Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 26]

Supreme Court of India

State Of Gujarat vs M/S. Kailash Engineering Co on 26 September, 1966

Equivalent citations: 1967 AIR 547, 1967 SCR (1) 543, AIR 1967 SUPREME COURT 547

Author: Vishishtha Bhargava

Bench: Vishishtha Bhargava, J.C. Shah, V. Ramaswami

           PETITIONER:
STATE OF GUJARAT

	Vs.

RESPONDENT:
M/S.  KAILASH ENGINEERING CO.

DATE OF JUDGMENT:
26/09/1966

BENCH:
BHARGAVA, VISHISHTHA
BENCH:
BHARGAVA, VISHISHTHA
SHAH, J.C.
RAMASWAMI, V.

CITATION:
 1967 AIR  547		  1967 SCR  (1) 543
 CITATOR INFO :
 RF	    1972 SC 744	 (13)
 D	    1974 SC2309	 (13)
 RF	    1976 SC2108	 (48)
 RF	    1977 SC1537	 (23)


ACT:
Bombay	 Sales-tax  Act,  1953,	 s.  27-Contract   for	 the
construction of Railway coach bodies-Provisions in  contract
showing property in construction material vesting in Railway
on  arrival  at	 site and in  coach  bodies  on	 completion-
Transaction whether sale or works contract.



HEADNOTE:
The  respondent	 company, which was an	engineering  concern
with  a	 workshop  at Morvi, obtained a	 contract  from	 the
Western	 Railway  Administration for construction  of  third
class	coaches.    Under  the	 contract   the	  respondent
constructed  three  coaches and submitted a bill  which	 was
properly  certified on October 4, 1958, in  accordance	with
the agreement as to the work done by the respondent.   After
the  bill  had	been  paid,  the  respondent  wrote  to	 the
Additional  Collector  of  Sales-tax  requesting  him  under
Section	 27 of the Bombay Sales-tax Act, 1953 to  hold	that
the transaction was a works contract and not a sale, so that
no sales-tax was payable under the Act.
The  Additional Collector held however that the	 transaction
was  a sale on which tax was payable.  Dismissing an  appeal
from  this  decision, the Sales-tax Tribunal took  the	view
that  the  general  conditions of the  contract	 showed	 the
ownership  of the coach bodies only passed to the Rail	when
they were completed and handed over to the Railway, so	that
way contract was for supply of coach bodies.  Sales-tax	 was
therefore payable on the price of these coach bodies.	Upon
a reference made to it, the High Court held however that the
contract  clearly  mentioned  that  the	 contract  was	 for
performance  of	 work of building, erecting  and  furnishing
coach  bodies on Broad Gauge under frames which already	 be-
longed	to the Railway.	 The terms of the  contract  further
showed	that  as  soon as the materials were  taken  by	 the
respondent  to the site of the construction of coaches,	 the
ownership  in those materials vested in the Railway and	 all
that  the respondent had to do was to carry out the work  of
erecting  and furnishing the coach bodies.  When  the  coach
bodies	.were  ready,  the property in them  vested  in	 the
Railway automatically without any further transfer of rights
in  it	to the Railway.	 The ownership in  the	ready  coach
bodies	never  vested in the respondent company at  all	 and
although materials for their construction had to be obtained
by it and brought to the site, in purchasing those materials
it  was acting more or less in the capacity of an agent	 !or
the  Railway.	Accordingly  the High  Court  came  to	the-
finding that the contract between the parties was one entire
and indivisible contract for carrying out the works specifi-
ed in the agreement and that it did not envisage either	 the
sale  of the materials by the respondent to the Railway,  or
of the coach bodies as such; no sales-tax was therefore held
leviable on the transaction.
On appeal to this Court.
HELD  : The terms of the contract led to the only  inference
that  the  respondent was not to be the owner of  the  ready
coach bodies and that the property in those bodies vested in
the  Railway even during the process of	 construction.	 The
transaction was therefore clearly a works contract which did
not involve any sale. [547 G]
544
Patnaik	 & Company v. State of Orissa, [1965] 2 S.C.R.	782:
distinguished.



