State of Tamilnadu - Subsection

Section 11(4) in The Tamil Nadu Electricity Supply Code, 2004

(4)Where the meter becomes defective immediately after the service connection is effected, the quantum of electricity supplied during the period in question is to be determined by taking the average of the electricity supplied during the succeeding four months period after installation of a correct meter, provided the conditions in regard to the use of electricity in respect of such low tension service connection are not different. The consumer shall be charged monthly minimum provisionally for defective period and after assessment the actual charges will be recovered after adjusting the amount collected provisionally.