   respondent
             towards   maintenance       subject    to    the
             outcome of the suit and to claim set off in
             that regard for all future maintenance;
                               15




        c) The fourth respondent is willing to restore
           electricity forthwith upon the orders of
           this Court in that regard, and also make
           an application for receipt of the monies in
           deposit and to receive the amounts
           payable      towards     future     maintenance
           subject     to   the    two     conditions        as
           aforesaid.



        8.7          These statements have not brought

about quietus on restoration of electricity with the

Executing Court passing orders on 05.10.2023 for

breaking open the Electrical Room and restoration of

electricity to the petitioner's apartment with the

assistance of the jurisdictional police. This Court,

after   recording     submissions        for   restoration        of

electricity,   has    deferred     the    execution     of    the

executing Court's order while calling for a Report.


        8.8          Subsequently, the electricity to the

petitioner's   Apartment      is    restored.    The     fourth

respondent is reserved with liberty to receive the sum

of Rs.5,32,781/- deposited by the petitioner with the
                             16




civil Court. On 09.10.2023, the Executing Court has

closed the proceedings on a Memo filed by the

petitioner   after   the   orders   of   this   Court   as

aforementioned.


The details of the submission by Sri Vittal B R,
the learned counsel for the petitioner


      9.     The fourth respondent could have sought

for transfer of the HT connection only if it was

constituted by all the owners of 360 Apartments in

the complex, and that this would be because of

Section 3[d] of the Karnataka Apartment Ownership

Act and as seen from the Law Department's response

[allegedly to a query raised by the Department of Co-

operation]. The fourth respondent is not formed or

registered as contemplated under Regulation 9.10 of

the Conditions of Electricity Supply Regulations.


     9.1     In view of the expressions 'formed' and

'registered' as found in Regulation 9.10[b][ii] of the

Conditions of Electricity Supply Regulations and the

definition of a 'consumer' in clause 2.18 of Regulation
                              17




2 of the aforesaid Regulations the fourth respondent

is 'a service agency' and the petitioner is 'the

consumer' insofar as her Apartment. The power to

disconnect electricity is under Section 56 of the

Electricity Act, 2003 and such power must be

exercised by the MESCOM when a consumer is in

default.



     9.2    The       MESCOM           can       transfer

installations/connections according to Regulation 36

of the Conditions of Electricity Supply Regulations

and that this Regulation makes it mandatory for the

transferee to produce proof of ownership and if the

transferee is not an owner, a proper lease deed. In

the present case, because the fourth respondent

claims to be an Association of Apartment owners, it

should     have   produced    a   proper   Certificate   of

Registration, but the fourth respondent has not

produced the same and the second respondent has

transferred the HT connection.
                            18




The details of the submission of Sri Vijay
Krishna M, the learned counsel for the fourth
respondent:

     10.    The fourth respondent is constituted as

required under the provisions of the Karnataka

Apartment      Ownership    Act    with   the   Deed   of

Declaration dated 16.03.2007 and that there is no

other mode of registration or certification under this

Act. The learned counsel also submits that MESCOM

cannot decide on the due constitution of the fourth

respondent and therefore has rightly acted upon the

Deed of Declaration and other documents such as the

consent by the developer, the indemnity bond and

other compliances to transfer the HT connection in

favour of the fourth respondent.


        10.1      The petitioner, having initially relied

upon the Karnataka Ownership of Flats Act to

undermine the efficacy of the Deed of Declaration in

the suit in SC No.26/2019 and calling in question the

validity of this Deed in OS No. 221/2022, cannot

challenge the merits of the first respondent's order
                            19




 dated   31.08.2020     contending     that   the    fourth

 respondent is not duly constituted. As such, all

 questions [including whether the fourth respondent

 could rely upon the Deed of Declaration to raise

 maintenance charges with electricity charges] must be

 decided by the concerned Civil Court in the suit in

 OS No. 221/2022 based on the decision in CRP

 No.64/2021 and CRP No. 96/2021,


          10.2    The   Regulation     36.01[a]     of   the

Conditions of Electricity Supply Regulations, which

refers to the title documents and lease deed for the

purposes of transfer of connections, do not apply to the

fourth respondent. The transfer of the HT Connection

in favour of the fourth respondent is under Regulation

9.10 of these Regulations, which contemplate transfer

of connection from a Promoter/Developer. The transfer

of the connection in favour of the fourth respondent is

rightly made under this Regulation with the Developer

providing the Consent/NOC and the fourth respondent

complying with all the requirements.
                                20




The details of the submission of Sri H V Devaraj,
the learned counsel for MESCOM / its Officers:

       11.     The learned counsel does not join the

 debate on whether the fourth respondent is a duly

 constituted Association/ Society under the Karnataka

 Apartment Ownership Act but he relies upon the

 circumstances in which LT Connection is sanctioned

 and   later    a   HT     Connection    is      approved        and

 transferred to the fourth respondent. The learned

 counsel places on record the following details:


       On      9.12.2011:      The      concerned         Chief

       Engineer sanctioned 1695 KW power under

       LT- 2A Tariff upon an application filed by the

       Developer for power supply under LT tariff.

