[Cites 0, Cited by 0] [Section 9] [Entire Act]

Union of India - Subsection

Section 9(2) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(2)In case of an existing generating station or unit thereof, or transmission system or element thereof, the application shall be made by the generating company or the transmission licensee, as the case may be, by 31.10.2019, based on admitted capital cost including additional capital expenditure already admitted and incurred up to 31.3.2019 (either based on actual or projected additional capital expenditure) and estimated additional capital expenditure for the respective years of the tariff period 2019-24 along with the true up petition for the period 2014-19 in accordance with the CERC (Terms and Conditions of Tariff) Regulations, 2014.