Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 38, Cited by 0]

Delhi District Court

Brg Energy Systems Limited vs Indian Council Of Arbitration on 27 February, 2018

  IN THE COURT OF GAURAV RAO, ADJ­02 & Wakf Tribunal / 
NEW DELHI DISTRICT, PATIALA HOUSE COURTS, NEW DELHI.

CS No. 488/2017
CNR No. DLND01­004377­2017

BRG Energy Systems Limited,
Through its Authorized signatory
Registered Office at : A­5, Pannamgadu
Industrial Estate, Ramapuram Post, 
Sullurpet Taluk, Nellore District, 
Andhra Pradesh
Corporate Office at : 443, Guna Complex,
Anna Salai, Tuyenampet, Chennai ­ 600018                                                      
                                                                            
                                                                      ........Plaintiff
                                   Vs.
1.          Indian Council of Arbitration 
            Through its Registrar 
            Federation House, Tansen Marg,
            New Delhi­110001. 

2.              GJF Construction Co. Pvt. Ltd. 
                Through it Director 
                3rd Floor Surya Towers
                Block F­1, Saradar Patel Road
                Secunderabad, Telangana                              .......Defendants

Date of institution                                         :   29.03.2017
Date on which reserved for judgment                         :   27.02.2018
Date of decision                                            :   27.02.2018
Decision                                                    :   Application dismissed.



CS No. 488/17     BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr   1/23
                                               ORDER

1. The present order shall dispose off application dated 21.12.2017  filed under Section 151 CPC and application under Order 39 Rule 1 and 2  CPC dated 21.03.2017.

Plaintiff's version

2. It is the case of the plaintiff that it had awarded a work of the  Balance of Plant Package for Vijayawada Thermal Power Station Stage IV­ Unit   7,   1X500   MW   Power   Project   at   Vijayawada,   Andhra   Pradesh   to  defendant no. 2 vide work order no. GIX/PPD/064/182 dated 17.11.2006  accepted by defendant no. 2 on 19.11.2006.  

2.1 It is further its case that during the currency of the work/contract  dispute   arose   between   the     parties   and   defendant   no.   2   invoked   the  arbitration clause contained in the agreement and accordingly the dispute  was referred to defendant no. 1. 

2.2   It   is   further   its   case   that   ultimately   all   the   disputes   and  differences between it and defendant no. 2 was settled vide memorandum of  compromise dated 27.11.2009 and accordingly plaintiff paid all the sums  and   dues   payable   to   defendant   no.   2   and   an   award   in   terms   of   the  memorandum   of   compromise   was   passed   by   Arbitral   Tribunal   on  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 2/23 23.12.2009.     It   is   further   its   case   that   defendant   no.   2   issued   No   Due  Certificate to the plaintiff on 31.07.2012 indicating that there are no dues or  claims payable by the plaintiff to defendant no. 2 relating to aforementioned  contract. 

2.3   It   is   further   its   case   that   after   lapse   of   seven   years   plaintiff  received copy of letter dated 13.09.2016 from defendant no. 2 which was  addressed to defendant no. 1 whereby defendant no. 2 had registered its case  with defendant no. 1.  It is further its case that on 14.10.2016 plaintiff was  asked to submit its defence statement by 15.11.2016 in respect of defendant  no. 2's claim of Rs. 6 crores approximately.  It is further its case that the it  was   also   called   upon   to   deposit   tentative   amount   of   Rs.   11   lacs  approximately   towards   plaintiff's   share   of   arbitration   fees,   administrative  charges etc.  2.4   It   is   further   its   case   that   it   sent   a   letter   dated   10.11.2011   to  defendant no. 1 clarifying that on payment of Rs. 1.50 lacs in full and final  settlement of all claims and dues and award dated 23.12.2009 there is no  subsisting   agreement   or   claim   or   arbitration   for   reference   to   Arbitral  Tribunal and as such defendant no. 1 has no authority to act on the claim of  defendant no. 2. However defendant no. 1 insisted upon the plaintiff to make  the payment of Rs. 11 lacs and file its defence statement vide letter dated  18.11.2016 and 21.12.2016.

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 3/23 2.5   It   is   further   its   case   that   the   assumption   of   jurisdiction   by  defendant no. 1 is per­se illegal, against the ICA Rules and also the Indian  Arbitration and Conciliation Act, 1996.  Hence the present suit. 

Application under Order 39 Rule 2 CPC

3. In   the   applications   at   hand,   it   is   the   plaintiff's   case   that   its  application for stay of proceedings before the Arbitral Tribunal is pending.

3.1 It is its case that defendants have filed their respective written  statements and reply to the interlocutory/stay application. It is its case that  defendant   no.   2   has   not   filed   any   application   under   section   8   of   the  Arbitration & Conciliation Act, 1996 for referring the case to arbitration and  hence defendant no. 2 has submitted to the jurisdiction of this court.  

