Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 0]

Delhi High Court

Harish Chander & Ors. vs Hindustan Petroleum Corporation Ltd. & ... on 23 February, 2015

Author: Rajiv Sahai Endlaw

Bench: Chief Justice, Rajiv Sahai Endlaw

           *IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                      Date of decision: 23rd February, 2015

+      W.P.(C) No.2611/2012 & CMs No.5584/2012 (for stay), 5729/2013
       (for directions), 16629/2013 (for disposal of CM No.5729/2013) &
       969/2014 (for rectification of order dated 18.12.2013)

       HARISH CHANDER & ORS.                  ..... Appellants
                   Through: Ms. Indira Unninayar with Ms. Kirat
                            Randhawa & Mr. Narayan Krishan,
                            Advs.

                                     Versus

    HINDUSTAN PETROLEUM
    CORPORATION LTD. & ORS.                  ..... Respondents
                  Through: Mr. Kailash Vasdev, Sr. Adv. with
                           Mr. P. Sinha, Ms. Reshmi Rea Sinha
                           & Mr. Avneesh Garg, Adv. for R-
                           1/HPCL.
                           Mr. Ripu Daman Bhardwaj, CGSC
                           with Mr. T.P. Singh, Adv. for R-2 to 7
                           & 14 / UOI.
                           Ms. Ferida Satarawala, Adv. for
                           GNCTD.
                           Mr. Amitabh Marwah, Adv. for DDA.
CORAM:-
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

RAJIV SAHAI ENDLAW, J

1.     This petition under Article 226 of the Constitution of India, filed as a

Public Interest Litigation (PIL), seeks the reliefs of:


W.P.(C) No.2611/2012                                            Page 1 of 59
        (a)     restraining the Hindustan Petroleum Corporation Ltd. (HPCL)

               (respondent No.1) from constructing and operating its Petroleum

               Storage Depot at Tikri Kalan;


       (b)     a direction to the HPCL to shift / re-site its Petroleum Storage

               Installation to a safe distance of a minimum of 10 to 15 Kms. from

               the village Tikri Kalan, thereby excluding the residents of village

               Tikri Kalan from the high risk zone in case of fire, explosion or

               any other accident / incident in the said Petroleum Storage

               Installation;


       (c)     a direction to the Government of National Capital Territory of

               Delhi (GNCTD) (respondent No.11) to identify appropriate

               alternative land for re-locating the said petroleum storage depot of

               HPCL at a safe distance from population / populated areas;


       (d)     a declaration that the Environment Clearance dated 24th August,

               2009 granted by the Ministry of Environment and Forests

               (MOEF), Government of India (respondent No.7) for setting up of

               petroleum storage depot at Tikri Kalan is void ab initio and a writ

               quashing the same;

W.P.(C) No.2611/2012                                               Page 2 of 59
        (e)     quashing of the "consent order" if any issued by the Delhi

               Pollution Control Committee (DPCC) (respondent No.8);


       (f)     quashing of the clearances / NOC if any issued by the Petroleum

               and Explosives Safety Organization (PESO) (respondent No.6),

               Ministry of Petroleum and Natural Gas (MoP&NG) (respondent

               No.4) and Oil Industry Safety Directorate (OISD) (respondent

               No.5) for setting up of the said oil storage depot;


       (g)     quashing of the Zonal Plan dated 9th June, 2010 of the Delhi

               Development Authority (DDA) (respondent No.12) and the Clause

               6.3 of the Master Plan of Delhi (MPD) notifying the said land near

               / in Tikri Kalan as a major storage site for oil;


       (h)     a direction to the MoP&NG to incorporate mandatory safety

               norms for installation of oil and petroleum storage depots in the

               Petroleum Rules, 2002;


       (i)     a direction to the OISD to declare as mandatory and ensure

               compliance of the appropriate safety norms and safety standards

               with regard to installation of petroleum / oil depots all over India;



W.P.(C) No.2611/2012                                                 Page 3 of 59
        (j)     a direction to the National Disaster Management Authority

               (NDMA) (respondent No.2) and Delhi Disaster Management

               Authority (DDMA) (respondent No.9) to review the instant

               installation of HPCL‟s petroleum / oil storage depot at Tikri Kalan

               in the light of M.B. Lal Committee report;


       (k)     a direction to the Delhi Fire Service Authority (DFSA)

               (respondent No.13) to review the instant installation;


       (l)     a direction to the NDMA to ensure compliance of Safety

               Guidelines / procedures into Disaster Management Guidelines;


       (m)     a direction to the DDMA and the Government of India to

               prominently publish its final Chemical Disaster Management

               Guidelines;


       (n)     a direction to the National Executive Committee for Disaster

               Management (NECDM) (respondent No.3) to prepare a proper

               National Plan for Disaster Management;




W.P.(C) No.2611/2012                                                Page 4 of 59
        (o)     a direction to the NDMA to mandate safety audits before setting

               up of hazardous Petroleum Storage Installations and to review

               from time to time adherence to safety by such installations;


       (p)     a direction to the DDMA to formulate policies for installation of

               petroleum / oil depots; and,


       (q)     a direction to the State Executive Committee of Delhi for Disaster

               Management (respondent No.10) to ensure coordination between

               all concerned agencies of Delhi for setting up / implementation of

               any project.


2.     It is inter alia the case of the seven petitioners, all of whom claim to be

residents of village Tikri Kallan:


       (i)     that village Tikri Kalan situated in West Delhi has around 25,000

               to 30,000 inhabitants and the surrounding areas within a radius of

               1 to 2 Kms. also have around 1.5 to 2 lakhs population, spread

               over several villages;




W.P.(C) No.2611/2012                                               Page 5 of 59
        (ii)    that HPCL has set up a Petrol Storage Installation at Tikri Kalan,

               without adhering to the necessary distance for the purpose of

               safety;


       (iii)   that the said Petrol Storage Installation violates the right of the

               petitioners and the other residents of village Tikri Kalan to live in

               a safe environment;


       (iv)    that the said Petrol Storage Installation is at a dangerously close

               distance of only 1440 odd feet i.e. 440 mtrs. from the residences;


       (v)     that the boundary wall of the installation is at a distance of 180

               feet i.e. 55 mtrs. only from the residences of villagers;


       (vi)    that Tikri Kalan also has bottling plants for Liquefied Petroleum

               Gas (LPG) of Indian Oil Corporation Ltd. (IOCL), HPCL as well

               as Bharat Petroleum Corporation Ltd. (BPCL);


       (vii) that after a major fire in 1995 in Jwala Puri and in the light of the

               hazards of the plastic industry, Delhi‟s largest plastic waste

               industry was also in or about the year 2000 shifted to Tikri Kalan;




W.P.(C) No.2611/2012                                                 Page 6 of 59
        (viii) that a major fire at the IOCL Petroleum Storage Depot near Jaipur

               on 29th October, 2009 had left 11 dead and 150 injured; the area

               within 5 Kms. radius of the said depot was reported as „danger

               zone‟;


       (ix)    that a seven Member Committee headed by former HPCL

               Chairman M.B. Lal was constituted to submit a report on the

               Jaipur fire;


       (x)     that M.B. Lal Committee reported the impact of fire upto 2 Kms.

               or more from the site; and,


       (xi)    that the representations of the petitioners commencing from 11th

               February, 2010 till the filing of the petition in or about April, 2012

               remained unheeded.


