State of Madhya Pradesh - Subsection

Section 5(b) in Madhya Pradesh Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement Mechanism and related matters of Wind and Solar generating stations) Regulations, 2018

(b)Deviation: For the purposes of Deviation settlement "amongst State Entities, the SLDC shall work out the 'Deviation Pool Accounts' comprising over-drawal/under-drawal and over-injection and under-injection for each State Entity corresponding to each Scheduling period in accordance with the provisions of these Regulations.