3.2 It   is   further   its   case   that   defendant   no.   1   has   constituted   the  Arbitral Tribunal and issued a letter dated 07.11.2017 and a meeting was  held by tribunal on 24.11.2017 and the plaintiff was informed about the date  of hearing as 08.01.2018.  It is its case that the illegally constituted Arbitral  Tribunal   cannot   be   allowed   to   act   and   proceed   further   in   the   matter   as  existence of arbitration agreement and the validity of Arbitral Tribunal is  directly an issue before this court.  It is thus prayed that the defendants and  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 4/23 the   Arbitral   Tribunal   be   restrained   from   acting   in   any   manner   or   from  proceeding   further   in   the   so   called   arbitration   proceedings   scheduled   for  08.01.2018. 

Defendant no. 1's version 

4. In reply it is the stand of defendant no. 1 that present suit is not  maintainable being barred by Section 5 of the Arbitration and Conciliation  Act 1996 as there is an arbitration agreement governing the contract entered  into between plaintiff and defendant no. 2 and defendant no. 1 has been  appointed as the institution which will facilitate the arbitration between the  plaintiff and defendant no. 2.    It is further its stand that in view of clause  12.2   of   the   arbitration   agreement   between   the   parties   this   court   has   no  jurisdiction to adjudicate upon the present suit. 

4.1  It is further its stand that present suit is not maintainable as the  relief of declaration is guided by section 34 of the Specific Relief Act 1963  and   this   court   has   no   jurisdiction   to   try   the   present   suit   and   grant   the  aforesaid relief in view of the presence of arbitration agreement between the  plaintiff   and   defendant   no.2.   It   is   further   its   case   that   the   suit   is   not  maintainable being barred under section 41 (h) of the Specific Relief Act,  1962 as the plaintiff has equally efficacious relief u/s 16 of the Arbitration  Act   to   raise   all   the   objections,   as   raised   in   the   present   suit,   before   the  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 5/23 Arbitral Tribunal. 

4.2   It is further its stand that on 13.09.2016 defendant no. 2 filed  statement of claim requesting it to constitute the arbitral tribunal under the  ICA   Rules   of   Commercial   Arbitration   and   Conciliation   2016   for   the  resolution   of   its   dispute   with   plaintiff   in   relation   to   work   order   dated  17.11.2006 which contains arbitration clause being Clause 12.2 of the Work  order dated 17.11.2006. 

4.3 It is further its stand that it upon receiving the reference vide  letter   dated   14.10.2016   plaintiff   was   intimated   regarding   claim   and  forwarded  the statement  of  claim along  with  supporting documents.  It is  further its stand that as the claim amount was more than 5 crores the dispute  would be decided by a panel of three arbitrators as per the said ICA Rules of  Arbitration and invited the plaintiff to choose its nominee arbitrator from the  panel maintained by it. It is further its stand that it advised the plaintiff to  submit its statement of defence by 15.11.2016 and deposit Rs. 10,91,653/­  towards plaintiff's share in the arbitration fee/ charges. 

4.4 It is further its stand that on 10.11.2016 plaintiff challenged its  jurisdiction   to   entertain   the   reference   for   arbitration   and   constitute   an  arbitration tribunal on the ground the arbitration had earlier been invoked  between the parties and dispute of the same nature was adjudicated which  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 6/23 ended up in a compromise and plaintiff had already paid an amount of Rs.  150 lacs as full and final settlement of all the claims. It is further its stand  that on 17.11.2016 it forwarded the objection of the plaintiff to defendant no.  2 for its information and reply. 

4.5 It is further its stand that on 18.11.2016 it replied to the letter of  plaintiff   dated   10.11.2016   categorically   stating   that   the   objection   of   the  plaintiff   was   on   merits   of   the   dispute   and   it   was   neither   competent   nor  authorized to decide any issue on the merits of the case. It is further its stand  that it further provided a fresh extension of time till 30.11.2016 for filing of  statement of defence, name of nominee arbitrator and arbitral expenses.  

4.6 It is further its stand that on 28.11.2016 plaintiff replied to its  letter dated 18.11.2016 stated that there was no valid contract or arbitration  agreement between the parties and the present reference was not valid. 

4.7 It is  further  its stand that on 16.12.2016 defendant no. 2 vide  letter addressed to it stated that the present claim is wholly different from the  claim made before the earlier tribunal culminating into a compromise and  award dated 23.12.2009 and it was further stated that payment of Rs. 150  lacs   did   not   include   pending   RA   bills   upto   bill   no.   18   and   service   tax  reimbursement. 

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 7/23 4.8 It is further its stand that on 21.12.2016 it forwarded the letter  dated 16.12.2016 addressed to defendant no. 2 and further strongly urged the  plaintiff to comply with the previous directions to file statement of defence  and make necessary payment by 09.01.2017. 