       On      28.01.2013      &     25.09.2013:               The

       developer     was     required      to        furnish     a

       Completion Certificate but before that he

       submitted     his    applications        to    avail    HT

       Connection.
                               21




      On    16.11.2013:      The   HT for 400 KVA

      connection is sanctioned.

      On      05.04.2014:      The    Developer     has

      furnished the Completion Certificate.

      On 11.04.2015: The HT power is serviced by

      Installation bearing RR No. MGHT 47.


The learned counsel next emphasizes the following

on the merits of the decision of sanctioning HT

connection.


           11.1      The power sanction as aforesaid is

subject to Regulation 4.02 of the Conditions of

Electricity Supply Regulations which contemplate

providing, "for the power supply to building/premises

either HT or LT or combination of HT and LT through

separate distinct service mains from a single source

with the provision for a common isolation point". The

initial   sanction    is   under   Regulation   9   of   the

Conditions of Electricity Supply Regulations, and the

request for 400 KVA [which is for 320 KW] is also

considered under Regulation 9 of the Regulations.
                                  22




            11.2      The      Regulation       9      of     the

Regulations3, when read in its entirety along with the

Notes appended, a Consumer must avail HT supply

for load 100 KW and above. The power sanction as

aforesaid is subject to Regulation 4.02 of the

Conditions of Electricity Supply Regulations which

contemplate providing, "for the power supply to

building/premises either HT or LT or combination of

HT and LT through separate distinct service mains

from a single source with the provision for a common

isolation point". Further, the Electricity Tariff 2018 -

Schedule HT- 4 provides for tariff payable by the

Residential Colonies/ Apartments.


This Court's reasoning:

         12.   The petitioner's case, as canvassed in this

application with the Grievance Redressal Forum is

encapsulated thus.



3   These submissions are both by Sri H V Devaraju and Sri
    Vijay Krishna Bhat in response to the clarification sought for
    by this Court vide the order dated 06.11.2024
                                  23




[a]   The submission of the apartments to the

      provisions      of   the     Karnataka          Apartments

      Ownership Act is only to ensure marketable

      title to the concerned apartments and the

      responsibility       of    maintenance          and   other

      aspects       are    covered         by   the    Karnataka

      Ownership of Flats Act, and the fourth

      respondent is not duly constituted because it

      is not registered under this latter enactment.


[b]   The fourth respondent, taking advantage of

      the transfer of HT Connection in its name,

      has    raised        unauthorized           charges     for

      electricity     as    part      of    the   Maintenance

      Charges payable by her. The MESCOM has

      not raised any Bill, but she has paid to the

      fourth respondent electricity charges based

      on the average consumption over the relevant

      six months and that she is only liable to pay

      such amount and not any other amount that

      the fourth respondent may claim.
                                24




[c]     As an Apartment Owner she will be the

        consumer        of     such         apartment           as

        contemplated under the provisions Section

        43 of the Electricity Act, 2003 [referred to as

        'the Electricity Act'] and Regulation 9.10 of

        the    Conditions      of     Electricity     Supply

        Regulations.


            12.1     The     merits    of     the    petitioner's

grievance against the first respondent's order dated

31.08.2020,         in the peculiarities of this case, are

examined       as    against   the    touchstone          of   these

questions:


      [i]     Whether this Court, with the petitioner
              raising      question    about        the        due
              incorporation of the fourth respondent in
              the pending suit in OS No. 221/2022 on
              the file of the III Additional Civil Judge
              and JMFC, Mangaluru, should render
              any finding in that regard or should the
              parties be relegated to work out their
              remedies in the suit in view of this
                                25




               Court's decision in CRP No.64/2021
               connected with CRP No.96/2021.

      [ii]     Whether the change of the initially
               sanctioned LT supply to HT supply is
               permissible under the Conditions of
               Electricity   Supply    Regulations,   and
               whether the first respondent should
               have considered this facet.