3.     The petition came up before this Court first on 2 nd May, 2012 when

notice, only to HPCL, NDMA and DDMA was issued.


4.     HPCL filed an affidavit pleading:


       (a)     that in view of the fire that took place in the Army Ordinance

               Depot adjoining the Oil Storage Depot / Tanks of HPCL at Shakur

W.P.(C) No.2611/2012                                                 Page 7 of 59
                Basti, Delhi, all the Oil Marketing Companies (OMCs) were

               advised to shift the existing Petroleum Products Storage

               Installations from Shakur Basti;


       (b)     that pursuant thereto process of land acquisition for Petroleum Oil

               Terminals across the National Highway-10 from village Tikri

               Kalan was initiated in the year 2004 and suitable land was

               identified along with the DDA in accordance with the Zonal

               Development Plan, Planning Zone-L, West Delhi-III as per MPD-

               2021;


       (c)     that Notification under Section 4 of the Land Acquisition Act,

               1894 was published on 20th January, 2009 in respect of land ad-

               measuring 145 Bighas for construction of HPCL‟s terminal;

               thereafter notifications under Section 17(1) and under Section 6 of

               the Land Acquisition Act were issued and published on 25 th

               February, 2009;


       (d)     that MPD-2021 authenticated by Government of India on 9th June,

               2010 also mentions that Shakur Basti Oil Depot had been shifted



W.P.(C) No.2611/2012                                              Page 8 of 59
                to a site between Ghevra and Tikri Kalan which will be a major

               storage site for oil;


       (e)     that HPCL, for setting up of its Terminal on the land, obtained:


               (i)     Environment Clearances dated 24th August, 2009 from the

                       MOEF:


               (ii)    Layout Approval dated 27th October, 2009 from PESO;


               (iii)   Consent dated 23rd December, 2009 of the DPCC;


               (iv)    Approval dated 2nd August, 2011 from the Chief

                       Inspectorate of Factories, GNCTD.


       (f)     that HPCL, while setting up the Terminal, complied with the

               provisions of the Petroleum Act, 1934, Petroleum Rules, 2002

               framed thereunder and the OISD-118 as well as the Local Building

               Byelaws;


       (g)     that the center line of the tank farm containing the storage tanks

               storing High Speed Diesel, Superior Kerosene Oil and




W.P.(C) No.2611/2012                                               Page 9 of 59
                Petrol/Motor Spirit is 430 mtrs. away from the village side edge of

               the National Highway;


       (h)     that HPCL has left a distance of 125 mtrs. from the center line of

               National Highway, as against the required distance of 61.96 mtrs.;


       (i)     that construction activity for the said Terminal was commenced in

               the year 2009 and had been completed and the Terminal is ready

               though operations had not begun awaiting some fire-fighting

               equipment which are 100% in line with OISD-117, as revised,

               subsequent to the M.B. Lal Committee report;


       (j)     that the said terminal could not be compared with the IOCL‟s

               Terminal at Jaipur where the incident of fire had occurred; the said

               IOCL Terminal was three times larger than the said Terminal and

               the fire water storage capacity of the said terminal is more than

               double of the IOCL‟s Jaipur Terminal;


       (k)     that HPCL and BPCL‟s terminals in close vicinity of IOCLs Jaipur

               terminal were not affected;




W.P.(C) No.2611/2012                                               Page 10 of 59
        (l)     that each oil installation has to be analyzed for risks and safety

               provisions on its own merits and there can be no blanket

               comparison;


       (m)     that the re-sitement of the HPCL terminal from Shakur Basti to

               across the National Highway-10 from village Tikri Kalan was at a

               cost of about Rs.190 crores;


       (n)     that the operation of the said terminal would avoid the current risk

               of surface transportation; the input to Shakur Basti installation was

               through railway / tank wagons; the input to said terminal will be

               through dedicated underground cross-country pipeline thereby

               ensuring environment friendliness, safety and faster movement of

               the product;


       (o)     that prior to setting up of the said terminal, Environmental Impact

               Assessment and Risk Analysis was carried out in July, 2009;


       (p)     that the probability of leakage due to tank failure and mechanical

               seal failure or other causes is very low in view of stringent




W.P.(C) No.2611/2012                                                Page 11 of 59
                precautions taken in the design and construction of the said

               installation;


       (q)     that the Environment Impact Assessment (EIA) and Risk Analysis

               report were studied by the DPCC and consent given thereafter

               only;


       (r)     that subsequent to the incident of fire at IOCL‟s Jaipur Terminal

               and in line with the M.B. Lal Committee‟s recommendation,

               Quantitative Risk Assessment Studies were carried out in

               February, 2012 and whose report revalidated the findings of the

               earlier Risk Analysis Studies / reports;


       (s)     that as per the said report, the impact areas under various scenarios

               fall within the premises of the said Terminal;


       (t)     that the extent of area impacted in the remotest possible event of

               vapor cloud explosion also falls within the boundary wall of

               HPCL‟s said terminal;


       (u)     that the said terminal is constructed in accordance with MPD-2021

               as well as OISD-118 and HPCL has taken all necessary


W.P.(C) No.2611/2012                                                Page 12 of 59
                precautions reviewed by various authorities such as MOEF,

               DPCC, PESO and Chief Factory Inspectorate‟s Office, thereby

               ensuring that risk, if any, is contained within HPCL‟s said

               Terminal;


       (v)     that OISD-118 relates to the layout of the petroleum storage

               installation and OISD-117 relates to fire safety measures to be

               taken for an oil storage installation;


       (w)     that detailed particulars running into as many as 100 items, of the

               compliances done for OISD-117 pre M.B. Lal Committee

               recommendation and running into 13 items for OISD-117 post

               M.B. Lal Committee‟s recommendations are given; and,


       (x)     that HPCL has thus taken all necessary steps towards fire safety

               including those in the M.B. Lal Committee‟s report.


5.     The petitioners have filed a response to the aforesaid reply affidavit of

HPCL inter alia pleading:


       (I)     that the money already spent by HPCL cannot be a relevant factor

               inasmuch as the loss estimated in the M.B. Lal Committee‟s report


W.P.(C) No.2611/2012                                              Page 13 of 59
                with respect to the incident of fire at IOCL‟s Jaipur storage was of

               approximately Rs.280 crores besides the loss of 11 lives;


       (II)    that safety has to be the primary concern;


       (III) that moreover the petitioners had been representing for stoppage of

               the construction work since before it began;


       (IV) that the M.B. Lal Committee had recommended a buffer safety

               zone around High Hazardous Petroleum Installations and had

               reiterated that from the explosion, buildings close to the boundary

               wall had also been damaged;


       (V)     that 1440 feet will not be an adequate buffer should there be any

               disaster;


       (VI) that Tikri Kalan is surrounded by highly inflammable industries

               and even a slight spark in the area can set off an eminently

               preventable disaster by just ensuring adequate distance / safety

               buffer;




W.P.(C) No.2611/2012                                               Page 14 of 59
        (VII) that the issue is not with respect to putting out a fire but of the

               inherent lack of safety in setting up petrol storage depots near

               thickly populated areas;


       (VIII) that though the reason for shifting of oil depots of IOCL, BPCL as

               well as HPCL from Shakur Basti was a fire which took place in

               the Army Ordinance Depot adjoining the said oil storage depots

               yet in re-locating the oil storage depots, the said concern had been

               ignored;


       (IX) that since the decision in 2001, Tikri Kalan has become thickly

               populated.