4.9 It is further its stand that on 21.01.2017 plaintiff issued a legal  notice   stating   that   action   of   assuming   the   jurisdiction   to   constitute   the  tribunal,   seeking   filing   of   statement   of   defence   and   nomination   of   the  arbitrator   along   with   payment   of   arbitral   fee/charges   in   unilateral   and  arbitrary manner and not binding on the plaintiff. 

4.10 It   is   further   its   stand   that   plaintiff   has   till   date   not   filed   its  statement of defence, nominated its arbitrator or paid it share of fee/charges  of the arbitration while defendant no. 2 has already complied with all the  requirements of the ICA rules. 

Defendant no. 2's version

5. In reply it is the stand of defendant no. 2 that there has been  concealment of material facts and documents by the plaintiff and it has not  approached the court with clean hands. 

5.1 It is its case that arbitral proceedings commenced on 13.09.2016  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 8/23 and the plaintiff is delaying the matter by not filing the reply/objections to  the statement of claim made by defendant no. 2. 

5.2  It is further its case that the court has no jurisdiction to entertain  the present suit, application and it is the Arbitral Tribunal constituted as per  the arbitration agreement which is the appropriate authority to adjudicate  upon the dispute.   It is further its case that as per the work order it is the  Chennai   courts   which   have   the   exclusive   jurisdiction   in   all   the   matters  arising under the said work order. It is further submitted that plaintiff must  submit itself to the jurisdiction of defendant no. 1 instead of approaching this  court.  

5.3   It   is   further   its   case   that   the   arbitration   clause   was   invoked,  defendant no. 1 approached and statement of claim dated 13.09.2016 filed  with regard to unresolved, live and pending disputes. It is its case that these  disputes were expressively excluded from the memorandum of compromise  and pertain to payment of service tax, interest and penalty on account of  notice issued by Commissioner of Customs, Central Excise and Service tax  etc. It is its case that minutes of meeting dated 10.11.2009 as referred in para  12 of the memorandum of compromise excluded the dispute in respect of  above subject matters.  It is further its case that even after the consent award  the work was executed and completed upto 25.01.2011.

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 9/23 5.4  It is its case that the plaintiff failed to discharge its contractual  obligations,   faltered   and   delayed   in   payment   of   RA   bills   which   caused  financial loss to defendant no. 2. It is its case that as per the contract the  plaintiff   is   obligated   to   reimburse   defendant   no.   2   for   payment   made   to  service tax department but the same was not done so which led to the dispute  and invocation of the arbitration clause. 

Findings

6. I have heard the rival contentions raised at bar and perused the  record carefully. After considering the entire material available on record, I  am of the considered opinion that no grounds are made out for grant of stay,  allowing the application under Order 39 Rule 1 and 2 CPC as moved by the  plaintiff. 

6.1 Work  order  no. GIX/PPD/064/182  dated  17.11.2006 issued  by  the plaintiff was accepted by defendant no. 2 on 19.11.2006. Clause 12 of  the   General   and   Commercial   Conditions   of   the   contract   as   was   entered  between   the   plaintiff   and   defendant   no.   2   provides   for   settlement   of   the  disputes through arbitration. Same is reproduced hereunder:

"12.0.0 SETTLEMENT OF DISPUTES 12.1.0 Any dispute (s) or difference(s) arising out of or in connection with the   Contract   shall,   to  the  extent   possible   in  the   first   instance   be   resolved  amicably   between  the   Supplier and the Purchaser's Engineer.   In the event dispute could not be resolved amicably   between the parties then either party may apply Arbitration in accordance with the Arbitration   CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 10/23 Clause. 
12.2.0 Arbitration 12.2.1 any dispute or difference whatsoever, arising between the parties out of or   relating to the construction, meaning, scope, operation or effect of this Contract or the validity or   the breach thereof shall be settled by arbitration in accordance with the Rules of Arbitration and   Conciliation of the Indian Council of Arbitration and the Award made in pursuance thereof shall   be binding on the parties. The seat of Arbitration shall be in Chennai."