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 945 of 1965. Appeal by special leave from the judgment and order dated December 14, 1962 of the Gujarat High Court in Sales Tax Re- ference No. 16 of 1961.

N. S. Bindra and R. H. Dhebar, for the appellant. M. V. Goswami, for the respondent.

The Judgment of the Court was delivered by Bhargava, J. This appeal under special leave granted by this Court arises out of proceedings for assessment of sales-tax under the Bombay Sales Tax Act III of 1953. Messrs. Kailash Engineering Co. (hereinafter referred to as "the respondent") was an engineering concern having their workshop at Morvi on the meter gauge section of the Western Railway. They obtained a contract from the Western Railway Administration for construction of III class passenger coaches on certain conditions described as the conditions of tender. Under that contract which was reduced to writing and was described as an agreement, the respondent constructed three coaches and submitted a bill which was properly certified in accordance with the agreement by the Railway Administration on October 4, 1958. The net value of the work done by the respondent was certified at Rs. 1,22,035/-. After receipt of this money, the respondent wrote to the Additional Collector of Sales Tax requesting him under S. 27 of the Bombay Sales Tax Act, 1953, to hold that this was a works contract, and that the transaction, in respect of which the respondent received the money, did not amount to a sale, so that no sales-tax was payable under that Act. The Additional Collector held that two questions fell for determination before him:

(1) Whether the transaction covered by the bill dated 4th October, 1958, is a sale; and (2) if it is a sale, whether any tax is payable in respect of the same.

The Additional Collector answered both the questions in the affirmative against the respondent. The appeal before the Gujarat Sales Tax Tribunal failed; and thereupon, the respondent sought a reference to the High Court of Gujarat. The Tribunal referred the following question for the opinion of the High Court:-

"Whether on a proper construction of the agreement as a whole and its general conditions and specification, the work done and covered by Contract Certificates No. M/60(1)/B-PRTN, dated 4th October, 1958, for the perfor-
545
mance of the works of building, erecting and furnishing 3 B. G. Coaches over the chassis supplied by the Railway is a works contract not amounting to sale, or whether it is a transaction of sale."

The High Court answered the question in favour of the respondent, holding that the transaction was a works contract carried out by the respondent and did not amount to a sale. Consequently, this appeal has been brought up by the State of Gujarat challenging the correctness of the decision of the High Court.

The Tribunal, when dealing with the case, mentioned a few of the terms of the contract entered into between the respondent and the Western Railway Administration, and, though there was a provision in one of the clauses of the agreement that as soon as the plant and materials were brought on the site where the coaches were to be constructed, the ownership in them would vest in the Railway, the Tribunal held that the ownership in those materials never passed to the Railway because of the indication given by another clause which provided that on removal of contractor or on rescission of contract, the Railway Authorities would be entitled to take possession and retain all materials, tools, implements, machinery and buildings. On this basis, the Tribunal held that, from the general conditions of the contract, it appeared that the ownership of the coach bodies only passed to the Railway when completed and handed over to the Railway, so that the contract was for supply of coach bodies. It was on supply of these coach bodies that the respondent received the price of those bodies, and thus received the amount subjected to sales-tax as sale consideration for those bodies. The High Court, however, in its judgment, reproduced the preamble of the contract as well as a large number of clauses of it to show that in the contract, at every stage, it was clearly mentioned that the contract was for performance of work of building, erecting and furnishing coach bodies on Broad Gauge underframes which already belonged to the Railway. The terms of the contract showed that as soon as the materials were taken by the respondent to the site of construction of the coaches, the ownership in those materials vested in the Railway and all that the respondent had to do was to carry out the work of erecting and furnishing the coach bodies. When the coach bodies were ready, the property in them vested in the Railway automatically without any further transfer of rights in it to the Railway. In fact, the ownership in the ready coach bodies did not vest in the respondent at all. No doubt, the materials for building the' coach bodies had to be obtained by the respondent and brought to the site of construction, but the provision that the ownership in those materials would vest in the Railway as soon as those materials were brought to the site clearly indicated that the respondent, in purchasing those materials, was 546 acting more or less in the capacity of an agent for the Railway. While the materials were at site, the effect of vesting of their ownership in the Railway was that if they were destroyed or damaged, the risk had to be borne by the Railway, even though the Railway might have been entitled to reimburse itself, because those materials -and goods were in the custody of the respondent on behalf of the Railway. In fact, under clause 29, there was a specific provision for the contingency that the materials or plant may be lost, stolen, injured or destroyed by fire, tempest or otherwise. This special provision was to the effect that the liability of the contractor was not to be diminished in any way, nor was the Railway to be in any way answerable for loss or damage on the happening of such contingency. This special provision had to be made, because the ownership in the materials vested in the Railway, though the contractor was in actual physical possession of the materials and plant in order to carry out the works contract. It was for this reason that a specific provision had to be made that the contractor would be liable to the Railway if any such loss occurred.