6.     DDMA in its counter affidavit dated 25th August, 2012 pleaded that

HPCL‟s Petroleum Storage Depot at village Tikri Kalan was surveyed on 30th

May, 2012 and the Surveying Committee had recommended that a Consultant

be appointed to suggest measures to augment safety of the areas surrounding

the depot and the said proposal was under consideration. The District Disaster

Management Plan of West District within whose jurisdiction village Tikri

Kalan falls was also enclosed to the said affidavit.



W.P.(C) No.2611/2012                                               Page 15 of 59
 7.     It was however the contention of the counsel for the petitioners that the

said affidavit of the DDMA was contrary to the report of the survey got

conducted by the DDMA;


8.     A perusal of the said survey report showed the surveying committee to

have observed:


       (A)     that the HPCL‟s plant was located at a distance of approximately

               500 mtrs. from the residential area of village Tikri Kalan and that

               distance is not enough in case of any major disaster spreading out

               of the plant;


       (B)     that HPCL has an elaborate Internal Disaster Management Plan

               but there was no External Disaster Management Plan till then;


       (C)     that the location of LPG bottling plan nearby also poses some

               threat to the nearby localities but the PVC bazar is located quite far

               away from the HPCL‟s plant and does not pose any imminent

               danger in case of any major incident;




W.P.(C) No.2611/2012                                                 Page 16 of 59
        (D)     that there is a need of Comprehensive External Disaster Plan for

               handling the major disasters in the vicinity of HPCL plant in case

               of any accident or disaster inside the plant; and


       (E)     that there is also a need to have an expert opinion on explosions,

               fire and other eventualities like projectiles due to presence of large

               number of LPC cylinders in nearby LPG bottling plant etc. and a

               comprehensive disaster mitigation plan should be formulated for

               external areas of those plants;


9.     In view of the said survey report, this Court vide order dated 24th

January, 2013 on the application filed by the petitioners along with the writ

petition for interim reliefs, restrained HPCL from commencing the operation of

the subject project without seeking specific permission from the Court. The

said interim order has continued in force till now.


10.    HPCL filed CM No.5729/2013 dated 7th May, 2013 seeking permission

to commence operations, detailing the steps taken by it for a comprehensive

emergency response and disaster management plan for handling any major

disaster in the vicinity of the terminal in case of occurrence of any accident /



W.P.(C) No.2611/2012                                                 Page 17 of 59
 disaster inside the terminal. In the affidavits subsequently filed in support of

the application, it was inter alia pleaded:


               (i)     that a Fire Safety Certificate dated 11th November, 2012 for

                       occupancy of the said storage depot had been obtained from

                       Delhi Fire Services;


               (ii)    that Delhi Fire Service was satisfied that HPCL, besides

                       fulfilling the standards laid down by the OISD, had also

                       made       additional   provisions   for   detection    and      fire

                       suppression using inert gas for electrical panels and by

                       providing additional water monitors in the tank farm to

                       provide effective water curtain between the tanks for

                       restricting the heat retention from one tank to another;


               (iii)   that the ACP (Licensing for Storage of Petroleum Products)

                       also had given a NOC dated 3rd December, 2012 with

                       respect to the said storage depot after inspecting the safety

                       aspects;




W.P.(C) No.2611/2012                                                    Page 18 of 59
                (iv)    that in consultation with DDMA, a Consultant had been

                       appointed for carrying out Qualitative Risk Assessment /

                       Emergency Response and Disaster Management Plan with

                       respect to the three plants separately as well as together;


               (v)     that on 7th March, 2013 and 11th March, 2013, mock drills

                       were conducted by the Consultant with the involvement of

                       all the agencies including DDMA and prominent villagers

                       of Tikri Kalan;


               (vi)    that the Consultant also in its report had stated that the

                       distance of Tikri Kalan village border from the incident

                       point is 440 mtrs. and thus the village will have no risk due

                       to heat radiation also;


               (vii) that the consultant had found that the probability of

                       happening of such an incident itself is five in ten lakhs per

                       annum;


               (viii) that the Consultant had further reiterated that even in the

                       worst case scenario of fire / disaster at the HPCLs plant,



W.P.(C) No.2611/2012                                                  Page 19 of 59
                        towards Tikri Kalan village, the impact thereof will be

                       totally contained within the HPCL installation only;


               (ix)    that safety and firefighting equipment in line with M.B. Lal

                       Committee recommendations and revised OISD standards

                       had been installed;


               (x)     that arrangements have been made for deploying trained

                       manpower for safe operation of the facility;


               (xi)    that HPCL being a Government company is fully committed

                       to the issue of safety and has taken and will at all time take

                       all steps so that its installation does not pose any safety risk

                       to any inhabitants;


11.    It was further pleaded in the affidavit accompanying the said application

that the petitioners and other villagers of Tikri Kalan did not challenge the

acquisition of the land for the purpose of setting up of the said terminal of

HPCL and rather accepted the acquisition by accepting compensation without

demur and even thereafter did not challenge the installation of the said terminal




W.P.(C) No.2611/2012                                                   Page 20 of 59
 till 2012 and filed the writ petition only when the terminal was ready to be

commissioned.


12.    It was yet further pleaded that the Comprehensive Disaster Management

Plan (CDMP) prepared by the Consultant had been forwarded to the DDMA

and thus the reasons for which this Court had vide order dated 24th January,

2013 restrained HPCL from commissioning the subject storage depot stood

satisfied.


13.    DDMA filed a response dated 30th May, 2013 to the application aforesaid

of the HPCL for commissioning of the storage depot, stating:


       (i)     that HPCL, pursuant to the interim order dated 24th January, 2013

               (supra) had submitted to the DDMA a CDMP of its storage plant,

               LPG Bottling Plant of IOCL and Oil Terminal of IOCL at Tikri

               Kalan, prepared by M/s International Certification Services Pvt.