6.2 After the initial dispute arose between the parties, they held a  meeting to resolve the same, settle out the dispute and in the minutes of  meeting   dated   10.11.2009   held   at   the   Chennai   office   of   the   plaintiff   the  parties arrived at the following agreement:

"The outstanding issues including the disputes pending before the Arbitral Tribunal   were discussed & following terms were agreed by both parties. 
1. Towards settlement of all claims Rs. 150.0 Lacs will be paid by BGR as a   one time full & final settlement to GJF. 
2. The above amount of Rs. 150 lacs would exclude the following:­
(a) Pending RA Bills upto RA Bill no. 18.
(b) Service Tax reimbursement
(c) Claim under 2 (b) (iii) relating to SAP quantity withheld in the  bills.
(d) Work Contract Tax beyond RA Bill no. 18.
3.  With regard to the above excluded items in para 2 above, the parties have   agreed as under:­
(a)   Pending   RA   Bills   payment   upto   RA   Bill   no.   18   :   ­   The   amount   will   be   released within (10) ten days from date of meeting. 
(b)   Service   Tax   reimbursement   pending   upto   RA   Bill   no.   18   will   be   released   with in (10) ten days from date of meeting and for subsequent RA Bill, within   (7) seven days of submission of challan. 
(c)   Claim   under   2   (b)   (iii)   :­   The   quantities   will   be   reconciled   and   mutually   accepted for payment within (15) fifteen days of the meeting.
(d) Work Contract Tax for RA Bill No. 19 onwards : BGR will provide to GJF   Form 501 B Certificate of transfer of Tax deduction at source by the contractor to  the Sub­contractor for the total gross bill amount paid to GJF." 

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 11/23 6.3 Pursuant to the meeting one memorandum of compromise dated  27.11.2009 was filed, with reference to the minutes of meeting as above,  before the Ld. Arbitral Tribunal and finally award was passed by the Ld.  Arbitral   Tribunal   on   23.12.2009   in   terms   of   the   memorandum   of  compromise.  However it is to be seen that obligations were casted upon the  respective   parties   to   perform   certain   works   in   terms   of   the   original  contract/award. Clause 6 of the memorandum of compromise reveals that  major work was to be completed by 31.12.2009 and the minor work upto  15.01.2010. Furthermore as per  Clause 12, the minutes of meeting dated  10.11.2009,   as   discussed   above,   formed   part   of   the   memorandum   of  compromise. The minutes of meeting as discussed above makes it amply  clear that issues relating to payment of RA Bills upto RA Bill no. 18 and  Service Tax reimbursement were specifically excluded from the settlement.

6.4 Defendant   no.   2   has   placed   on   record   communication   dated  15.03.2012   received   by   it   from   the   Superintendent   of   Central   Excise  regarding the observations made during the audit for the period April 2007  to March 2011 whereby the defendant  was communicated regarding certain  short payment of service tax due to non inclusion of value of free supplied  material in the taxable value. Some of these materials were supplied by the  plaintiff. Non payment of service tax on the mobilization advanced received  from the plaintiff was also highlighted apart from payment of interest on the  RA bills. 

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 12/23 6.5 Defendant no. 2 has also placed on record communication dated  21.05.2012 whereby plaintiff was called upon to settle the outstanding issues  relating to payment which included bill payment as well as payment towards  taxes and also for providing the certificate towards tax deductions. Issue  relating   to   service   tax   was   also   highlighted   in   detail   in   the   said  communication.

6.6 Hence even after the arbitral award was passed, the parties had  certain outstanding liabilities, obligations to be performed and certain issues,  dispute   also   arose   in   between   the   parties   on   account   of   subsequent  developments, communications received by defendant from the authorities  as   discussed   above.   All   these   disputes   had   their   genesis   in   the   work  order/contract which as discussed above, contains an arbitration clause for  settlement of disputes through arbitration. 

6.7 Undoubtedly plaintiff has relied upon No Due Certificate dated  01.08.2012 and vehemently argued that after issuance of No Due Certificate  not only the contract came to an end, but once the contract came to an end  even the arbitration clause ceased to exist. However I do not find merit in the  claims of the plaintiff. Apart from No Due Certificate dated 01.08.2012 there  is   another   No   Due   Certificate   dated   31.07.2012   on   record.   The   relevant  portions of the two No Due Certificates are reproduced hereunder:

