Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 0]

Delhi District Court

Bbr (India) Pvt. Ltd vs Satilila Charitable Society on 13 February, 2017

     IN THE COURT OF  GAURAV RAO, SENIOR CIVIL JUDGE 
       CUM RENT CONTROLLER ( SOUTH EAST), DISTRICT 
                COURTS, SAKET, NEW DELHI

CS No: 51790/2016 (Old no. 156/15)
CNR No.: DLSE03­001055­2015
BBR (India) Pvt. Ltd.
C­63, Ground Floor, 
Okhla Indl. Area Phase I,
New Delhi - 110020.                                                                 .....Plaintiff
                                               Versus


Satilila Charitable Society
A­14, Kailash Colony, 
Near Metro Station,
New Delhi - 110048.                                                                 ....Defendant

Date of institution of suit                                       :        22.05.2015
Date on which Judgment reserved                                   :        13.02.2017
Date on which judgment pronounced                                 :        13.02.2017
Decision                                                          :        Decreed
                                      J U D G M E N T


1.

The   present   suit   for   recovery   of   Rs.   94,732/­   has   been  filed by the plaintiff company against the defendant society.

Plaint

2. The   case   of   the   plaintiff   is   that   it   is   a   company  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 1/21 incorporated under the Companies Act 1956 and is inter alia engaged  in post tensioning work in the construction of buildings etc. 2.1 It is further its case that defendant is a Charitable Society  engaged   in   the   activity   of   construction   and   running   of   educational  institutes etc. 2.2 It is further its case that defendant approached the plaintiff  for   post   tensioning   of   beams   at   7th   and   8th   Floor   for   its   building  named   Skyline   Institute   of   Engineering   and   Technology,   Greater  Noida, UP and placed work order on 23rd July 2012 for a consideration  of Rs. 6,30,000/­ plus taxes.

2.3 It   is   further   its   case   that   in   terms   of   the   work   order   the  defendant was to release the payment of 10% on mobilization advance,  40% on delivery of pre­stressing material at site, 15% on concreting  and 35% on stressing.

2.4 It is further its case that it raised three bills viz. RA­01 dated  29.10.2012, RA­02 dated 28.11.2012 and RA­03 dated 02.01.2013 for  the agreed amount yet part payment is pending against all the three  bills making a total outstanding of Rs. 66,488/­ which the defendant is  neglecting to release for no reason or rhyme.

CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 2/21 2.5 It is further its case that defendant requested the plaintiff  for   issuance   of   completion   certificate   which   was   duly   sent   by   the  plaintiff vide its letter reference no. SCS/SITE/2012/07­01/BBR dated  19.02.2013 and plaintiff again requested the defendant to release the  outstanding payment yet to no avail.

2.6 It   is   further   its   case   that   it   sent   a   legal   notice   dated  16.12.2014 demanding a sum of Rs. 66,488/­ to the defendant, but to  no avail.

2.7 It is further its case that to its utter shock the defendant in  its reply to legal notice dated 16.12.2014 despite having received the  completion   certificate   and   using   the   same   in   furtherance   of   the  sanctions of the institute, made a wild allegation of not removing the  scaffolding and rectification of defect alleged to be pending.

2.8  Hence, the present suit. 

 

3. The  defendant   appeared   in   pursuant   to   service   of  summons and filed its Written Statement. 

Written Statement of defendant

4.  It was pleaded that the suit filed by the plaintiff is vague,  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 3/21 does not reflect any cause of action and is liable to be dismissed. It  was pleaded that the plaintiff has not disclosed the facts on the basis of  which it claims that there is total outstanding of Rs. 66,488/­.

4.1 It was further pleaded that plaintiff with an intention to  misguide this court did not disclose the terms of work order on the  basis of which it is alleged that amount of Rs. 66,488/­ is outstanding  on the part of defendant.

4.2 It was further pleaded that the plaintiff intentionally omitted  to mention that there would be VAT @ 4% and service tax @ 4.88%  on the work order of Rs. 6,30,000/­ and that the completion time of  work was 75 days from the date of work order i.e. 23 July 2012 which  expired on 6th October 2012. 

4.3 It was further pleaded that the defendant released advance  payment of 10 % of the contract value to the plaintiff and the same was  accepted   by   the   plaintiff   however   despite   receiving   the   advance  payment on 27.07.2012 plaintiff did not complete the work order on  06.10.2012.