               Ltd.;


       (ii)    that as a norm, DDMA conducts and puts such plan to test /

               analysis on the ground, in order to determine their actual

               feasibility and their ability to achieve the targeted results;



W.P.(C) No.2611/2012                                                   Page 21 of 59
        (iii)   that accordingly, a mock drill with the help of all Emergency

               Support functionaries with respect to the CDMP submitted by

               HPCL will be conducted;


       (iv)    that in this mock drill Indian Army as well as a third party

               observer as well as prominent villagers of the area were also

               scheduled to be involved;


       (v)     that only after such mock drill would the DDMA be able to check

               the preparedness level of HPCL;


       (vi)    that the said CDMP submitted by HPCL was also to be forwarded

               to the NDMA and the National Institute of Disaster Management

               (NIDM) for their comments and suggestions as both the said

               institutions are the apex bodies for disaster management at

               national level;


       (vii) that DDMA would also be consulting the neighbouring North-

               West district as inter-district coordination is very important and

               necessary in case of any eventuality;




W.P.(C) No.2611/2012                                              Page 22 of 59
        (viii) that after completion of the said mock drill, a observation report

               will be obtained from the Indian Army and on the basis of which

               final report of the mock drill will be prepared by the DDMA and

               submitted before the Court;


       (ix)    that DDMA would be able to respond to the request of the HPCL

               for commissioning of the plant only after the mock drill is

               conducted and the targeted results as claimed by the CDMP

               achieved;


       (x)     that the area surrounding the plant, to the extent 1 to 2 kms. has a

               population of 1.5 to 2 lakhs villagers and it is vital to ensure and

               protect their safety;


       (xi)    that the CDMP submitted by HPCL was a piece of paper till the

               efficacy thereof is established in the mock drill; and,


       (xii) however with the submission of the Comprehensive Emergency

               Response and Disaster Management Plan, HPCL had complied

               with all the requirements for commissioning and operation of its

               Tikri Kalan Oil Terminal.



W.P.(C) No.2611/2012                                                 Page 23 of 59
 14.    Needless to state, the petitioners contested the application aforesaid of

HPCL for commissioning of the storage depot by filing reply thereto but at this

stage, it is not deemed necessary to detail the contents thereof.


15.    HPCL filed rejoinder to the response aforesaid of DDMA stating:


       (a)     that DDMA on 27th June, 2013 had conducted the mock drill

               aforesaid in the presence of an independent observer and the

               villagers of Tikri Kalan including the petitioner No.1;


       (b)     that in the mock drill the working of the Comprehensive

               Emergency Response and Disaster Management Plan got prepared

               by HPCL was checked;


       (c)     that HPCL had complied with all the relevant statutory provisions

               including Rules, Regulations, Guidelines and / or Notification in

               this regard; and,


       (d)     however if any of the statutory authorities indicate any other

               requirement to be fulfilled, HPCL is ready and willing to comply

               with the same for the safety and security of the villagers of Tikri

               Kalan and other neighbouring villagers.


W.P.(C) No.2611/2012                                                Page 24 of 59
        The said rejoinder was accompanied with a note on the sequences of

events during the mock drill and the photographs thereof which also show the

independent observer participating in the mock drill interacting with the

villagers.


16.    DDMA also submitted to this Court a report of the mock drill conducted

on 27th June, 2013 along with the report of the independent observer who had

participated therein.


17.    DDMA in the said report, while analyzing the mock drill, in the column

"strength"     of      the   Comprehensive    Emergency      Response      &     Disaster

Management Plan inter alia observed that the Fire Hydrant System of HPCL

and IOCL worked properly - within few seconds of the incident the Fire-

dousing equipment were made operational effectively to control the fire. In the

column of „weakness and suggestions‟, the report is that;


               (A)      the site being situated in a remote area, the response time by

                        most of the departments was not very good;


               (B)      the movement of emergency vehicles was obstructed by

                        heavy traffic on the access roads;



W.P.(C) No.2611/2012                                                    Page 25 of 59
                (C)     the security staff of HPCL and IOCL needs to be trained

                       more professionally on search and rescue techniques and

                       first aid;


               (D)     proper signage board of emergency exit needs to be

                       displayed at different suitable locations in the premises of

                       both the plants;


                (E)    awareness generation-cum-orientation programme about

                       disaster management should be conducted in the nearby

                       areas of these plants; and,


               (F)     there should be mutual collaboration between management

                       of both the plants to cope up with such incidents more

                       effectively.


18.    The independent observer of the mock drill has inter alia reported that:


       (i)     the response of HPCL for the on-site emergency was very good;


       (ii)    two fire tenders reported immediately including one which is

               stationed within the premises and started the fighting;



W.P.(C) No.2611/2012                                                Page 26 of 59
        (iii)   the hydrants were also started;


       (iv)    in the tanks in the vicinity of the tank where the incident was

               simulated, water sprinklers were started;


       (v)     foam had started spilling inside automatically to douse the fire

               instantly;


       (vi)    rescue team with stretchers and first aid team with the first aid box

               reached the disaster site;


       (vii) though the disaster was managed within the boundary of HPCL

               but by way of abundant caution emergency was also declared off-

               site;


       (viii) the police, fire services and the ambulance services reached the

               disaster site beyond the acceptable response time owing to heavy

               traffic on the access roads;


       (ix)    HPCL‟s storage depot is fully automated with entry and exit

               control and an integrated tank farm management system;




W.P.(C) No.2611/2012                                                Page 27 of 59
        (x)     each tank is provided with radar type level transmitter, multi

               element averaging temperature sensor, water / product interface

               measurement and pressure transmitters for density measurement;


       (xi)    indication is available locally in the tank side display unit as well

               as in the control room;


       (xii) high velocity long range automated TT loading facility, automated

               fire alarm / fighting facility and fairly good communication system

               exists;


       (xiii) emergency shut down is in the terminal control room to stop all

               dispatch operation;


       (xiv) Emergency push button to stop all road loading operations are

               provided on either side of the gantry and one in the middle of the

               gantry and also in the control room;


       (xv) that the representatives of Tikri Kalan witnessing the mock drill

               did not want to listen to the logic that the storage depot was more

               modern, more safe and adhered to the laid down safety and

               security norms and continued to complain about the nearness of


W.P.(C) No.2611/2012                                                Page 28 of 59
                the installation and the fear of a disaster and blamed their earlier

               Sarpanch who had given the NOC on behalf of the village.


19.     The independent observer has inter alia recommended; i) that the control

room should preferably be at a higher floor from where the whole plant is

visible; ii) the control room should have a fire proof glass for functioning even

during disasters; and, iii) planting of more trees with shade within the premises

of HPCL.


20.     Thereafter, when the matter was listed before this Court on 22 nd August,

2013, though earlier notice of the petition had been issued only to HPCL,

DDMA and NDMA, notice of the petition was issued to the other respondents

also.


21.     In response thereto, DPCC has filed a counter affidavit stating that the

Environment Clearance was granted first for laying down of the pipeline from

Bahadur Garh to Tikri Kalan by HPCL and thereafter for setting up of the oil

depot at Tikri Kalan for storage of petroleum products and that the said storage

terminal had been established at site which had been specifically earmarked and

provided under the MPD-2021 for the said purpose and that the consent given

was valid and does not suffer from any infirmity. It is further stated that the

W.P.(C) No.2611/2012                                               Page 29 of 59
 storage of petroleum products is not an activity which would fall in the „Red‟

category of industries as per Classification list of industries under the DPCC

consent policy.