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 13/23 Certificate dated 31.07.2012 We, M/s G J F Construction Company Limited declare that we have received FULL and   FINAL SETTLEMENT of Rs. 84,11,681 vide RTGS Ref 32350 dated 30.07.12, against the   order   No.   GIX/PPD/064/182   dt.   17.11.2006   issued   by   M/s.   BGR   ENERGY   SYSTEMS   LIMITED for the execution of civil works for VTPS Project. We declare that we have no dispute/claims against M/s. BGR Energy Systems Limited   under any context with this settlement and all the payments have been made as per the Full   and Final settlement  excepting  the issue of Form 501B towards Work Contract Tax and   the reimbursement of Service Tax.
M/s. BGR Energy Systems Limited shall not be held responsible in any manner for any   claims/dues payable by M/s GJF Construction Company Limited, to any third party which   could have arisen during the period of the above mentioned contracts  excepting  for the  liability under Work Contract Tax and Service Tax relating to the above contract.  
Certificate dated 01.08.2012 We, M/s G J F Construction Company Limited declare that we have received FULL and   FINAL SETTLEMENT of Rs. 84,11,681 vide RTGS Ref 32350 dated 30.07.12, against the   order   No.   GIX/PPD/064/182   dt.   17.11.2006   issued   by   M/s.   BGR   ENERGY   SYSTEMS   LIMITED for the execution of civil works for VTPS Project. We declare that we have no dispute/claims against M/s. BGR Energy Systems Limited   under any context with this settlement and all the payments have been made as per the Full   and Final settlement.
M/s BGR Energy Systems Limited shall not be held responsible in any manner for any   claims/dues payable by M/s G J F Construction Company Limited, to any third party which   could have arisen during the period of the above mentioned contracts.  
6.8 No Due Certificate dated 31.07.2012 as discussed above absolves  the plaintiff from any liability whatsoever excepting the issue of Form 501B  towards Work Contract Tax and the reimbursement of Service Tax and for  the liability under Work Contract Tax and Service Tax relating to the above  contract. A bare perusal of two certificates would reveal that the subsequent  certificate   is   absolutely   silent   regarding   the   rights   and   liabilities   of   the  parties, their obligations in respect of service tax etc. In fact issuance of two  certificates itself proves that even till August 2012 there were disputes inter­ CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 14/23 se   the   parties,   unresolved   issues   remained   on   account   of   service   tax,   its  payment and liability. Nonetheless even after issuance of No Due Certificate  the   issue   regarding   payment   of   service   tax   and   issuance   of   relevant  certificates for reimbursement of service tax remained a bone of contention  between   the   parties.   Plaintiff   cannot   take   a   shield   behind   the   No   Due  Certificate and avoid subjecting itself to the arbitration proceedings.  
6.9 Defendant has placed on record letter dated 28.08.2012 written to  the plaintiff, the relevant portion of which is reproduced hereunder:
Sub : Construction of VTPS 1X500 MW - Civil Works - reg. 
Re : Service Tax Payment & bill for reimbursement. 
We are submitting our invoices claiming for reimbursement of service tax paid viz.,
1)   Invoice   for   RA   Bill   no.   21   claiming   reimbursement   of   Rs.   4,45,184/­   with   challan. 
2) Invoice of RA bill no. 20 claiming reimbursement of Rs. 2,41,567/­ with challan. 
3) Invoice for EIRL Bill claiming reimbursement of Rs. 3,08,759/­ with challan. 

We have addressed Mr. Ramesh Kumar/M/s Jacintha requesting for the control   statement/bill details for RA Bill No. 22 & final to facilitate the payment of Service  Tax.  Kindly arrange for the same. 

We have received Form 501B for RA Bill no. 19, 20 and 21. We request you to   kindly arrange the form 501B for R.A. Bill no. 22 & Final. 

6.10 Defendant has also relied upon one letter written to it on behalf of  the plaintiff i.e. letter dated 08.09.2012 which is reproduced hereunder:

Sub : Returning of Invoice No,. EIRL dt. 28.08.2012 Ref : Your letter ref. no. GJFCCL : BGR ; 2012­13­1014 dt. 28.08.2012.  We are returning your above referred bill towards claim for the service tax amount   which is not as per the agreed terms. 
Kindly acknowledge receipt. 
6.11 There are various letters including letter dated 09.10.2013 with  reference to communication dated 17.06.2013 and letter dated 20.01.2016  CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 15/23 with   reference   to   communication   dated   28.12.2015   all   in   respect   of  reimbursement of service tax which makes it amply clear that dispute arising  out of, having its basis in the contract is still subsisting between the parties. 

Hence it thus becomes evident that certain issues still remain to be settled  between the parties and no question of the contract having received accord  and satisfaction arises. The dispute, as discussed above, arose in discharge of  the contractual obligations in terms of the contract/award which contains an  arbitration clause.   In terms of the arbitration clause as has been discussed  above the parties ought to be referred to the arbitration in terms of section 8  of the Arbitration and Conciliation Act, 1996 however in the case at hand  arbitral proceedings have already commenced and it is the plaintiff who has  to submit  itself  to the jurisdiction of  the  Arbitral Tribunal. The question  regarding the maintainability of the dispute, limitation, jurisdiction of the  tribunal   etc.   can   be   raised   before   the   Ld.   Arbitrator,   Arbitrial   Tribunal  who/which has sufficient power to give a finding upon all such issues as  might be agitated before him/it as is provided in section 16 of the above act. 