4.4 It   was   further   pleaded   that   the   work   order   dated  23.07.2012 also contains the scope of work order and responsibilities  of the plaintiff. It was further pleaded that the plaintiff has not taken  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 4/21 insurance for equipment & W.C. Policy and that it has not complied  with item no. 8 i.e. cutting & Profiling of strands, ducts & anchorages  as per the work order dated 23.07.2012.

4.5 It was further pleaded that as per the terms of the work  order the defendant provided sufficient working platform near stressing  ends to the plaintiff during the entire period of work on hire basis from  Skyline Infratech Ltd on monthly rentals.

4.6 It   was   further   pleaded   that   plaintiff   was   required   to  handover the complete work by 06.10.2012 as specified in the work  order dated 23.07.2012 but the defendant was compelled to take the  unfinished,   incomplete   work   on   19.02.2013   in   order   to   avoid   more  losses on account of rent for providing scaffolding/working platform.

4.7 It was further pleaded that the defendant sustained heavy  losses on account of the delay caused by the plaintiff in completing the  work   and   now   the   defendant   is   willing   to   file   a   suit   for  damages/compensation   for   the   losses   sustained   by   it   on   account   of  delay   caused   by   the   plaintiff   in   completing   the   work   order   dated  23.07.2012   and   a   notice   for   that   was   also   sent   to   the   plaintiff   on  16.09.2015.

4.8 It was further pleaded that on account of delay caused by  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 5/21 the   plaintiff   in   performing   the   work   as   per   work   order   dated  23.07.2012, the defendant had incurred huge loss of Rs. 4,95,535/­ for  rentals for providing working platform/scaffolding for extra period of  around four and a half months than as provided in the work order.

4.9 It was further pleaded that the plaintiff has raised three  bills but has not shown what were the bill amounts and what were the  items against which the bills were raised. It was further pleaded that  the plaintiff has not shown whether the bills were raised according to  the terms of the work order or arbitrarily. It was further pleaded that  the plaintiff has also concealed the amounts received by it against each  bills and has straightforwardly claimed that there is a total outstanding  of Rs. 66,488/­.

4.10 It was further pleaded that the plaintiff has received its  entire dues according to the work done by it on 01.04.2013 itself and  the defendant is not liable to make any payment to the plaintiff. It was  pleaded that the legal notice dated 16.12.2014 sent by the plaintiff after  receipt of final payment on 01.04.2013 is vague, baseless and has been  sent just to illegally extort money from the defendant.

Replication/Rejoinder

5. The   plaintiff   filed   replication   to   the   written   statement   of   the  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 6/21 defendant  wherein  it  denied  the  averments  of   the  written  statement  while simultaneously reiterating and reaffirming the contents of the  plaint.

ISSUES

6. On   the   basis   of   the   pleadings   of   the   parties   following  issues were framed by the Ld. Predecessor of this court vide order  dated 15.10.2015:

1. Whether plaintiff is entitled to decree for a sum of Rs. 94730  as prayed ? OPP
2. Whether plaintiff is entitled to any interest, if yes, at what   rate and for what period? OPP
3. Relief. 

Plaintiff evidence

7. In order to prove its case  plaintiff examined Sh. Bharat  Bhushan as PW1 who deposed on the lines of plaint. He tendered his  evidence by way of affidavit as Ex. PW­1/A and relied upon following  documents:

(a) Board Resolution as Ex. PW­1/1,
(b) Work order as Ex. PW­1/2, CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 7/21
(c) Statement of Account as Ex. PW­1/3,
          (d) Bills and statement of account as Ex. PW­1/4,
          (e) copy of completion certificate as Mark PW­1/5,
(f) Legal notice as Ex. PW­1/6 and
(g) Reply as Ex. PW­1/7 7.1 Plaintiff examined another witness Sh. M. Raju as PW­2  who tendered his evidence by way of  affidavit as Ex. PW­2/A and  relied   upon   document   i.e.   copy   of   site   plan   as   Mark   PW­2/1   and  Conveyance Expenses as Ex. PW­2/2.