22.    DDA in its counter affidavit has stated:


       (a)     that MPD-2021 was prepared in accordance with the relevant

               provisions of the Delhi Development Act, 1957 and was approved

               by Central Government and notified on 7th February, 2007;


       (b)     generally speaking, a proposal is made and public objections /

               suggestions are invited under Section 11(a) of the Delhi

               Development Act;


       (c)     in the said public notice, the period prescribed for receipt of

               objections and suggestions is 30 to 45 days from the date of the

               notice;


       (d)     the objections and suggestions received are placed for hearing

               before the Board consisting of Engineer Member, DDA as

               Chairman and the Finance Member, DDA and other persons and

               other non official authority members;


W.P.(C) No.2611/2012                                             Page 30 of 59
        (e)     the Board thereafter gives its recommendations which are put up

               before the Competent Authority comprising of Lieutenant

               Governor, Vice Chairman, DDA and others including elected

               members of Legislative Assembly;


       (f)     the competent authority is empowered to accept / reject or modify

               the recommendations;


       (g)     the Scheme known as "Rohtak Road Scheme" was formulated by

               the DDA for 556 hectare of land falling in between Railway Line

               of Rohtak Road in West Delhi, for industrial / wholesale /

               warehousing use;


       (h)     a public notice inviting objections / suggestions for the purpose of

               change of land use was published in the newspapers on 30 th

               August, 1997;


       (i)     after examination of objections / suggestions, the proposed change

               of land use of 556 hectares of Rohtak Road Scheme were duly

               considered as per legally mandated procedure;




W.P.(C) No.2611/2012                                               Page 31 of 59
        (j)     the land use plan of Rohtak Road Scheme was processed as part of

               the MPD-2021 and a draft land use plan containing Rohtak Road

               Scheme was published for objections / suggestions in March /

               April, 2005;


       (k)     that after consideration of the objections / suggestions, MPD 2021

               as per legally mandated procedure as aforesaid was notified on 7th

               February, 2007;


       (l)     that it was the decision of the Government of India to relocate

               Shakur Basti oil depots to a site between village Ghevra and

               village Tikri Kalan which was to be a major oil storage site and the

               same is reflected in Clause 6.3 of MPD-2021;


       (m)     that the oil storage depots are required for the captive requirement

               of the city of Delhi and needs to be located in Delhi due to

               operational difficulties outside Delhi;


       (n)     the decision for relocating the oil depots at Shakur Basti to the said

               location was taken in the year 1980-85 and MPD-2001 was




W.P.(C) No.2611/2012                                                 Page 32 of 59
                notified in August, 1990 when the said area was sparsely

               populated and was predominately rural;


       (o)     however due to massive increase in population, the said area has

               become thickly populated and has changed its character from rural

               to urban.


23.    The petitioners thereafter applied for impleadment of Union of India

through the Ministry of Urban Development as respondent to the petition and

which was allowed vide order dated 21st April, 2013. We may also add that the

petitioners have filed rejoinders to all the counter affidavits, denying contents

thereof, but need is not felt to burden this judgment with content thereof also.


24.    We heard the counsels for the parties on 9th & 10th October, 2014 and

reserved judgment.         The petitioners however filed an application for further

hearing of the petition. Though the said application was dismissed on 29 th

October, 2014 but fresh written arguments submitted by the counsel for the

petitioners were taken on record.


25.    As would be obvious from the counter affidavits of HPCL and other

respondents, the subject oil storage depot is situated on a land earmarked in the



W.P.(C) No.2611/2012                                                Page 33 of 59
 Master Plan for the said purpose and has been set up after obtaining all

approvals, permissions, consents under all applicable laws, rules, regulations

and notifications. Though, till the date of filing of this petition and also till the

date of subject oil storage depot becoming ready for commissioning,

Comprehensive Emergency Response and Disaster Management Plan, as was

required to be in place as per the conditions of the approvals, consents,

permissions granted for setting up of the oil storage depot, was not in place but

now the same is also in place and has also been checked / tested in the mock

drill. It cannot thus be said that the setting up of the said oil storage depot is in

contravention of any law, rule and regulation for this Court to interfere on such

ground.


26.    The petitioners have however, also impugned the consents, permissions

and approvals given by the various authorities for setting up of the said oil

storage depot and sought the relief of setting aside thereof. The petitioners in

this regard rely on the recommendations of the M.B. Lal Committee‟s report.


27.    PESO in its counter affidavit, with respect thereto has stated that the said

recommendations have not been accepted by the Government and to be




W.P.(C) No.2611/2012                                                Page 34 of 59
 actionable, have to be incorporated in the Petroleum Rules, 2002 and which has

not been done.


28.    Perhaps, being fully aware of this fact, the petitioners have also sought

the relief of issuance of a direction for amendment of the said Rules. However

though the said relief was claimed but Union of India (UOI) against which the

said relief could have been granted was not even impleaded as a party in the

petition as originally filed. Though UOI has subsequently been impleaded as a

respondent but we do not feel the need for entertaining the said aspect in the

present case for the reason that the independent observer has opined that the

subject oil storage depot is compliant with the M.B. Lal Committee

recommendations also. We may record that no response has been filed by UOI

and the counsel for the petitioners, at the time of hearing, did not press for

amendment of the Petroleum Rules and which relief indeed cannot be granted.

The Petroleum Rules have been framed by the Central Government in exercise

of legislative power in this regard conferred on it by the Petroleum Act, 1934

and are a piece of subordinate legislation. We have recently in Mool Chand

Kucheria Vs. Union of India MANU/DE/1338/2014, on the conspectus of a

host of precedents, held that no direction amounting to compelling the

Government to initiate legislation can be given. The Supreme Court thereafter

W.P.(C) No.2611/2012                                            Page 35 of 59
 in Manoj Narula Vs. Union of India (2014) 9 SCC 1 has reiterated the

principle. In this respect, the pleadings of HPCL, of the subject oil depot

having been equipped with latest inbuilt technology to contain the incident, if

any occurs, of fire / blast also cannot be brushed aside. We have no reason to

doubt the said pleas.      Ignoring such scientific advancements and new

technology, even when made available, would tantamount to not availing

benefit thereof inspite of the energy, time, effort and resources including

monetary and human expended in research, innovation, development and

installation thereof and would not be wise. We have all experienced, the huge

space earlier occupied by library in law offices being freed and becoming

available, with the books being compacted in a disk or a pen-drive. The plea of

the HPCL is to the same effect i.e. of the buffer distance which was earlier

required to be maintained having been shortened with the advent of new safety

technology.


29.    It cannot also be lost sight of that as per the MPD-2001 as well as MPD-

2021, the prescribed user of the subject land is for the purpose of oil

installations only. Being fully aware of the same also, the relief of quashing the

same also has been claimed in the petition but again without impleading the

UOI. Though UOI has subsequently been impleaded but the petitioners have

W.P.(C) No.2611/2012                                              Page 36 of 59
 neither pleaded not argued any basis for claiming the relief of quashing of the

Clause of the MPD-2021 prescribing such use of the subject land. DDA in its

counter affidavit has already elaborated the process that goes into the making /

drafting of a Master Plan, including of inviting objections from the public to the

proposed use. There is no explanation whatsoever as to why the petitioners or

for that matter, any other residents of the village Tikri Kalan or neighbouring

villages did not object. They are thereby deemed to have consented to such

land use and are now estopped. The present is a case, not only of the said

residents / villagers having not objected but also of the subject land having been

acquired from them for the said purpose. At that time also, they did not

contend that the purpose stated for acquisition, in this context, was not a public

purpose. There can thus be no manner of doubt whatsoever that the said

residents / villagers were fully aware of the use to which the land being

acquired from them will be put. Thereafter also, they did not object to the

setting up of the LPG bottling plants of HPCL, IOCL and BPCL.