This Court's reasoning                and    conclusion     on
Question No. 1

        13.    This Court, in CRP No.64/2021 and CRP

No.     96/2021,      has    considered     the   petitioner's

contention that the submission of the apartments to

the     provisions      of   the     Karnataka    Apartment

Ownership Act is only to ensure marketable title to

the concerned apartments and the responsibility of

maintenance and other aspects are covered by the

Karnataka Ownership of Flats Act, and that the

fourth respondent is not duly constituted because it

is not registered under this latter enactment.


             13.1    This    Court    has    considered   the

petitioner's aforesaid case in the backdrop of whether
                              26




the Karnataka Apartment Ownership Act and the

Karnataka Ownership of Flats Act are mutually

exclusive or supplementary, and when an apartment

is submitted to the former Act, would the latter apply.

This Court has summarized its conclusion on the

different    questions,   including     the    questions   as

aforesaid, as follows:


   • The Karnataka Apartment Ownership Act
      and the Karnataka Ownership of Flats Act
      are not mutually exclusive nor can they be
      said to be supplementary to each other
      inasmuch as both the enactments cannot
      apply at the same time.

   • Once an apartment is submitted to the
      Karnataka Apartment Ownership Act by
      execution of a Declaration and Deed of
      Apartment under such Act, the Karnataka
      Ownership of Flats Act will not apply. It is
      only     the   provisions   of   the    Karnataka
      Apartment Ownership Act, which would
      apply.

   • Declaration, Deed of Apartment and Bye-
      laws in respect of an apartment building or
                               27




      a property can be executed at any point of
      time   and     not     necessarily     when    the
      apartment complex is ready or is sold. As
      and    when     the     Declaration,    Deed    of
      Apartment     and     Bye-laws    are   executed
      under the Karnataka Apartment Ownership
      Act,   the   said     apartment   building     and
      property would come out of the purview of
      the Karnataka Ownership of Flats Act and
      be subject to the Karnataka Apartment
      Ownership Act.


Admittedly, this Court's opinion has attained finality,

and therefore, every question must be examined in

the light of this opinion.



         13.2      The petitioner further contends that

the fourth respondent, taking advantage of the

transfer of HT Connection in its name, has raised

unauthorized charges for electricity as part of the

Maintenance Charges payable by her, that the

MESCOM has not raised any Bill, but she has paid to

the fourth respondent electricity charges based on

the average consumption over the relevant six
                           28




months and that she is only liable to pay such

amount and not any other amount which the fourth

respondent may claim.


        13.3      These are aspects which are rooted

in factual matrix, and the petitioner [joined by her

husband] has sued the fourth respondent in OS No.

221/2022    for    declaration   that    the    Deed    of

Declaration dated 16.03.2007 is void and for other

relief/s. The fourth respondent relies upon certain

clauses in this Deed of Declaration to assert the right

not just to take care of the maintenance of the

Apartment Complex, but also to raise Bills for

electricity consumption. The petitioner and the fourth

respondent must lead evidence on the true import of

the clauses that are contained in the Deed of

Declaration and a host of other circumstances based

upon which the civil Court will have to decide on the

merits in the light of this Court's exposition in the

revision petitions   in CRP      Nos.   64/    2021    and

96/2021.
                                29




          13.4        When the first respondent's opinion

that the Courts must examine whether the fourth

respondent is constituted in accordance with the law,

is thus examined this Court cannot take any

exception, and the petitioner must work out remedies

in   such     suit.   The   first    question   is    answered

accordingly, and all questions are left open to be

considered by the Civil Court in OS No. 221/2022

subject to this Court's opinion in CRP Nos. 64/ 2021

and 96/2021.


This Court's reasoning                and    conclusion    on
Question No. 2

        14.   The      Electricity     Supply        Companies

[ESCOMS], as required under the KERC [Conditions

of Licence to ESCOMS] 2004, have furnished 'Model

Conditions Of Supply Of Electricity' describing the

operating practices and connection policies with the

Commission for approval. The Commission by its

Order    dated      02.06.2006       has   communicated     its

approval for the Conditions of Supply of Electricity
                                  30




which is notified on 17.06.2006. These Conditions

govern the terms upon which electricity is supplied

even by the MESCOM. If the expression 'a consumer'

is defined under clause 2.184, the supply of electricity

to Multi-storied Buildings [both Commercial and

Residential] is governed by Regulation 9 of these

Conditions.         The    subject      apartment          complex,

'Mourishka        Park     Condominium'           is     entirely   a

residential complex with about 360 units. Therefore,

the      relevant    Regulation       will   be        9.09c5.   This

Regulation is for metering of power supply to 'Purely

Residential Apartments/ Complex[es], and it reads as

under.

c) METERING OF PUREY RESIDENTIAL APARTMENTS/COMPLEX
(ES)


4   CONSUMER‟ means any person who is supplied with
    electricity for his own use by a licensee or the Government
    or by any other person engaged in the business of
    supplying electricity to the public under the Act or any other
    law for the time being in force and includes any person
    whose premises are for the time being connected for the
    purpose of receiving electricity with the works of a licensee,
    the Government or such other person, as the case may be.