 

6.12 In  Shree Subhlaxmi Fabrics Pvt. Ltd vs Chand Mal Baradia   And Others AIR 2005 SC 2161 it was held as under:

"In Konkan Railway Corpn. Ltd. vs. Mehul Construction Co . 2000  (7)   SCC   201,   a   three   Judge   Bench   of   this   Court   held   that   at   the   stage   when   a   party   has   approached the Chief Justice for appointment of an arbitrator, the contentious issues should not   be decided at that stage and the aggrieved party can raise all the objections including objection   regarding   non­existence   of   an   arbitration   clause   before   the   Arbitral   Tribunal.   The   Bench   observed as under in para 4 of the report:­  "When the matter is placed before the Chief Justice or his nominee under Section 11 of the Act it   CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 16/23 is imperative for the said Chief Justice or his nominee to bear in mind the legislative intent that   the arbitral process should be set in motion without any delay whatsoever and all contentious   issues  are left to be raised before the  Arbitral Tribunal itself.  At  that  stage it would not be   appropriate for the Chief Justice or his nominee to entertain any contentious issue between the   parties and decide the same. A bare reading of  Sections 13  and  16  of the Act makes it crystal   clear   that   questions   with   regard   to   the   qualifications,   independence   and   impartiality   of   the   arbitrator, and in respect of the jurisdiction of the arbitrator could be raised before the arbitrator   who would decide the same .... 

Section 16  empowers the Arbitral Tribunal to rule on its own as well as on objections with   respect to the existence or validity of the arbitration agreement. Conferment of such power on the   arbitrator under the 1996 Act indicates the intention of the legislature and its anxiety to see that   the arbitral process is set in motion. This being the legislative intent, it would be proper for the   Chief Justice or his nominee just to appoint an arbitrator without wasting any time or without   entertaining any contentious issues at that stage, by a party objecting to the appointment of an   arbitrator. If this approach is adhered to, then there would be no grievance of any party and in   the arbitral proceeding, it would be open to raise any objection, as provided under the Act."  Similar view has been taken in State of Orissa and others vs. Gokulananda Jena 2003 (6) SCC   465, where this Court held as under:­ "However, we must notice that in view of Section 16 read   with  Sections 12  and  13  of the Act, as interpreted by the Constitution Bench of this Court in   Konkan Rly.  Corpn. Ltd. v. Rani Construction (P) Ltd. [(2002) 2 SCC 388] almost all disputes   which   could   be   presently   contemplated   can   be   raised   and   agitated   before   the   arbitrator   appointed by the Designated Judge under Section 11(6) of the Act. From the perusal of the said   provisions of the Act, it is clear that there is hardly any area of dispute which cannot be decided   by the arbitrator appointed by the Designated Judge." 

In Food Corporation of India vs. Indian Council of Arbitration and others  2003 (6) SCC 564   (para 14), it was emphasized that the legislative intent underlying the 1996 Act is to minimize the   supervisory roles of courts in the arbitral process and nominate/ appoint the arbitrator without   wasting time, leaving all contentious issues to be urged and agitated before the arbitral tribunal   itself. It was further held that even in the old law, common sense approach alone was commended   for being adopted in construing an arbitration clause more to perpetuate the intention of the   parties   to   get   their   disputes   resolved   through   the   alternate   disputes   redressal   method   of   arbitration rather than thwart it by adopting a narrow, pedantic and legalistic interpretation.  The consistent view taken by this Court, therefore, is that contentious issues should not be gone   into or decided at the stage of appointment of an arbitrator and no time should be wasted in such   an   exercise.   The   remedy   of   the   aggrieved   party   is   to  raise   an   objection   before   the   arbitral   tribunal as under Section 16 of the Act it is empowered to rule about its own jurisdiction. It is,   therefore, open to the plaintiff to raise all the pleas before defendant No. 2 including a plea that   there is no arbitration agreement between the parties for referring any dispute for arbitration   before   the   Hindustan   Chamber   of   Commerce,   Mumbai.   It   is   also   important   to   note   that   in   response to the notice issued by defendant No. 2 the plaintiff had sent a communication raising   certain   pleas   and   had   also   remitted   an   amount   of   Rs.200/­   as   fee   for   arbitration.   In   such   circumstances we are of the opinion that the view taken by the City Civil Court was just and   CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 17/23 proper and the High Court erred in granting an injunction in favour of the plaintiff and staying   the proceedings before defendant No. 2."  

6.13 In  Jayesh Engineering Works Vs. New India Assurance (2000)   10 SCC 178 it was held as under:

"At that stage, an application was filed under Section 33 of the Arbitration Act   seeking a declaration that the agreement dated 7­4­1981 between the parties no longer subsists   as the work has already been completed and the payment was received by Respondent 1 in full   and final settlement..............Whether any amount is due to be paid and how far the claim made   by the appellant is tenable are matters to be considered by the arbitrator. In fact, whether the   contract has been fully worked out and whether the payments have been made in full and final   settlement are questions to be considered by the arbitrator when there is a dispute regarding the   same.  
6.14 There is one more aspect i.e. regarding the jurisdiction of this  court.  As   per   clause   15   of   the   work   order/   award/contract   which   is  reproduced hereunder it is the Chennai court which has the jurisdiction.
"15.0.0 Jurisdiction of court:
The laws  applicable to  the  contract   shall   be  the   laws  applicable  in India.  The   courts of Chennai shall have exclusive jurisdiction in all matters arising under this order."  