30.    The only other ground on which the petitioners sought to challenge the

permissions granted was qua the subject installation being a „Red Category‟

industry. However, as aforesaid, DPCC in its counter affidavit has explained

that though in the draft of the Prevention and Control of Pollution (Uniform

W.P.(C) No.2611/2012                                              Page 37 of 59
 Consent Procedure) Rules, 1999, the activities of storage, transfer and

processing of petroleum products was shown in the list of „Red Category‟

industries but the said Rules have not been notified till date. DPCC has also

explained that as per the draft Rules also, there is a provision for granting

sanction to the „Red Category‟ industries and it cannot thus be said that such

industries are prohibited for which no consent can be given.


31.    The petitioners, along with the petition have not filed any documents

showing the boundaries of the residential abadi of village Tikri Kalan as they

existed at the time of acquisition of the subject land or as to how far the said

abadi then was from the acquired land. The petitioners have also not filed any

documents to show the title to the land within 500 mtrs. or for that matter 1

k.m. of the subject oil depot i.e. whether it is government land or the land of the

Gram Sabha or belongs to any individual. We had during the hearing enquired

from the counsel for the petitioners that what would be the position if the

persons stated to be residing in close proximity to the subject oil depot were to

be encroachers and unauthorized occupants on public land and whether such

persons after first settling down in close proximity to an establishment, whether

for the reason of seeking employment therein or for otherwise earning

livelihood from activities ancillary to that establishment can subsequently turn

W.P.(C) No.2611/2012                                               Page 38 of 59
 around and complain that the activities being carried on in the establishment

pose a danger to their life and the establishment should be shut down.


32.    The counsel for the petitioners of course contended that no such issue

had been raised and the petitioners were thus not required to make any such

pleadings or file any such documents.


33.    However we do not even know what is the prescribed user of the land,

residences whereon are stated to be threatened by the danger posed by the

subject oil depot. If the prescribed user of the said land is not residential but the

same is being unauthorizedly used for residence, the question would again arise

whether by residing on land not meant for residence, user of the adjoining land

for the purpose for which it is permitted to be used can be objected to. In our

view these are all relevant aspects for adjudication of the lis brought by the

petitioners before this Court and are in fact essential to the adjudication and

without establishing which the petitioners could not expect to succeed. With

respect to the rights of the residents of village Tikri Kalan, the concept of

„right‟ cannot be conceived in isolation. Social experience and public realities

are all relevant as juridically, right is understood as a relative abstraction

flowing from the concept of duty itself. The word „right‟ in favour of one


W.P.(C) No.2611/2012                                                Page 39 of 59
 person serves as a sign that someone else is obliged to conform to a pattern of

conduct. Before the Court can be called upon to pronounce on the right asserted

it must be further shown that the activity in relation to which the right is

asserted is sanctioned. However wide a right is, it cannot be as wide as to

destroy similar or other rights in others. The Supreme Court in Minerva Mills

Ltd. Vs. Union of India (1980) 2 SCC 591 held that the object of fundamental

rights is to protect individual liberty but individual liberty cannot be considered

in isolation from the socio-economic structure in which it is to operate and that

that there is a real connect between individual liberty and the shape and form of

the social and economic structure of the society.


34.    Experience of human life shows that residential settlements, mostly

unauthorized, and where none earlier existed come up in close proximity to

sources of income and livelihood such as commercial establishments. This has

been classified by the geographers and landscape historians as a nucleated

village or a clustered settlement and as one of the main types of settlement

pattern.     Such nucleated villages / concentrated settlements have been

precursors to many a small town.




W.P.(C) No.2611/2012                                               Page 40 of 59
 35.    At the same time, we cannot say that the concerns of the petitioners as

residents of the village in the vicinity of the subject oil storage depot are

unfounded. The petition was filed in the wake of the incident of fire in a similar

installation at Jaipur. Moreover, with the intervention of the petitioners, HPCL

which at the time of filing of the petition appeared to be going ahead with the

commissioning of the subject oil storage depot without even preparing the

Comprehensive Emergency Response and Disaster Management Plan and

without even having such a plan tested, as was required, has been compelled to

do so. The petition, to that extent, has already achieved the purpose of filing

thereof.


36.    After giving our anxious consideration to the concerns of the petitioners

pitted against the factum of the subject oil storage depot being situated on a

land specified in the MPD-2021 and acquired for the said purpose and having

been established in accordance with all the requisite approvals, permissions and

consents, we are of the view that no case for restraining the commissioning of

the subject oil storage depot or for considering further the aspects of challenge

to the MPD-2021, Petroleum Rules or the classification of industries or for

grant of any other relief claimed, is made out for the following reasons:



W.P.(C) No.2611/2012                                              Page 41 of 59
        A.      The subject oil storage depot is in relocation of the existing oil

               storage depot at Shakur Basti.


       B.      The decision for such re-location was taken long back, when the

               vicinities of Shakur Basti were densely populated (as they

               continue to be, if not more) and the area of the subject oil storage

               depot was largely rural and considered the outskirts of Delhi;

               though with the passage of time is now stated to have a population

               of 1.5 to 2 lakhs.


       C.      The need for and dependence on oil, of the residents of the city of

               Delhi, is inevitable.


       D.      If we restrain the commissioning of the subject oil storage depot, it

               would necessarily mean continued operation of the Shakur Basti

               storage depot and which the Government, in public interest, had

               taken a decision should be relocated; after all the city cannot be

               without petroleum and petroleum products.


       E.      No challenge was / is made to the decision of the Government to

               relocate the oil storage depot from Shakur Basti.



W.P.(C) No.2611/2012                                                Page 42 of 59
        F.      The question which arises is, whether implementation of the

               decisions taken in accordance with the then contemporaneous

               situations can be stopped / stalled due to the change in the

               interregnum.


       G.      In our opinion, no. We cannot be blind to the ever growing

               population which is converting the hitherto uninhabited lands into

               inhabited. We cannot also be blind to the human tendency of

               making their habitats in close proximity to places of trade and

               commerce and which also serve as source of employment.


       H.     We have no reason to believe that when the Government /

               governmental agencies took the decision to earmark the land on

               which subject oil storage depot is situated, for the said purpose, all

               the said aspects would not have been considered.


       I.      The Supreme Court in N.D. Jayal Vs. Union of India (2004) 9

               SCC 362 held that once the government has taken a considered

               decision and has put a system in place for the execution of the

               project and such a system cannot be said to be arbitrary, then the

               only role which the Court has to play is to ensure that the system

W.P.(C) No.2611/2012                                                 Page 43 of 59
                works in the manner it was envisaged. It was further held that the

               decision or the question whether to have an infrastructural project

               or not and what is the type of project to be undertaken and how it

               is to be executed are a part of policy making process and the

               Courts are ill-equipped to adjudicate on a policy decision so

               undertaken; the only duty of the Court is to see that in undertaking

               the decision, no law is violated. It was further observed that at the

               penultimate stage of execution of the project it was too late in the

               day to think as to why the decision was taken, though at one stage

               it was thought it would not be appropriate to continue with the

               project. We may add that in the present case, the situation is

               beyond even the penultimate stage.


