Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Jharkhand High Court

M/S Hari Om Traders vs State Of Jharkhand & Ors on 15 February, 2017

Author: Aparesh Kumar Singh

Bench: Aparesh Kumar Singh

                     IN THE HIGH COURT OF JHARKHAND AT RANCHI
                                  W. P. (C) No.904 of 2012
                                                 ­­­­
                    M/s. Hari Om Traders, District­Ranchi....   Petitioner
                                                Versus
                    1. The State of Jharkhand
                    2. The Engineer in Chief, Rural Works Department,
                    Jharkhand, Ranchi
                    3. The Chief Engineer, Jharkhand State Rural
                    Road Development Authority, Ranchi
                    4. The Chief Engineer, Rural Engineering 
                    Organization, District­Ranchi
                    5. The Superintending Engineer, Rural Works
                    Circle, Chaibasa, District­Singhbhum West
                    6. The Executive Engineer, Rural Works
                    Department, District­Singhbhum East  . ...........   Respondents.
                                                ­­­
                    CORAM: HON'BLE MR. JUSTICE APARESH KUMAR SINGH
                                                ­­­
                    For the Petitioner                 :    Mr. Manoj Tandon, Advocate                
                    For the Respondents                :    J. C to A.G 
                                                ­­­

12/15.2.2017

Heard learned counsel for the petitioner and Respondent­State.

Petitioner was awarded work under Agreement no. 8/2008­09 under  PMGSY Package No. JH­0603, Phase­Vth, in the district of East Singhbhum  for execution of work relating to (i) Kadamdih to Marchagora­5.388 Km.; 

(ii)   Simuldanga   to   Betakocha­1.450   Km.   For   Agreement   Value   Rs.  1,68,55,687/­ .  Construction cost was Rs. 153,16,013.00 while Maintenance  cost was Rs. 15,39,674.00.   Agreement is dated 10th January, 2009.   Work  was to commence from 10th January, 2009 itself to be completed by 9th  January, 2010.  A similar nature of work was also awarded to the petitioner  under   Agreement   no.   06/2008­09   under   PMGSY     package   no.   JH­0605,  Phase­Vth,   in   the   same   district   for   construction   of   road   (i)   Jadugora  Musabani   road   to   Swaspur­2.028   Km.   (2)   Govindpur   Jadugora   road   to  Tilamura­2.680   Km.,   for   Agreement   Value   Rs.   1,26.90,863.00.   The  construction   cost   was   Rs.   1,16,67,130.00   while   Maintenance   cost   was  Rs. 10, 23,733.00.   Agreement is dated 16th May, 2008. Agreement was to  commence from the same date and to be completed by 15th May, 2009.  Both these agreements have been rescinded by the impugned order dated  15th May, 2010 bearing Memo nos. 974 and 975  issued by respondent no.  6,  Executive Engineer, Rural Works Department, District­Singhbhum East  invoking the terms and conditions of Clause­ 52.2, Sections­c, f, h and k  2. as respects Agreement no. 08/2008­09 and Clause­52.2, Sections­a, e and f  as regards agreement no. 06/2008­09 (Annexures­5 to writ petition and B &  C   to   counter   affidavit   respectively)     Dispute   Redressal   Mechanism   is  provided   under   Clause   24   of   the   agreement   (brought   on   record   by  supplementary affidavit dated 29th September, 2016) which however has  been   clarified   not   to   be   an   arbitration   Clause   as   per   Clause   25.1.  The  Dispute Redressal System  do provide a mechanism whereunder firstly it is  to   be   referred   to   competent   authority   and   thereafter   before   Standing  Empowered Committee if the amount appealed against the decision of the  competent   authority   is   in   excess   of   rupees   one   lakh.   Clause   52   of   the  agreement which contains the Termination Clause is quoted hereunder:

52.  Termination                52.1 The   Employer   may   terminate   the   Contract   if   the   Contractor causes a fundamental breach of the Contract. 52.2 Fundamental breaches of Contract shall include but shall  not be limited to, the following
a)   the   Contractor   stops   work   for   28   days   when   no   stoppage of work is shown on the current Programme   and   the   stoppage   has   not   been   authorized   by   the   Engineer;

b) the Contractor is declared as bankrupt or goes into   liquidation other than for approved reconstruction or  amalgamation; 

c)   the  Engineer   gives  Notice   that   failure   to   correct  a   particular Defect is a fundamental breach of Contract   and   the   Contractor   fails   to   correct   it   within   a   reasonable period of time determined by the Engineer;  

d) the Contractor does not maintain a Security, which   is required

e)   the  Contractor  has  delayed   the   completion   of  the  Works by the number of days for which the maximum   amount of liquidated damages can be paid, as defined   in clause 44.1

f)  the Contractor fails  to provide insurance cover as   required under clause 13;

g) if the Contractor, in the judgment of the Employer,   has engaged in the corrupt or fraudulent practice in   competing for or in executing the Contract.   For the  purpose   of   this   clause, "corrupt   practice"  means   the  offering, giving, receiving, or soliciting of any thing of   value to influence the action of a public official in the   procurement   process   or   in   Contract   execution.  