6.15 In  Shree   Shublaxmi   Fabrics   Pvt.   Ltd.   (supra)  it   was  held   as  under:­ ..............The   other   point,   which   needs   consideration,   is   that   the   appellant   had   raised a specific plea by moving an application under  Section 20  read with Section 151 CPC   before the trial court that the court at Calcutta had no territorial jurisdiction to try the suit.   According to the appellant the indent (contract) contained a clause that the dispute under the   contract shall be decided by the court at Bombay  and by  no other court. That  apart it was   defendant No. 1, which had commenced arbitration proceedings before defendant No. 2 and both   are situate in Bombay.

The plaintiff wants that the Hindustan Chamber of Commerce (defendant No. 2)   may be restrained from proceeding with arbitration of the dispute, which has been raised by the   CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 18/23 appellant   Shree   Subhlaxmi   Fabrics   Pvt.   Ltd.   (defendant   No.   1).   Both   defendant   No.   1   and   defendant No. 2 have their offices at Bombay. Insofar as commencement of proceedings before   defendant No. 2 by defendant No. 1 is concerned, no part of cause of action has accrued in   Calcutta. In Hakam Singh vs. Gammon (India) Ltd. 1971 (1) SCC 286, it has been held that it is   not open to the parties to confer by their agreement jurisdiction on a court which it does not   possess under the Code. But where two courts or more have under the Code of Civil Procedure   jurisdiction to try a suit or a proceeding, an agreement between the parties that the disputes   between them shall be tried in one of such courts is not contrary to public policy and that such an   agreement does not contravene Section 28 of the Contract Act. In A.B.C. Laminart (P) Ltd. vs.   A.P. Agencies 1989 (2) SCC 163, it was held as under: ­  "When the court has to decide the question of jurisdiction pursuant to an ouster clause it is   necessary to construe the ousting expression or clause properly. Often the stipulation is that the   contract   shall   be   deemed   to   have   been   made   at   a   particular   place.   This   would   provide   the   connecting factor for jurisdiction to the courts of that place in the matter of any dispute on or   arising out of that contract. It would not, however, ipso facto take away jurisdiction of other   courts. Where an ouster clause occurs, it is pertinent to see whether there is ouster of jurisdiction   of other courts. When the clause is clear, unambiguous and specific accepted notions of contract   would bind the parties and unless the absence of ad idem can be shown, the other courts should   avoid exercising jurisdiction. As regards construction of ouster clause when words like 'alone',   'only', 'exclusive' and the like have been used there may be no difficulty. Even without such words   in appropriate cases the maxim 'expressio unius est exclusion alterius'  expression of one is the   exclusion of another may be applied. What is an appropriate case shall depend on the facts of the   case.   In   such   a   case   mention   of   one   thing   may   imply   exclusion   of   another.   When   certain   jurisdiction is specified in a contract an intention to exclude all others from its operation may in   such cases be inferred. It has therefore to be properly construed."  This view has been reiterated in  Angile Insulation vs. Davy Ashmore India Ltd. 1995 (4) SCC  

153.  In the case on hand the clause in the indent is very clear, viz., "court of Bombay and no other   court". The trial court on consideration of material on record held that the court at Calcutta had   no jurisdiction to try the suit." 

6.16   In  B.E.   Simoese   Von   Staraburg   Niedenthal   and   anr   Vs.   Chhattisgarh Investment Ltd. (2015) 12 SCC 225 it was held as under:

"In a very recent judgment delivered on 10­9­2014 in State of W.B v. Associated   Contractors, the three­Judge Bench (speaking through one of us, Rohinton Fali Nariman, J.),   noticing the decisions of this Court in FCI v. A.M Ahmed & Co. FCI v. A.M Ahmed & Co.
   , 2001      10 SCC 532 (SCC para 6);  Neycer India Ltd. v. Gmb Ceramics Ltd. Neycer India Ltd. v. Gmb   Ceramics Ltd., 2002 9 SCC 489 (SCC para 3) with reference to section 31(4) of the arbitration   act, 1940 and the decisions of this Court in Jatinder Nath v. Chopra Land Developers (P) Ltd. 
CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 19/23 Jatinder Nath v. Chopra Land Developers P Ltd.,  2007 11 SCC 453 (SCC  para 9);  Rajasthan   State Electricity Board v. Universal Petrol Chemicals Limited (SCC paras 33 to 36) and Swastik   Gases (P) Ltd. v. Indian Oil Corpn. Ltd. (SCC para 32), held that where the agreement between   the   parties   restricted   jurisdiction   to   only   one   particular   court,   that   court   alone   would   have   jurisdiction as neither  section 31(4) nor section 42 (of the 1996 act)  contains a non obstante   clause wiping out a contrary agreement between the parties. On the basis of the above decisions,   it was further held that applications preferred to courts outside the exclusive court agreed to by   parties would also be without jurisdiction."