       J.      It has been held by the Supreme Court in Shri Sachidanand

               Pandey Vs. State of West Bengal (1987) 2 SCC 295 relied upon

               by HPCL, that where the government while dealing with an

               administrative order or action has been alive to various

               considerations requiring thought and deliberation and has arrived

               at a conscious decision after taking them into account, it may not

               be for the Court to interfere in the absence of mala fides.

W.P.(C) No.2611/2012                                                 Page 44 of 59
        K.      We cannot also be unmindful of the fact that there is implicit time

               lag in the setting up and commissioning of such mammoth

               projects, from the date of conception thereof and when they are to

               be set up by governmental agencies, the delay is a little longer. In

               the interregnum, there are bound to be considerable changes in and

               around the site thereof, particularly qua human habitation. As

               aforesaid, the very conception of such a project and the

               commencement itself thereof attracts humans to the sites. If it

               were to be held that owing to hazards posed by the project to the

               human settlement in proximity thereto and which settlement owes

               its existence to the project, the project should be abandoned,

               possibly no project would ever see the date of commissioning or

               live its life. If such subsequent events were to come in the way of

               implementation of the decisions taken when the circumstances

               were different, it will lead to a hiatus and not allow any

               development to take place.


       L.      The petitioners and the other residents of village Tikri Kalan

               though had opportunity to, at the time when the subject land was

               so earmarked for the purpose of oil storage and oil products

W.P.(C) No.2611/2012                                               Page 45 of 59
                installations, did not object. In fact the said land was acquired for

               the said purpose only and thus the villagers from whom the said

               land was acquired were fully aware of the purpose for which their

               land was being acquired. They then also did not contend that there

               could be no oil installation thereon for the reason of the land being

               in close vicinity to their residences. On the contrary, they received

               compensation for acquisition. Obviously, their residences at that

               point of time must have been far away from the said land and the

               village over the years appears to have extended its abadi towards

               the said land.


       M.      The concerns of the residents of village Tikri Kalan whose present

               population is stated to be 20,000 to 30,000 are also pitted against

               larger public interest of the citizens of Delhi numbering over a

               crore who need petroleum and petroleum products and which have

               to be stored somewhere.


       N.      The Supreme Court, in G. Sundarrajan Vs. Union of India (2013)

               6 SCC 620 relied upon by senior counsel for HPCL, while dealing

               with safety concerns expressed with respect to setting up of a


W.P.(C) No.2611/2012                                                Page 46 of 59
                nuclear power plant, held that a balance has to be struck between

               the benefits of establishing such a plant, since the production of

               nuclear energy is of extreme importance for the economic growth

               of the country, to alleviate poverty, generate employment, with the

               right to life and property. It was held that the Court has to have an

               overall view of larger public interest rather than a smaller violation

               of right to life guaranteed under Article 21 of the Constitution. It

               was further held that we have to put up with "minor

               inconveniences", "minor radiological detriments" and "minor

               environmental detriments" in our lives because the benefits to be

               reaped from the nuclear power plant in question are enormous.

               The Supreme Court also in Chameli Singh Vs. State of U.P.

               (1996) 2 SCC 549 held that in an organized society, the right to

               live as a human being is not ensured by meeting only the human

               needs of man, but secured only when he is assured of all facilities

               to develop himself and is freed from restrictions which inhibit his

               growth.


       O.      We find that similarly, in Indian Council for Enviro-Legal Action

               Vs. Union of India (1996) 5 SCC 281 it was held that both,

W.P.(C) No.2611/2012                                                 Page 47 of 59
                development and environment must go hand in hand, the necessity

               to preserve ecology and environment should not hamper economic

               and other developments; there should not be development at the

               cost of environment and vice versa but there should be

               development while taking due care.


       P.      In Essar Oil Vs. Halar Utkarsh Samiti (2004) 2 SCC 392 relied

               upon by HPCL also, it was held that the aim is to balance

               economic and social needs on one hand with environmental

               considerations on the other and that there need not necessarily be a

               deadlock between development on one hand and environment on

               the other.


       Q.      A balance, thus must be maintained between the need for and the

               benefits which the subject oil depot brings and the safety hazards

               that it possesses.


       R.      Undoubtedly, the residents in the vicinity of the existing oil

               storage depot at Shakur Basti far outnumber the residents in the

               vicinity of the subject oil storage depot. The Supreme Court, in

               The State of Maharashtra Vs. The Jalgaon Municipal Council

W.P.(C) No.2611/2012                                               Page 48 of 59
                (2003) 9 SCC 731, opined "that smaller interest must always give

               way to larger public interest in case of conflict" to be a principle of

               good governance in a democratic society. We may add that, a

               community of rights, not always synchronizing with each other,

               have to be harmonized.


       S.      Also, while oil to the existing oil storage depot at Shakur Basti has

               to be transported from the oil refineries in trucks / wagons,

               adversely impacting environment, the transportation to the subject

               oil storage depot at Tikri Kalan will be through underground

               pipeline already laid and which will also stop the environmental

               damage through such transportation of oil by road.


       T.      Though it is the contention of the petitioners that the oil storage

               depot should be shifted from the subject place to some other place

               but we also cannot be blind to the fact that there is hardly any

               space left in the city which can be said to be far away from

               habitation or which will remain far away from habitation. Though

               DDA in a meeting held on 29th July, 2013 is stated to have taken a

               decision to hereafter have oil storage depots in the NCR region but


W.P.(C) No.2611/2012                                                 Page 49 of 59
                the position is not very different there also.       Moreover, as

               aforesaid humans have a tendency of congregating around

               wheresoever alternative site is announced and starts coming up.

               Our experience shows that it is generally the families and extended

               families of those involved in setting up of such projects who in the

               absence of any enforcement mechanism against encroachment of

               surrounding lands make up their residences in the vicinity and

               continue to reside there even after the work of construction and

               setting up is complete.


       U.      We cannot also ignore the fact that the residents of the village of

               Tikri Kalan have themselves tacitly consented to the land being

               notified for the subject use. The petitioners are but a few of the

               residents who though have filed the petition as a PIL for the

               benefit of all residents but cannot be assumed to be representing

               even the majority of the residents. It is not known as to what the

               view of the majority is. It is possible that majority of villagers,

               who owing to acquisition of their agricultural land cannot depend

               upon agriculture as a source of livelihood, are happy with such

               development.

W.P.(C) No.2611/2012                                               Page 50 of 59
        V.      We are satisfied that HPCL has taken all possible steps to prevent

               any disaster as well as to meet such a disaster. We cannot also

               loose sight of the fact that large sums of money have already been

               spent on the project and which was a factor taken into

               consideration in G. Sundarrajan supra also.


       W.      In G. Sundarrajan it was further observed that once justification

               for establishing the nuclear power plant had been vindicated and

               all safety and security measures had been taken and necessary

               permissions and clearances had been obtained from all statutory

               authorities, apprehension expressed by some of the consequences

               flowing from commissioning thereof, however legitimate, cannot

               be permitted to override the justification of the project. It was

               observed that nobody on this earth can predict what would happen

               in future and to a larger extent we have to leave it to destiny but

               once the justification test is satisfied, the apprehension test is

               bound to fail. It was further observed, apprehension is something

               we anticipate with anxiety or fear, a fearful anticipation which

               may vary from person to person. It was further held that electricity

               is the heart and soul of modern life; to sustain rapid economic

W.P.(C) No.2611/2012                                               Page 51 of 59
                growth, it is necessary to double the supply of energy and thus the

               production of nuclear energy is of extreme importance for the

               economic growth of our country.


