State of Rajasthan - Subsection

Section 15(2) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016

(2)In case intra-State transmission system or distribution system is used by an open access customer in addition to inter-State transmission system, transmission charges and wheeling charges shall be payable for use of intra-State system in addition to payment of transmission charges for inter-State transmission.