5    The service of electricity for "Mixed Loads" too is also under
    Regulation 9.08 and as discussed in this Order. The
    expression "Mixed Loads" refer to both supply of power to
    residential and commercial uses.
                       31




     L.T. Power supply shall be arranged at
     the request of the Applicant with the
     facility of LT metering to individual
     installations subject to observing all
     other Conditions as per provisions under
     note (b) & (c) of Clause 3.1.1 of the
     K.E.R.C (Recovery of Expenditure for
     supply of Electricity) Regulations 2004
     and its amendments from time to time
     {Annex-2}.

a)   Power supply to common areas like lifts,
     water supply, staircase lighting etc., if
     metered separately, shall be billed
     under either residential or commercial
     Tariff as per the classification of the
     building as defined under note (b) & (c)
     of Clause 3.1.1 of the K.E.R.C (Recovery
     of Expenditure for Supply of Electricity)
     Regulations 2004 and its amendments
     from time to time {Annex-2}.

b)   For building having requisitioned load of
     combined residential and commercial
     loads less than 100 KW, the power
     supply shall be arranged on LT basis
     with individual meters to each of the
     installations irrespective of whether it is
     commercial or domestic installation.
     Billing shall be done at appropriate
     Tariff.

c)   For    commercial       buildings    having
     requisitioned load less than 100 KW, the
     power supply shall be arranged on LT
     basis with individual meters to each of
     the installations. Billing shall be done at
     the appropriate Tariff.
Note:
i)    In the case of existing commercial
      buildings already under service, where
      the requisitioned load is less than 100
      KW and Consumer opts for individual
      meter, the same can be arranged if the
                               32




             Consumer gets the wiring done through
             LEC at his cost duly making provision to
             fix up the meter by the side of the
             existing bulk meter. However, the
             sanctioned load of the bulk meter shall
             be automatically reduced to the extent of
             the load of the installation bifurcated for
             individual meter.
     ii)     If additional load is requested over and
             above the total load already sanctioned,
             the same shall be sanctioned within 100
             KW only. For loads of 100 KW and
             above, the Consumer shall avail himself
             of HT supply.


           14.1    This Court, upon reading of these

Regulations, must opine that the clustering of

additional clauses [a] to [c] after Regulation 9.09c

could lead to a reading that these clauses will be

applicable        to     even       "Purely      Residential

Apartments/Complex[es]". However, whether it must

be read so will have to examined. When Regulation

9.09c is read along with the Heading, it would be that

LT Power supply shall be arranged at the request of

an applicant for Residential Apartments/Complexes

subject to observance with the conditions mentioned

therein.     Crucially, when LT Power supply is thus

arranged, there will be LT Metering to individual
                                33




installations as against one Bulk Energy Meter as

contemplated under Regulation 9.09[a] and [b] for the

'Mixed Loads'.      The decision to extend LT power

supply with individual LT Meter brings about a

relationship of consumer and the company supplying

electricity between the owner of the concerned unit

and the company unlike when Bulk energy Meter is

installed where such relationship is between the

company and an intermediary as is the case.


        14.2        The subsequent Clauses i.e. [a] - [c]

relate to metering and billing of power supply to [i]

common areas for both residential and commercial

building,    [ii]   buildings       with    residential   and

commercial      loads   less    than       100KW    and   [iii]

commercial buildings with less than 100KW. Even in

case of buildings with only commercial and both

commercial and residential loads, there will be

Individual Meters as in the case of 'purely residential

Apartments/Complexes'. Under Note [i], an existing

building with commercial load less than 100KW can
                           34




be serviced with Individual Meters if the concerned

opts for the same subject to bearing 'the cost' as

stipulated therein. The Note [ii] stipulates, without

specifying whether it is for residential or commercial

or mixed [both residential and commercial] loads, the

additional load can be up to 100KW, and beyond that

the consumer must apply under HT supply.


