Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 3]

Delhi High Court

M/S Oasis Projects Ltd vs Managing Director, National Highway ... on 7 February, 2023

Author: Navin Chawla

Bench: Navin Chawla

                                 Neutral Citation Number: 2023/DHC/000828


          *        IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                         Reserved on:25.01.2023
                                                         Date of decision:07.02.2023

          +        ARB.P. 1364/2022
                   M/S OASIS PROJECTS LTD             ..... Petitioner
                                 Through: Mr. Bharat Chugh & Mr.
                                          Siddharth Shiva Kumar, Advs.
                                 versus

              MANAGING DIRECTOR, NATIONAL HIGHWAY AND
              INFRASTRUCTURE DEVELOPMENT CORPORATION
              LIMITED                           ..... Respondent
                            Through: Mr. Debal Kumar Banerjee, Sr.
                                     Adv. with Mr. Dharmender
                                     Verma & Mr. Vishal Singh,
                                     Advs.
          CORAM:
          HON'BLE MR. JUSTICE NAVIN CHAWLA

          1.       This petition has been filed under Section 11(6) of the
          Arbitration and Conciliation Act, 1996 (hereinafter referred to as the
          „Act‟) seeking appointment of an Arbitrator for adjudicating the
          disputes that have arisen between the parties in relation to the
          "Balance work for Four-Laning of NH-39 Dimapur-Kohima Road
          from Design 152.490 to Km. 166.700 (Existing Km 156.000 to Km.
          172.900), in the State of Nagaland under SARDP-NE through an
          Engineering, Procurement and Construction (EPC) Contract (Package
          -III)" (hereinafter referred to as the "Contract").
          2.       The Arbitration Agreement between the parties is contained in
          Article 26 of the Agreement, which is reproduced hereinunder:-
                                                    "Article 26
                                                Dispute Resolution
                                    26.1 Dispute Resolution

                                    (i)   Any dispute, difference or controversy of
Signature Not Verified                    whatever nature howsoever arising
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                                 Page 1 of 11
                                  Neutral Citation Number: 2023/DHC/000828


                                           under or out of or in relation to this
                                           Agreement (including its interpretation)
                                           between the Parties, and so notified in
                                           writing by either Party to the other
                                           Party (the "Dispute") shall, in the first
                                           instance, be attempted to be resolved
                                           amicably in accordance with the
                                           conciliation procedure set forth in
                                           Clause 26.2.

                                    (ii)   The Parties agree to use their best
                                           efforts for resolving all Disputes arising
                                           under or in respect of this Agreement
                                           promptly, equitably and in good faith,
                                           and further agree to provide each other
                                           with reasonable access during normal
                                           business hours to all non-privileged
                                           records,      information     and     data
                                           pertaining to any Dispute.

                                    26.2   Conciliation

                                           In the event of any Dispute between the
                                           Parties, either Party may call upon the
                                           Authority's Engineer, or such other
                                           person as the Parties may mutually
                                           agree upon (the "Conciliator") to
                                           mediate and assist the Parties in
                                           arriving at an amicable settlement
                                           thereof. Failing mediation by the
                                           Conciliator or without the intervention
                                           of the Conciliator, either Party may
                                           require such Dispute to be referred to
                                           the Chairman of the Authority and the
                                           Chairman of the Board of Directors of
                                           the Contractor for amicable settlement,
                                           and upon such reference, the said
                                           persons shall meet no later than 7
                                           (seven) business days from the date of
                                           reference to discuss and attempt to
                                           amicably resolve the Dispute. If such
                                           meeting does not take place within the
                                           30 (thirty) business day period or the
                                           Dispute is not amicably settled within 30
                                           (thirty) days of the meeting or the
                                           Dispute is not resolved as evidenced by
                                           the signing of written terms of settlement
                                           within 30 (thirty) days of the notice in
                                           writing referred to in Clause 26.1.1 or
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                                   Page 2 of 11
                                  Neutral Citation Number: 2023/DHC/000828


                                          such longer period as may be mutually
                                          agreed by the Parties, either Party may
                                          refer the Dispute to arbitration in
                                          accordance with the provisions of
                                          Clause 26.3 but before resorting to such
                                          arbitration, the parties agree to explore
                                          conciliation by the Conciliation
                                          Committees of Independent Experts set
                                          up by the Authority in accordance with
                                          the procedure decided by the panel of
                                          such experts and notified by the
                                          Authority on its website including its
                                          subsequent amendments. In the event of
                                          the conciliation proceedings being
                                          successful, the parties to the dispute
                                          would sign the written settlement
                                          agreement and the conciliators would
                                          authenticate the same. Such settlement
                                          agreement would then be binding on the
                                          parties in terms of Section 73 of the
                                          Arbitration Act. In case of failure of the
                                          conciliation process even at the level of
                                          the Conciliation Committee, either party
                                          may refer the Dispute to arbitration in
                                          accordance with the provisions of
                                          Clause 26.3.