"Fraudulent   Practice"  means   a   misrepresentation   of   facts in order to influence a procurement process or   the   execution   of   a   contract   to   the   detriment   of   the  Employer   and   includes   collusive   practice   among   Bidders (prior to or after bid submission) designed to  establish   bid   process   at   artificial   non­competitive  levels and to deprive the Employer of the benefits of   free and open competition; 
3
h) if the Contractor has not completed at least thirty  percent of the value of construction Work required to   be completed after half of the completion period has  elapsed;
i) if the Contractor fails to set up a field laboratory   with   the   prescribed   equipment,   within   the   period   specified in the Contract Data and 
j) any other fundamental breaches as specified in the   Contract Data;
k)   if   the   Contractor   fails   to   deploy   machinery   and   equipment or personnel as specified in the Contract  Data at the appropriate time.

Termination   entails   consequences   which   are   enumerated   at  Clause­53 and other clauses thereof. 

Petitioner has also assailed the e­Procurement Notice i.e., Notice  Inviting Tender issued by respondent no. 3 by paper publication in a Daily  Newspaper     dated   5th   February,   2012.     By   interim   order   dated  10th   July,   2012,   respondents   were   restrained   from   proceeding   in   the  matter.  No fresh allotment of work has been made, therefore, in favour of  anyone during the pendency of the writ petition.  

Essentially,   challenge   to   impugned   action   is   based   upon   the  grounds of violation of principles of natural justice. Petitioner contends  that no notice or opportunity of hearing was given before termination of  the   contract.     Counsel   for   the   petitioner   has   relied   upon   a   judgment  rendered in the case of  Modi Projects Ltd., Ranchi & Ors. ­Vs.­ State of   Jharkhand   &   Ors.   reported   in  2012(3)   JLJR   60  in   support   of   his  contention. Statements made at para­15 of the writ petition to that effect  have   been   answered   by   the   respondent   at   para­   26   of   their   counter  affidavit referring to several letters no. 1663 dated 27th October, 2008; 1842  dated       14th   October,   2009,   129   dated   2nd   April,   2009,   239   dated   2nd  September, 2009; 147 dated 28th January, 2010, 326 dated 25th February,  2010     enclosed   as  Annexure­F   series.   Perusal   of   letters   at   Annexure­F  series however, shows that the petitioner has been repeatedly reminded of  abnormally slow progress of work and failure to complete the work within  the stipulated time. In fact, one letter dated 14.10.2009 bearing no. 1842  issued by the Respondent No. 6 conveys that on account of abnormally  4 slow   progress   of   work   and   failure   to   complete   the   work   within   the  stipulated   time,   the   said   Agreement   has   been   terminated   under  instruction of Higher Authorities as per Clauses­52.1, 52.2 (a), (e) and (f) of  General   Conditions   of   the   contract.  This   relates   to   the   Agreement   No.  06/2008­09.  The   impugned   letter   at   Annexure­5,   however,   convey   that  pursuant to the direction of Chief Engineer, Jharkhand State Rural Road  Development Authority contained in letter no. 1449 dated 08.04.2010, as  per the work programme submitted by the petitioner, construction of the  road was to be completed by 15.05.2010. Since the work was not found to  be completed by 15.05.2010, Agreement has been terminated invoking the  various Clauses under Clause 52.2. It therefore appears that after initial  termination   of   the   Agreement   of   the   petitioner,   as   per   Annexure­F,  petitioner was given some more time to complete the work till 15.05.2010.  Thereafter,   termination   has   been   effected.   However,   the   documents   at  Annexure­F series do not show that any notice to the petitioner to show­ cause as to why the Agreement be not terminated for failure to comply  with the terms and conditions of the Agreement and Instructions issued  by the Respondent Engineers, has been issued before passing the order of  termination. Petitioner and the Respondent both are at crossroads  on the  allegations   relating   to   non­completion   of   the   work   within   the   time  schedule. The execution of the work obviously involves performance of  reciprocal promises by the parties. That however is a question dependent  upon   the   facts,   which   may   be   disputed   between   the   parties   and   on  interpretation of terms and conditions of the Agreement. Therefore, in this  proceeding, no determination or observation can be made in that regard.

However, decision to terminate the Agreement with the petitioner,  does not appear to have been preceded by appropriate show­cause notice,  though   it   would   entail   serious   adverse   consequences.   Therefore   the  impugned order cannot be sustained in the eye of law on the grounds of  violation of principles of natural justice. 

5

Accordingly, the impugned order dated 15th May, 2010 is quashed.  Respondents shall take a fresh decision in the matter after due notice and  show­cause   to   the   petitioner   containing   specific   charges   and   also  enclosing  supporting  documents,  if   any,  thereto  so   that  petitioner   may  have an opportunity to respond before any fresh decision is taken. Since  the impugned decision has been quashed only on the grounds of violation  of   principles   of   natural   justice   by   remanding   the   matter   to   the  Respondent, Agreement as such does not stand revived for the present till  a fresh decision is taken by the respondent, in accordance with law. It goes  without   saying   that   parties   would   face   consequences   based   upon   the  decision to be taken by the respondent in accordance with law.

Accordingly, the  writ petition is allowed  in the  aforesaid  manner.  Consequently, I.A. No. 1595 of 2015 stands disposed of. 

(Aparesh Kumar Singh,J)  jk