6.17 It thus primarily appears that it is only the Chennai courts which  have the jurisdiction to entertain the dispute which otherwise is arbitrable,  subject matter of arbitration as discussed above. Merely on the strength of  the notice issued by defendant no. 1 no jurisdiction can be vested in this  court. 

6.18 Though   Ld.   counsel   for   the   plaintiff   has   relied   upon  Today's   Homes And Infrastructure Pvt. Ltd. Vs. Ludhiana Improvement Trust and   anr.   (2014)   5   SCC   68  however   the   said   case   law   rather   supports   the  defendant's version as it reiterates the fact that it is the Ld. Arbitrator who  can adjudicate all such questions regarding the claim being dead or time  barred and that the arbitration agreement, the arbitration clause which forms  part of the contract has to be treated as an agreement independent of the  other terms of the contract. Once the arbitral tribunal, as discussed above,  has already been constituted all questions ought to be agitated before the  tribunal   and   not   before   this   court.   For   similar   reasons  Ashapura   Mine­ Chem Ltd. Vs. Gujarat Mineral Development Corporation (2015) 8 SCC   CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 20/23 193 does not apply to the facts of the present case. 

6.19 Similarly   though   Ld.   counsel   for   the   plaintiff   relied   upon  Chatterjee   Petrochem   Company   and   anr   Vs.   Haldia   Petrochemicals   Limited and ors (2014) 14 SCC 574 however from a careful reading of the  said   case   law   it   becomes   evident   that   section   5   of   the   Arbitration   bars  intervention   by   Judicial   authorities.   The   jurisdiction   aspect   was   also  considered as per the agreement which   vested exclusive jurisdiction in a  particular   court,   court   situated   in   a   particular   state   i.e.   Calcutta   in   that  particular case. Furthermore in view of subsisting arbitration clause the suit  for declaration and injunction was held to be not sustainable in the eyes of  law and thus liable for dismissal. In the case at hand it has been discussed  above that there is a valid arbitration clause in a contract wherein dispute has  arisen and in terms of the arbitration clause the dispute has to be resolved by  taking recourse to clause 12. 

6.20 As  far  as  Young Achievers  Vs.  IMS  Learning  Resource  Pvt.   Ltd. (2013) 10 SCC 535  is concerned it does not apply to the facts of the  present case as the agreement has neither been superseded nor novated by  any later agreement. Furthermore no question of accord and satisfaction in  the present case arises as what was settled between the parties as per the  memorandum of compromise was the dispute which arose at that point of  time while the other obligations and liabilities under the contract continued. 

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 21/23 Disputes/issues arose subsequently for which statement of claim has been  made to the Arbitral Tribunal and those disputes/issues have their roots in  the contract. 

6.21 As   far   as  Chloro   Controls   India   Pvt.   Ltd.   Vs.   Severn   Trent   Water Purification Inc and other (2013) 1 SCC 641 is concerned there is no  applicability   of   the   said   case   law   to   the   present   case.   The   work   order,  contract which contains the arbitration clause is not disputed. No question of  same being null, void or incapable of being performed arises or has been  raised.   Plea   regarding   the   contract   having   been   concluded,   accord   in  satisfaction is not tenable as discussed above. Moreover all the above case  laws as discussed above categorically lay down that it is obligatory upon the  court to make a reference to the arbitration in case there is an arbitration  clause in a contract, agreement. 

6.22 In view of the above observations nothing remains to be decided  in the original action. Reliance may be placed upon the law laid down in P.   Anand  Gajapathi   Raju  Vs.  P.V.G.  Raju   (dead)   2000   (4)   SCC   539  and   Venture Global Engineering Vs. Sathyam Computers Services Ltd. AIR   2008   SC   1061.  This   court   would   have   referred   the   parties   to   arbitration  however as discussed above arbitral proceedings have already  commenced  and in fact vide proceedings dated 05.02.2018 the Ld. Arbitral Tribunal has  already ruled in favour of its competence, jurisdiction to decide the dispute. 

CS No. 488/17 BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr 22/23 6.23 Applications stands dismissed. Therefore nothing survives in the  present matter. 

6.24 File be consigned to record room. 

Announced in the open Court                                  (Gaurav Rao)
on 27th February 2018                                        ADJ­02 & Wakf Tribunal / 
                                                             New Delhi District,
                                                             Patiala House Courts, Delhi. 




CS No. 488/17     BGR Energy systems Ltd. Vs. Indian Council of Arbitration and anr   23/23