Defendant Evidence

8. As against this defendant examined Sh. Rajnish Kumar,  HR Manager as DW­1 who tendered his evidence by way of affidavit  as Ex. DW­1/A. He relied upon following documents:

(a) Authority letter dated 03.11.2016 as Ex. DW­1/1,
(b) Work order dated 23.07.2012 as Ex. DW­1/2,
(c)  10 photographs as Ex. DW­1/3 (colly),
(d)  Copy of bills as Mark A (colly)
(e) copy of ledger account maintained for BBR India Pvt. 

Ltd. as Ex. DW­1/5.

9. I have heard the Ld. counsel for parties, have given due  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 8/21 consideration to the rival contentions raised at bar and have carefully  gone through the record.

Findings

10. My issue wise finding is as under:­ Issue No. 1. 

Whether plaintiff is entitled to decree for a sum of Rs. 94730 as  prayed ? OPP 10.1 In   nutshell   it   is   the   case   of   the   plaintiff   that   despite  completing   the   work   in   terms   of   work   order   dated   23.07.2012   and  despite   repeated   demands   defendant   did   not   clear   the   outstanding  amount of Rs. 66,488/­ and it is this amount with interest which is now  being claimed by the plaintiff by way of the present suit. 

10.2 After considering the entire material on record I am of the  opinion that the plaintiff is indeed entitled to the outstanding amount  as per work order dated 23.07.2012. 

10.3 Execution   of   work   order   dated   23.07.2012   i.e.   Ex.  PW1/2/Ex.DW1/2 is not disputed. Ex. PW1/2/Ex.DW1/2 which is an  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 9/21 admitted document is the basis of the entire claim of the plaintiff. As  per this work order the total amount agreed to be paid by the defendant  to the plaintiff was Rs. 6,30,000/­ excluding the VAT and Service Tax. 

10.4 Apart from the work order even the payments made by the  defendant and received by the plaintiff are not disputed. Though the  defendant did agitate that the plaintiff failed to file on record different  bills raised at different times and the particulars of the payment made  against those bills however this agitation looses significance in view of  the fact that there is no dispute as to the total payment made to and  received by the plaintiff. The plaintiff as per its statement of account  Ex. PW1/3 claims to have received a total a sum of Rs. 6,13,520/­ from  the   defendant.   The   defendant   did   not   dispute   the   same   even   once  during the trial.  It was not even once claimed and accordingly never  suggested to the plaintiff's witnesses during their cross examination  that  the  defendant  had  paid or  that  the  plaintiff   had received more  payment than Rs. 6,13,520/­. 

10.5 Nonetheless apart from Ex. PW1/3 plaintiff also filed Ex.  PW1/4 i.e. detailed statement of account and copy of the bills against  which the payments were received which puts to rest controversy if any  regarding the payment made to or received by the plaintiff. In fact the  defendant had also produced its ledger account i.e. Ex. DW1/5 wherein  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 10/21 all   the   payments   made  by  it   and  received  by  the   plaintiff   are  duly  reflected and all the payments tally. The payment was made to the  plaintiff   on   four   occasions   in   the   sum   of   Rs.  55900/­,   2,74,571/­,  1,01,819/­ and 1,81,230/­ respectively. There is no dispute regarding the  the above payments. Though there is a dispute regarding the time of  payment   however   the   dispute   regarding   the   time   of   payment   is  insignificant except for the payment of Rs. 55,900/­.

10.6     Though   Ld.   Counsel   for   the   defendant   relied   upon  Anvar  PV Vs.  P.K. Basheer  and ors.  (2014)  10 SCC  473, Central   Bureau   of   Investigation   Vs.   V.C.   Shukla   AIR   1998   SC   1406  and  Ishwar Dass Jain Vs. Sohan Lal AIR 2000 SC 426 to argue that the  statement   of   account   were   not   proved   as   per   the   rules   of   evidence  however the said case laws does not help the cause of the defendant for  the simple reason that there is no dispute regarding the total payment  made by the defendant or received by the plaintiff in the present case.  The judgments would have assumed significance in the context of the  present case if the defendant had disputed the claims of the plaintiff  regarding the total payment made to it and had claimed that defendant  had paid much more than as was claimed by the plaintiff. Once there is  no such dispute reliance upon the above case laws does not come to the  rescue of the defendant. 

CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 11/21 10.7 Ld. Counsel  for the defendant had also argued that the  defendant is not liable to make any further payment to the plaintiff as  the plaintiff did not complete the work in time as per the work order. It  was argued that as per work order dated 23.07.2012 entire work was to  be completed within 75 days however the plaintiff failed to complete  the work within 75 days and therefore the plaintiff is not entitled to any  amount. It was argued that time was the essence of the contract and as  the plaintiff failed to complete the work within the stipulated time it  cannot claim any amount from the defendant. However I find no merits  in the arguments of the Ld. Counsel for the defendant.

10.8 No doubt as per Ex. PW1/2 i.e. work order the entire work  was to be completed within 75 days and it was not completed within  the said period/time­line however the plaintiff cannot be blamed for  non completion of work within the stipulated time. As per the work  order defendant was under an obligation to make advance payment of  10%   i.e.   Rs.   63,000/­   as   "mobilization   advance".   However   the  "mobilization advance" was given to the plaintiff only on 10.10.2012  as is reflected in the statement of account i.e. Ex. PW1/4 i.e. after the  lapse of more than 2 and ½ months (Note: as per work order dated  23.07.2012   the   work   was   to   be   completed   within   75   days   i.e.   by  06.10.2012 but the payment of "mobilization advance" was made only  on 10.10.2012). This caused the delay in completion of the work within  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 12/21 the stipulated time. PW1 during his cross examination explained the  same   when   he   stated   "I   can   start   the   work   only   when   I   get   10%   mobilization advance in terms of the work order. It is correct that we   have to complete the work order within 75 days from the date of receipt   of the work order. (Vol., but we have to start the work only after getting   the 10% mobilization advance).  Obviously the plaintiff and for that  matter any other person or entity would not have commenced the work  unless the " mobilization advance" was paid to it. This is a prudent call  which   every   person   or   entity   would   make   at   the   time   of  commencement of any work as per the contract/work order.  

10.9 The delayed payment by the defendant itself proves that  the time was not the essence of contract/work order as claimed by the  defendant. Whether the time is the essence of the contract or not is to  be gathered from the intention of the parties and in the case at hand the  conduct of the defendant in releasing the " mobilization advance" after  2 and ½ months itself proves that time factor was not material or it was  not the essence of the contract.  Reliance may be placed upon the law  laid   down   in  Hind   Construction   Contractors   Vs.   State   of  Maharashtra 1979 AIR 720, Chand Rani Vs. Kamal Rani 1993  AIR   1742   and   Gomathinayagam   Pillai   Vs.   Pullaniswami   Nadar  1967 AIR 868.

CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 13/21 10.10 Furthermore once the defendant itself does not do its part  of   the   obligation   as   per   the   work  order   and   defaults   and   delays   in  making the payment of "mobilization advance" the defendant cannot  agitate that the work was not completed within the stipulated time. In  fact the complete amount as "mobilization advance" was not paid to  the plaintiff as per the work order. As per work order defendant was to  pay   Rs.   63,000/­   but   only   a   sum   of   Rs.   55,900/­   was   paid   to   the  plaintiff.  

10.11 Though Ld. Counsel for the defendant relying upon Ex.  DW1/5 had argued that the "mobilization advance" was released to the  plaintiff on 27.07.2012 itself however I am of the firm opinion that the  plea of the defendant to that extent is nothing but a falsehood. To that  extent the defendant tried to hoodwink the court and set up a case  which was nothing but a bundle of lies. A bare glance at Ex. DW1/5  would reveal that there is cutting/ interpolation on the date mentioned  against   the   cheque/payment.   Date   seems   to   have   been   altered  deliberately to defeat the claim of the plaintiff. If indeed the payment  was   made   on   27.07.2012   as   claimed   by   the   defendant   than   the  defendant   should   have   proved   its   statement   of   account/entry   in   the  passbook/bank   records   to   corroborate   the   said   claim.   In   fact   DW1  during his cross­examination stated as "I have no record as to prove   that   the   cheque   of   advance   payment   of   10%   was   released   on   CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 14/21 27.07.2012 except the date mentioned in Ex. DW1/5."   It is also not  disputed that the above said cheque was credited in the account of the  plaintiff   on   10.10.2012   which   is   otherwise   also   evident   from   Ex.  PW1/4.   The   defendant   also   did   not   bother   to   examine   any   of   its  employee   to   prove   that   the   cheque   was   given   to   the   plaintiff   on  27.07.2012.   Hence   the   defendant   could   not   even   remotely   prove   its  claim of having made the payment or issued the cheque on 27.07.2012.

