State of Rajasthan - Section

Section 21 in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016

21. Unscheduled Interchange Pricing.

- The payment settlement for mismatch between the schedule and the actual drawal/ injection in both intra-State and inter-State transactions by customers connected to transmission/ distribution network of the State licensees shall be governed by the pricing mechanism as specified below:
(i)Any under-injection with respect to the schedule approved by the SLDC by an open access customer shall be settled at higher of the applicable deviation rates as notified in CERC Deviation Settlement Mechanism Regulations 2014 amended from time to time or energy charge at the rate of Temporary Tariff applicable for HT (NDS) category as determined by the Commission from time to time;
(ii)Any over-injection upto 5% in a time block of 15 minutes and averaging upto 1% over a day with respect to the schedule approved by the SLDC by an open access customer shall be compensated at the deviation charge rate at frequency of 50 Hz. or applicable deviation charge rate (as notified in CERC Deviation Settlement Mechanism Regulations 2014 amended from time to time) whichever is less;
(iii)Any underdrawl with respect to the schedule approved by the SLDC by an open access consumer shall not be compensated and this underdrawl shall be considered to be attributable to the consumer;
(iv)Any over drawl with respect to the schedule approved by the SLDC by an open access customer who is not a consumer of Distribution Licensee of his area of supply shall be settled at higher of the applicable deviation rates (as notified in CERC Deviation Settlement Mechanism Regulations 2014 amended from time to time) or energy charge at rate of Temporary Tariff applicable for HT (NDS) category as determined by the Commission from time to time;
(v)Any over drawl with respect to the schedule approved by the SLDC, by an open access customer who is also a consumer of Distribution Licensee of his area of supply, shall be considered as the drawal from Discom and the open access consumer shall be required to pay charges for the excess capacity utilized computed in the manner specified in regulation 26 for the entire month equal to the same percentage of the fixed and energy charges by which percentage the excess demand has actually been availed during the month on the rates specified in the tariff orders in force. However, the excess capacity utilized up to 5% of capacity allocation occurring to the extent of two time blocks of 15 minutes each during a month shall be exempted.