                                    26.3 Arbitration

                                    (i)   Any dispute which remains unresolved
                                          between the parties through the
                                          mechanisms available/ prescribed in the
                                          Agreement, irrespective of any claim
                                          value, which has not been agreed upon/
                                          reached settlement by the parties, will
                                          be referred to the Arbitral Tribunal as
                                          per the Arbitration and Conciliation
                                          Act.
                                                           xxxxx"
                                                              (Emphasis supplied)

          3.       Disputes arose between the parties pursuant to the alleged
          Notice of Termination of the Contract dated 17.08.2022 by the
          petitioner and the Notice for intention to Terminate the Contract dated
          16.11.2022 issued by the respondent. The petitioner invoked the
          Arbitration Agreement vide notice dated 19.11.2022. In response, the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                                  Page 3 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          respondent, vide letter dated 25.11.2022, called upon the petitioner to
          first explore Conciliation by the Conciliation Committees of
          Independent Experts (hereinafter referred to as the „Committee‟), as
          provided in Article 26.2 of the Contract. However, the petitioner
          proceeded to file the present petition.
          4.       The learned senior counsel for the respondent maintains that the
          present petition is not maintainable as the petitioner has failed to
          follow the procedure prescribed for invocation of the arbitration, as
          contained in Article 26 of the Contract. He submits that Article 26.2
          specifically states that the parties agree to explore Conciliation by the
          Committee before resorting to arbitration. He submits that as the
          petitioner has failed to follow the said procedure, the present petition
          is liable to be dismissed on the ground of it being premature. In
          support, he places reliance on the judgment of the Supreme Court in
          Iron & Steel Co. Ltd. v. Tiwari Road Lines, (2007) 5 SCC 703 and of
          this Court in Sushil Kumar Bhardwaj v. Union of India, 2009 SCC
          Online Del 4355.
          5.       The learned senior counsel for the respondent, placing reliance
          on the judgment of Bharat Sanchar Nigam Limited and Another v.
          Nortel Networks India Private Limited, (2021) 5 SCC 738, submits
          that the petitioner approached this Court without giving adequate time
          to the respondent to reply to its request for arbitration and to bring to
          the notice of the petitioner that the Committee has been set up by the
          respondent. He submits that, therefore, the present petition is not
          maintainable.
          6.       On the other hand, the learned counsel for the petitioner submits
          that the process of Conciliation as mentioned in Article 26 is directory
          in nature. He submits that such Conciliation process cannot, in any
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                              Page 4 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          manner, affect the right of the petitioner to invoke the Arbitration
          Agreement. He further submits that before invoking arbitration, the
          petitioner had taken steps to arrive at an amicable settlement of
          disputes with the respondent, however, such attempts had failed. He
          submits that, therefore, the present petition cannot be said to be
          premature. In support, he places reliance on Visa International
          Limited v. Continental Resources (USA) Limited, (2009) 2 SCC 55;
          Ravindra Kumar Verma v. M/s BPTP Ltd. & Anr., 2014 SCC
          OnLine Del 6602; Saraswati Construction Company v. East Delhi
          Co-operative Group Housing Society Ltd., 1994 SCC OnLine Del
          563; Sarvesh Security Services Pvt. Ltd. v. Managing Director,
          DSIIDC, 2018 SCC OnLine Del 7996; Siemens Limited v. Jindal
          India Thermal Power Limited, 2018 SCC OnLine Del 7158; Union
          of India v. M/s Baga Brothers & Anr., 2017 SCC OnLine Del 8989;
          M/s Sikand Construction Co. v. State Bank of India, 1978 SCC
          OnLine Del 180; M/s IMZ Corporate Pvt. Ltd. v. MSD Telematics
          Pvt Ltd., ARB. P 204/2021; Demerara Distilleries Private Limited v.
          Demerara Distillers Limited, (2015) 13 SCC 610; Quick Heal
          Technologies Limited v. NCS Computech Private Limited, (2020)
          SCC OnLine Bom 693; and Republic of Sierra Leone v. SL Mining
          Ltd., [2021] EWHC 268 (Comm).
          7.       He further submits that the respondent having refused to give
          consent to the appointment of an Arbitrator, the petitioner need not
          have waited for a period of 30 days before approaching this Court.
          8.       He submits that as on the date of filing of the present petition,
          the website of the respondent did not reflect/provide the constitution
          or the procedure of the Committee.


Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                              Page 5 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          9.       On the submission of the website not reflecting the constitution
          or procedure of the Committee, the learned senior counsel for the
          respondent submits that though the constitution as also the procedure
          was duly available on the website of the respondent, it was available
          under the icon „MoA (Memorandum of Association) & Notices‟. He
          submits that now the same is duly reflected under a separate icon of
          „Dispute Resolution Mechanism‟. He submits that had the petitioner
          given sufficient time to the respondent to respond on the above, the
          respondent would have pointed out the icon under which the petitioner
          can access the constitution as also the procedure of the Committee.
          10.      I have considered the submissions made by the learned counsels
          for the parties.
          11.      As far as the constitution and the procedure of the Committee
          not being available on the website of the respondent on the date of
          filing of the petition is concerned, for the reason that the case of the
          petitioner is that such procedure even otherwise is directory in nature
          and is not to be mandatorily followed prior to invoking the arbitration,
          in my opinion, the same need not detain this Court any further. Prima
          facie, however, the respondent has been able to satisfy this Court that
          the information regarding the constitution and the procedure of the
          Committee was available on the website of the respondent albeit
          under an obscure link.
          12.      The primary issue to be decided in the present petition is,
          therefore, as to whether it was mandatory for the petitioner to resort to
          the Conciliation process by the Committee before invoking
          arbitration. Though Article 26.2 clearly states that before resorting to
          arbitration, the parties agree to explore Conciliation by the
          Committee, in my opinion, the same cannot be held to be mandatory
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                              Page 6 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          in nature. It needs no emphasis that Conciliation as a Dispute
          Resolution Mechanism must be encouraged and should be one of the
          first endeavours of the parties when a dispute arises between them.
          However, having said that, Conciliation expresses a broad notion of a
          voluntary process, controlled by the parties and conducted with the
          assistance of a neutral third person or persons. It can be terminated by
          the parties at any time as per their free will. Therefore, while
          interpreting Article 26.2, the basic concept of Conciliation would have
          to be kept in mind.
          13.      In addition to the above, even the Office Memorandum dated
          03.07.2020 (hereinafter referred to as the „OM‟), giving the
          establishment, constitution and procedure of the Committee, published
          by the respondent on its website, clearly evidences that such
          Conciliation process is voluntary and can be resorted to only where
          the Contractor agrees to such process after the disputes have arisen
          and inspite of the earlier agreement, as recorded in the Agreement.
          Clause 3.1 of the OM is reproduced hereinunder:-
                                    "3.1 On receipt of a reference from the
                                         Contractor (reference to Contractor
                                         made            herein           includes
                                         Consultant/Concessionaire) as per
                                         provision in the agreement for
                                         conciliation of disputes, the Concerned
                                         Technical Division shall send a
                                         response within 7 working days.
                                         NHIDCL shall offer the other party to
                                         refer the matter to the Conciliation
                                         Committee of Independent Experts as
                                         the conciliation is intended to be one
                                         consolidated package of settlement.
                                         Subject to consent of the other party, the
                                         matter would be referred to CCIE
                                         established under these guidelines."
                                                             (Emphasis supplied)


Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                                 Page 7 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          14.      A reading of the above Clause would show that the respondent,
          on receipt of a notice from the Contractor, shall „offer‟ the Contractor
          to refer the matter to the Committee. It is subject to the consent of the
          Contractor that the matter would eventually be referred to the
          Committee.
          15.      In Ravindra Kumar Verma (Supra), this Court had stated that
          any doubt on the aspect of whether Conciliation proceedings, as
          required by the arbitration clause, is directory or mandatory in nature,
          is removed when reference is placed on Section 77 of the Act, which
          reads as under:
                                    "77. Resort     to   arbitral   or      judicial
                                    proceedings

                                    The parties shall not initiate, during the
                                    conciliation proceedings, any arbitral or
                                    judicial proceedings in respect of a dispute
                                    that is the subject-matter of the conciliation
                                    proceedings except that a party may initiate
                                    arbitral or judicial proceedings where, in his
                                    opinion, such proceedings are necessary for
                                    preserving his rights."