       X.      The said test, in our opinion, equally applies to petrol and

               petroleum products which are also necessary in furtherance of the

               commercial needs of the country and we have to necessarily have

               storage facilities and thus striking a balance between such

               developmental needs on one hand and security and safety concerns

               on the other should be aimed at.


       Y.      Even according to the M.B. Lal Committee, such installations

               should be at a distance of 250 to 300 mtrs. from the habitation.

               While according to the petitioners, the said distance has to be

               measured from the outer boundary of the installation, according to

               HPCL, it has to be measured not from the outer boundary of the

               installation but from the storage point within the said boundary.

               We are satisfied that from the storage point within the boundary of

               the subject installation, the distance of the habitation is 430 mtrs.




W.P.(C) No.2611/2012                                                Page 52 of 59
                and which satisfies the M.B. Lal Committee‟s recommendations

               also.


       Z.      In our opinion, the insistence ought not to be upon the distance

               being from the boundary wall. What is necessary is to provide a

               buffer from the hazardous point of the installation. In the present

               case, obviously HPCL has acquired land much more than actually

               required for storage tanks, so as to provide a buffer around the said

               storage tanks. When HPCL has already provided buffer within its

               boundary, it cannot be compelled to provide buffer beyond its

               boundary also.


       ZA. Though the counsel for the petitioners during the hearing relied

               upon recent news reports about the Disaster Management

               Authorities being ineffective but we are afraid, we cannot proceed

               on the said premise.


       ZB.     We have no reason not to believe the report of the experts who

               have certified that the requisite safety measures have been

               complied with. A Constitution Bench of the Supreme Court in

               University of Mysore Vs. C.D. Govinda Rao AIR 1965 SC 491,

W.P.(C) No.2611/2012                                                Page 53 of 59
                reiterated in G. Sundarrajan supra, held that normally the court

               should be slow to interfere with the opinion expressed by the

               experts and it would normally be wise and safe for courts to

               leave the decisions to experts who are more familiar with the

               problems which they face than courts generally can be. It was

               held that the court cannot sit in judgment on the views

               expressed by the technical and scientific bodies in setting up of

               the concerned project and on its safety and security. Similarly,

               in Essar Oil supra it was held that a court will not substitute it

               own assessment in place of opinion of persons who are

               specialists and who may have decided the question with

               objectivity and ability.


37.    The counsel for the petitioners has in her written submissions

accompanied with a document titled „Detailed Notes‟ and list of dates and a

glossary of pleadings, all running into thirty six pages, besides repeatedly re-

emphasizing the danger the subject oil depot poses to the residents has

alleged various violations by HPCL of what according to the petitioners the

standards of safety should be. It is contended that the vacuum between the

outdated standards of safety in the existing laws / rules / regulations and

W.P.(C) No.2611/2012                                                Page 54 of 59
 what such standards ought to be, should be filled in by the court by issuing

guidelines. The deficiencies in pleadings of the petitioners pointed out by us

are sought to be got over by contending that in issues of public importance

and enforcement of fundamental rights the procedural laws have to be

relaxed. G. Sundarrajan is sought to be distinguished by contending that all

the safety guidelines were complied therein. It is contended that the

acquisition of land being under emergent provisions, there was no right to

object factual dispute of the distance between the subject oil depot and the

human settlement is of course reiterated. It is further contended that the

danger which the subject oil depot poses could be perceived only after the

Jaipur incident. It is also the contention of the petitioners that the road

between the subject oil depot and the human settlement is itself the ignition

point and thus the distance has to be measured from the road and not even

from the storage point within the depot else submissions are made on the

need for re-drawing the standards. The village of Tikri Kalan is described as

in the green belt.


38.    We only need to state that we have in arriving at the decision

aforesaid weighed and considered all the said submissions and for the

reasons stated above do not find any merits in any of the contentions.

W.P.(C) No.2611/2012                                             Page 55 of 59
 39.    We thus do not find the petitioners entitled to any of the reliefs

claimed.


40.    Though we have held the petitioners not entitled to the reliefs claimed

but at the same time, it is essential to ensure that the Comprehensive

Emergency Response and Disaster Management Plan on the basis of existence

whereof we are refusing to interfere, continues to be efficacious. For the said

purpose, we direct:


       A.      HPCL to:


               (i)     Comply and continue to comply with all the suggestions in

                       the subject plan to a tee.


               (ii)    Review the said plan from time to time and at least once

                       every year and to keep updating the same with the changing

                       circumstances, needs and with advancement in technology

                       and to cooperate in the conduct of the mock drills herein

                       below directed to be undertaken regularly from time to time

                       and to comply with the all suggestions recommendations in

                       accordance therewith.



W.P.(C) No.2611/2012                                               Page 56 of 59
                (iii)   Ensure at all times the readiness of the human and other

                       resources, part of the said plan.


               (iv)    Enquire about the title of the land in the vicinity of the said

                       installation and if the said land is found to be public land, to

                       initiate action for removal of the encroachment in the form

                       of residences therefrom.


               (v)     From time to time, as part of its corporate social

                       responsibility, educate the residents of the vicinity about the

                       mock drill to be undertaken in the event of a disaster and

                       about the other safety precautions.


               (vi)    Comply with the suggestions, from time to time, of DDMA,

                       NDMA and other regulatory body.


               (vii) Within four weeks hereof, designate and from time to time

                       designate a General Manager level officer by name, to be

                       responsible for compliance with all these directions as well

                       as all rules / regulations concerning safety and maintenance

                       and readiness of all preventive measures. We make it clear



W.P.(C) No.2611/2012                                                  Page 57 of 59
                        that the officer so designated shall be responsible / liable in

                       law for breach if any.


       B.      GNCTD to:


               (I)     Enquire about the title to the land within a radius of about

                       500 mtrs. from the boundary wall of the subject oil storage

                       depot and if the same is found to be public land, within six

                       months hereof remove all encroachments therefrom.


               (II)    Within six months herefrom, prepare a scheme / plan for

                       ensuring quick / timely response by the outside agencies at

                       the time of need, including by making a scheme for

                       blocking traffic on the access roads to enable the rescue

                       teams to reach the subject site at the earliest.


       C.      DDMA to;


               (A)     Periodically and in any case latest every year, conduct a

                       mock drill to check the efficacy of the Comprehensive

                       Emergency Response and Disaster Management Plan of

                       HPCL and to issue necessary directions for making up


W.P.(C) No.2611/2012                                                      Page 58 of 59
                        deficiencies if any and suggestions for further improvement

                       and to ensure compliance therewith.


       With the aforesaid directions, the petition is disposed of.



                                                   RAJIV SAHAI ENDLAW, J.

CHIEF JUSTICE FEBRUARY 23, 2015 „gsr‟ W.P.(C) No.2611/2012 Page 59 of 59