        14.3     The Scheme under this Regulation,

as it emerges from the reading as above, is that in

case of commercial load and mixed load [both

commercial and residential] subject to a minimum of

100KW Individual Meters will be available with even

the existing building with commercial load up to

100KW being given this option of Individual Meters,

but in the case of Load for 'purely residential

Apartments/Complexes' notwithstanding the load, the

metering of consumption will be by Individual Meters.

The terms of Note [ii] will be applicable when there is

a request for additional load, if the request for

additional load is up to 100KW, it will be as a LT
                                35




supply with Individual Meters, and if the request for

additional load is for a load over 100 KW, the supply

must be as a HT supply. The supply through HT

supply will be metered by Bulk Energy Meters.


          14.4      This Court must reiterate that the

significance of this, apart from the tariff that will

apply, indubitably is that the owners of the premises

to   which     there    is   Individual    Meters   are    the

consumers unlike when there is a Bulk Energy Meter

with Sub-meters. When there is Bulk Energy Meter,

the applicant, who is given this facility, will be the

consumer and this consumer can provide for Sub-

meters to individual premises subject to "no profit"

and other conditions. The Owner/Occupier of the

premises with Sub-meters will not be the consumer.

This enables in the applicant who avails "Bulk Energy

Meters"   certain      obligation    and   rights   with   no

relationship     between       the   ESCOMS         and    the

Owner/Occupier.
                            36




        14.5     A residential apartment, if the Note

[ii] is made applicable, despite the Scheme and

consequences     as   aforesaid    only   because    the

Electricity Tariff - 2018 [with its amendments]

provide for HT tariff for residential apartments, is

provided with HT Supply, the entire Scheme under

this Regulation will be vitiated. This Court opines,

with the Regulations as they are, that              every

residential complex which is entirely so must be

initially given, irrespective of the load; LT supply with

Individual Meters, and if subsequently there is a

request for increase in the load, subject to a

maximum of additional load of 100KW, the supply

must be LT supply with Individual Meters.      However,

if the request is for an additional load which is above

100KW, the supply must be HT supply with Bulk

Energy Meters and Sub-meters.


        14.6     Further, this Court opines that if

despite this Scheme, a residential complex, which is

entirely so, is given HT supply with Bulk Energy
                                  37




Meter     facility,    unwittingly      or      otherwise,      the

Owner/Occupier of a unit in a purely residential

complex will be denied the status of being consumer

of the concerned ESCOMS leading to denial of

obvious    advantages.       The      present    case   perhaps

exemplifies the same, and that will have to be

examined in the pending suit.


          14.7        In   the   present     case,   the     initial

sanction is for LT supply with a load of more than

100 KW, but it is later changed to HT Supply again

with a load more than 100KW [though reduced]. It is

only stated that this is done because the Developer

requested for the same and nothing is placed on

record to justify that this decision was taken on                 a

minutiae reading of the Regulations and upon

examining the repercussions. The decision to give HT

supply and the servicing is in the year 2015 and

there have been multiple proceedings which are

mentioned. The first respondent has not considered
                                38




any of these circumstances, and should have as this

facet lies at the core of the dispute.


         14.8      This Court, in the peculiarities of the

case, opines that the Managing Director, MESCOM

must call for all the details and take such decision as

would be necessary to undo the deleterious effect of

the decision to grant HT supply with Bulk Energy

Meter   notwithstanding         the   Regulations    as    the

controversy over the change in the HT connection

from the Developers' name to the fourth respondent's

name will also be addressed by the said consideration

in the light of this Court's opinion on the object of the

Regulation 9.09 of the Conditions of Supply of

Electricity   Regulations.      The   second    question    is

answered accordingly.


                              ORDER

[a] The petition is disposed of directing the Managing Director, MESCOM to call for all the details and the records and take such decision 39 as would be necessary to ensure that the Maurishka Park Condominium, Opposite Sharada Vidyalaya, Near Bharat Circle, Kodialbail, Mangaluru has LT supply with Individual Meters for each of the Apartment in the Complex working out the modalities therefor.

[b] All questions inter se the petitioner and the fourth respondent as regards the Deed of Declaration dated 16.03.2007 and the action by the fourth respondent in terms thereof are left open to be decided in the suit in O.S. No.221/2022 on the file of the III Additional Civil Judge and JMFC, Mangaluru subject to this Court's opinion in CRP No.64/2021 and CRP No.96/2021.

[c] The fourth respondent is reserved with liberty to seek disbursement of Rs.5,32,781/- deposited by the petitioner in the suit subject to 40 the outcome in the afore suit in O.S. No.221/2022.

SD/-

(B M SHYAM PRASAD) JUDGE nv*