10.12 Furthermore I am not inclined to believe that the plaintiff  would   have   deliberately   not   encashed   the   said   cheque   immediately  after 27.07.2012 if indeed it was issued on 27.07.2012 and would have  encashed it only on 10.10.2012. Why would the plaintiff deprive itself  of the payment? The defendant could not explain and even I fail to  understand what could have been the rational behind the same as was  claimed by the Ld. Counsel for the defendant. In fact this very entry,  cutting,   interpolation   in   Ex.   DW1/5   entitles   the   plaintiff   to   the  recovery of the amount as it proves the falsehood in the case of the  defendant. 

10.13 It was also argued by Ld. Counsel for defendant that not  only the work was not completed within the stipulated time but in fact  the defendant was compelled to take incomplete and unfinished work  from the plaintiff as a result the defendant suffered damages and hence  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 15/21 no question of payment of any outstanding amount arises. However I  find   no   merits   in   the   said   arguments   of   the   Ld.   Counsel   for   the  defendant. It has already been discussed above that time was not the  essence of the contract/work order and the delay if any occurred on  account   of   delayed   payment   of   "mobilization   advance"   by   the  defendant. As far as the contentions that the defendant was compelled  to   take   incomplete   and   unfinished   work   are   concerned   same   are  meritless   and   merely   an   afterthought   to   avoid   payment   of   the  outstanding  amount/dues.   Plaintiff  proved  on  record  the  completion  certificate   issued   by   it   to   the   defendant   as   Mark   PW1/5.   Vide   this  completion   certificate   the   plaintiff   informed   the   defendant   that   no  work/activity was pending at their end and that they have completed  the job in all respects. This completion certificate was sent along with  a   covering   letter   via   e­mail   to   the   defendant   on   20.02.2013.   This  completion certificate was not disputed during the trial.  Not even once  it   was  suggested  to  PW1 that  this  completion  certificate  was  never  received by the defendant. In fact DW1 during his cross­examination  stated   as   "It   is   correct   that   after   completion   certificate   dated   19.02.2013 and legal notice thereafter on 16.12.2014 no objection was   raised   in   the   work   of   plaintiff."  Once   there   is   no   dispute/cross  examination of the plaintiff's witnesses on issuance of this completion  certificate the arguments of the Ld. Counsel for the defendant based  upon  Anvar   PV   (Supra)  that   no   certificate   u/s   65B   of   Indian  Evidence Act was filed along with the mail/ completion certificate can  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 16/21 be entertained. 

10.14   After   receipt   of   this   completion   certificate   i.e.   Mark  PW1/5 the defendant did not raise any objection with the plaintiff that  the plaintiff had falsely/wrongly claimed to have completed the work  or that the some work was still pending. Had that been the case there  still   might   would   have   been   some   merit   in   the   contentions   of   the  defendant   but   once   no   such   objection   is   raised   to   the   completion  certificate   than   the   plea   that   the   work   was   not   completed   or   that  incomplete work was taken by the defendant cannot be entertained. In  fact after the completion certificate the defendant admittedly released  payment of Rs. 1,81,230/­ to the plaintiff on 29.03.2013 which was  credited into the account of the plaintiff on 12.04.2013 as reflected in  Ex.   PW1/4/DW1/5.   If   indeed   the   defendant   was   compelled   to   take  incomplete or unfinished work than in my considered opinion that the  defendant would not have made the above payment to the plaintiff. The  very fact that the defendant did not agitate the issuance of completion  certificate   i.e.   Mark   PW1/5   coupled   with   the   fact   that   the   above  payment was released to the plaintiff itself proves that the plea of the  defendant is merely an afterthought to avoid the liability. 

10.15 Though Ld. Counsel  for  the  defendant  had  also  argued  that the account was duly settled with the plaintiff as is reflected in Ex. 

CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 17/21 DW1/5 and no amount remains due however I find no merits in the  said   arguments.   I   have   perused   Ex.   DW­1/5   and   the   noting   at   the  bottom of the same which reads as "full and final" "mera koi payment  company mein baki nahin hai". Though the defendant claimed that this  noting   was   made   on   behalf   of   the   plaintiff   however   I   am   of   the  considered opinion that this noting in Ex. DW­1/5 is forged, fabricated  and manipulated. To begin with the defendant did not give the name of  the person/employee who had made the above noting on behalf of the  plaintiff   company.   The   defendant   did   not   bother   to   examine   its  accountant who maintained the ledger account i.e. Ex. DW­1/5 or the  person   in   whose   presence   the   above   noting   was   allegedly   made   in  ledger. In fact the affidavit of DW­1 who had proved the said document  is absolutely silent as to the details of the person who had made the  above   noting   on   behalf   of   the   plaintiff   company   i.e.   his   name,  designation etc in the plaintiff company. In fact there is no mentioning  of any full and final payment/settlement in the written statement or the  affidavit of DW1. All this further proves that the defendant had put up  a   false   and   concocted   defence   based   upon   forged   and   fabricated  documents. 

10.16 Though Ld. Counsel for defendant had also argued that  the plaintiff had not taken the insurance cover in terms of the work  order   and   therefore,   this   itself   disentitles   the   plaintiff   to   any  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 18/21 outstanding amount, however, I find no merits in the same. To begin  with defendant could not prove that how on account of the insurance  cover not being taken by the plaintiff, the defendant suffered loss or  damages. Furthermore, DW­1 categorically admitted during the cross  examination that defendant did not suffer any loss because the plaintiff  did not take the insurance cover in terms of the work order. Hence,  merely because the plaintiff did not obtain the insurance cover this  itself does not entitle the defendant to avoid its liability. In fact the  witness (DW1) examined by defendant was not even aware about the  actual facts of the present case which is writ large from the opening  statement of his cross­examination which read as "I do not have the   knowledge what  job the plaintiff had done for the defendant".  One  cannot be expected to defend a recovery suit with such a witness and in  such a manner. 

10.17 Though Ld. Counsel for defendant argued that defendant had  to suffer damages and huge losses towards rental for providing working  platform/scaffolding for extra period of around four and a half months  as the plaintiff delayed the completion of the work and therefore, the  plaintiff   is   not   entitled   the   outstanding   amount,   however,   I   find   no  merits   in   the   same.   As   far   as   the   provision   of   working  platform/scaffolding is concerned it was the duty of the defendant to  provide the same as per the work order. Delay as already discussed  CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 19/21 above   at   length   cannot   be   attributed   to   the   plaintiff   but   the   delay  occurred on account of the delayed release of "mobilization advance" 

by   the   defendant   and   therefore,   if   the   defendant   had   to   bear   huge  rentals towards scaffolding charges only he has to bear the same and  not the plaintiff. And indeed if there was some damage or loss suffered  by the defendant due to fault or delayed execution of the work by the  plaintiff the defendant failed to prove the same. Though DW1 filed  certain   photographs   i.e.   Ex.   DW1/3   however   it   cannot   be   even  remotely guessed from the photographs as to how the defendant or the  defendant's property suffered the loss or damages as claimed by it. 
10.18 It will be worthwhile to highlight that despite such tall  claims of having suffered loss, damages and having to take incomplete,  unfinished work all of which was attributed to the plaintiff till date  defendant has not filed any suit seeking recovery of damages against  the plaintiff. If indeed there was some genuineness in the claims of the  defendant, the defendant would have definitely initiated some action  against the plaintiff. Having not done so till date is itself a proof of the  baldness of the defendant's claim. 
10.19 This issue is accordingly decided in favour of the plaintiff  and against the defendant. Plaintiff is entitled to the recovery of Rs.  94,730/­ which the defendant is liable to pay.
CS No. 51790/2016 BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society 20/21 Issue no. 2   Whether plaintiff is entitled to any interest, if yes, at  what  rate and for what period? OPP
11. As   far   as   interest   portion   is   concerned   I   award  pendentelite   and   future   interest   @   6%   per   annum   in   favour   of   the  plaintiff. This issue is accordingly decided in favour of the plaintiff.
Relief
12. Therefore   in   view   of   above   discussion   the   suit   of   the  plaintiff is decreed for a sum of Rs.  94,730/­ with pendentelite and  future interest @ 6% per annum. Decree sheet be prepared accordingly.
13. File be consigned to Record Room. 
Announced in the open court                                           (Gaurav Rao)
on 13th February 2017                                                SCJ/RC/South­East
                                                                 Saket Courts/New Delhi




CS No. 51790/2016      BBR (India) Pvt. Ltd. Vs. Satilila Charitable Society       21/21