[Cites 0, Cited by 2] [Section 16] [Entire Act]

State of Odisha - Subsection

Section 16(8) in The Orissa Development Authorities Act, 1982

(8)If, within a further period of one month from the date of receipt of the application drawing such attention, as mentioned in Sub-section (7), the Authority does not communicate its decision, either granting or refusing permission such permission shall be deemed to have been granted to the applicant on the date immediately following the date of expiry of the three months' period :Provided that in computing the period of two months under Sub-section (7) and further one month under Sub-section (8) the period in between the date of requisitioning any further information or documents from the applicant and the date of receipt of such information or document from the applicant shall be excluded.