                                                              (Emphasis supplied)

          16.      Section 77 of the Act as also Clause 16 of the OM state that
          where, in the opinion of a party, immediate initiation of the arbitral
          proceedings is necessary to preserve the rights of the said party, the
          said party may initiate arbitral or judicial proceedings even during the
          Conciliation proceedings. Therefore, in case of urgency, arbitral
          proceedings can be initiated even when conciliation proceedings are
          pending. To determine whether there is such an urgency or it is
          necessary to immediately invoke arbitration, it is the opinion of the
          party concerned which is the relevant and the governing factor. This is
          so because Conciliation, as noted hereinabove, is a voluntary process
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                                  Page 8 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          and by its very nature directory. It can be terminated at any point of
          time by any party.
          17.      In the present case, it is also to be noted that in terms of Article
          23.1(v) of the Contract, in case the respondent terminates the
          Contract, the petitioner shall be deemed to have been debarred for a
          period of two years and shall not be able to bid any Contract of the
          respondent. The petitioner also fears the invocation of the
          performance guarantee. Therefore, in terms of Section 77 read with
          Clause 16 of the OM, the petitioner is justified in expressing urgency
          in initiating arbitration for preserving its rights.
          18.      In Iron & Steel Co. Ltd. (Supra), the Court was considering an
          Arbitration Agreement which provided that the disputes between the
          parties shall be settled by arbitration in accordance with the rules of
          arbitration of the Indian Council of Arbitration. It was not disputed
          therein that the party approaching the Court did not make any effort to
          have the disputes settled in accordance with rules of arbitration of the
          Indian Council of Arbitration and, on the contrary, had straightaway
          moved an application under Section 11 of the Act. It was in those facts
          that the Supreme Court held that the agreed procedure having not been
          followed, the petition under Section 11 of the Act was not
          maintainable.
          19.      In Sushil Kumar Bhardwaj (Supra), the Court was considering
          an Arbitration Agreement wherein the Contractor was first to raise the
          dispute with the Superintending Engineer, and in case the
          Superintending Engineer fails to give his instructions or „decision in
          writing‟ or the Contractor is dissatisfied with such instructions or
          decision, the Contractor was to appeal the same to the Chief Engineer,
          „who shall afford an opportunity to the contractor to be heard, if the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                              Page 9 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          latter so desires, and to offer evidence in support of his appeal.' The
          Chief Engineer was thereafter to give his „decision‟ within a period of
          30 days of receipt of contractor‟s appeal. It was only thereafter that
          the Contractor could invoke the arbitration. In such circumstances, the
          Court held that the Contractor must follow the procedure prescribed
          before approaching the Court under Section 11 of the Act. In the said
          case, therefore, the procedure prescribed was multi-tiered and
          arbitration was to be invoked on failure of the previous stages of the
          said procedure.
          20.      As far as the submission of the learned senior counsel for the
          respondent that the petitioner should have waited for the respondent to
          have informed the petitioner of the website duly showing the
          constitution of the Committee, and, in any case, for a period of 30
          days, in my opinion, also deserves to be rejected. In Bharat Sanchar
          Nigam Limited and Another (Supra), the Supreme Court has held that
          the period for filing of the petition under Section 11 of the Act arises
          upon the failure of the parties to appoint an Arbitrator. In the present
          case, with the respondent, vide its notice dated 25.11.2022, insisting
          upon the petitioner to first initiate the Conciliation process by the
          Committee before seeking initiation of arbitration, the failure for
          appointment of the Arbitrator occurred. The present petition,
          therefore, cannot be said to be premature.
          21.      As the Arbitration Agreement and due invocation thereof are
          established, I see no impediment in appointing an Arbitrator for
          adjudicating the disputes that have arisen between the parties in
          relation to the Contract.
          22.      I accordingly appoint Mr. Justice Manmohan Sarin, Former
          Chief Justice of Jammu & Kashmir High Court, [Off. Add.: D-73
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:08.02.2023
18:27:33      ARB.P. 1364/2022                                              Page 10 of 11
                                  Neutral Citation Number: 2023/DHC/000828


          Basement, Block-D, Panchsheel Enclave, New Delhi-110017; Mobile:
          9818000210] as a Sole Arbitrator to adjudicate the disputes that have
          arisen between the parties in relation to the above Contract.
          23.      The learned Arbitrator shall give a disclosure under Section 12
          of the Act before proceeding with the reference.
          24.      The fee of the learned Arbitrator shall be in accordance with
          Schedule IV of the Act.
          25.      The petition is allowed in the above terms.


                                                                  NAVIN CHAWLA, J.

FEBRUARY 07, 2023/rv/Ais Signature Not Verified Digitally Signed By:SUNIL Signing Date:08.02.2023 18:27:33 ARB.P. 1364/2022 Page 11 of 11