Taking into account all the terms of the contract as a whole, the High Court came to the finding that the contract between the parties was one entire and indivisible contract for carrying out the works specified in full details in the agreement, and that it did not envisage either the sale of materials by the respondent to the Railway, or of the coach bodies as such.

In this connection, learned counsel for the appellant relied on the decision of this Court in Patnaik & Company v. State of Orissa.(1) In that particular case, the contract in question was for the supply of bus bodies, and it was held that when the bus bodies were supplied by the contractor and money received by him, it amounted to a sale. It, however, appears that the facts and circumstances, on the basis of which the Court gave that opinion, do not find place in the case, Three main circumstances were relied upon in that case for holding that the transaction amounted to a sale and not to a works contract. The first circumstance was that the bus bodies were, throughout the contract, spoken of as a unit or as a composite thing to be put on the chassis, and this composite body consisted not only of things actually fixed on the chassis but movable things like seat cushions, and other things which could be very easily detached. In the contract, with which we are concerned, the coach bodies are not separately described as units or components to be supplied by the respondent to the Railway. The language used in the contract everywhere describes the duty of the respondent to be that of constructing, erecting and furnishing coach bodies on the underframes supplied. At no stage does the contract mention that ready coach (1) [1965] 2 S.C.R. 782.

547

bodies were to be delivered by the respondent to the Railway. In fact, even during the process of construction of the coach bodies, the unfinished bodies in process of erection were treated, under the terms of the contract, as the property of the Railway.

The second circumstance found in that case was that if some work was not satisfactorily done and the body builder, on receipt of a written order, did not dismantle or replace the defective work or material at his own cost within seven days, the Controller was entitled to get the balance of the work done by another agency and recover the difference in cost from the body builder; and for this, purpose, the Controller was entitled to take delivery of the unfinished body. In the contract before us, as we have already mentioned in the preceding paragraph, the unfinished bodies of the coaches were from the earliest stage treated as the property of the Railway, and there was no question of ownership of the unfinished body passing to the Railway only after its seizure by it as was the case in the other contract in which the property in the unfinished body did. not pass to the Government till the unfinished body was seized.

The third circumstance taken into account in that case was the liability for the loss, if a fire took place and the bus bodies were destroyed or spoiled. In that case, there was a provision for insurance of the chassis, but there was no such provision regarding. insurance of bus bodies, and the Court inferred that till delivery was made, the bus bodies remained the property of the appellant on whom the loss would fall. On the other hand, in the contract with which we are concerned, the terms envisaged the property in the unfinished bodies vesting in the Railway, and since those unfinished bodies were to be in charge of the respondent during construction, a special provision had to be made making the respondent responsible for the loss and throwing upon the respondent the liability to reimburse the Railway for loss by fire, etc. Thus, the terms of the contract in this case are markedly different from those which came up for consideration in that case. Here, we find that all the terms of the contract lead to the only inference that the respondent was not to be the owner of the ready coach bodies and that the property in those bodies vested in the Railway even during the process of construction. This was, therefore, clearly a works contract which did not involve any sale. The decision given by the High Court was correct. The appeal fails and is dismissed with costs. R.K.P.S. Appeal dismissed.

548